AILoadmapAI gigawatts, campus by campus

Updates

What changed between weekly snapshots, then every dated step row by the day it was collected. Events are things that happened in the world; corrections and backfills are record maintenance and never count as market changes.

Snapshots · data version 2026-W41

One weekly snapshot so far (2026-W41, 2026-10-05). Each week's last build is kept as that week's snapshot; from the second week this section lists what changed campus by campus: first-power target, expected first power, energized, planned MW, status, steps past deadline, steps without a public date, equipment rows. Material changes (target moved three months or more, planned MW moved 10% or 100 MW, status changed, a required step gained a date, equipment with a named make) are marked.

2026-10-05 · 2 events · 4 record-maintenance rows across 6 campuses

CampusStepDateWhatSource
OpenAI Stargate New MexicoWater supply secured2026-09-17Emergency authorization to draw from the new well stands after the Supreme Court lifted its stay; permanent water rights still contested◐ source
Anthropic Barber LakeFinancing closed2026-09-15Cipher's Barber Lake contracted revenue above $9bn after a second ten-year lease commitment (reported September 2026)◐ source
Record maintenance · 4 rows (backfilled facts and corrections)
CampusStepDateWhatSource
OpenAI Stargate MilamFinancing closed2026-01-09OpenAI and SoftBank commit $1bn to SB Energy for the 1.2 GW Milam County site● source
Coreweave HeliosFinancing closed2025-08-15Galaxy closes a $1.4bn debt facility for the Helios campus◐ source
Anthropic Lake MarinerFinancing closed2026-06-30Fluidstack leases totalling 360 MW ($6.7bn contracted) with Google backstop; CB-5 expansion lease◐ source
Microsoft Narvik NorwayFinancing closed2026-05-11$790m project financing from ABN AMRO, DNB, Eksfin, Nordea and SEB, with an uncommitted accordion for a 115 MW expansion◐ source

2026-10-04 · 19 events · 266 record-maintenance rows across 61 campuses

CampusStepDateWhatSource
Microsoft Fairwater WisconsinGrid supply agreed2026-08-09PSC contract terms disputed◐ source
OpenAI Stargate New MexicoPermits in hand2026-08-23New Mexico Supreme Court stays the NMED air permit hearing and the emergency well authorization◐ source
OpenAI Stargate New MexicoPermits in hand2026-09-17Supreme Court lifts the stay; air permit hearing re-set for 2026-10-19, public comments due 2026-10-23◐ source
Meta PrometheusNew generation online2026-09-30Socrates South on-site gas plant complete (estimated Q3 2026)◐ source
OpenAI Stargate WisconsinGrid supply agreed2026-08-07PSC revokes completeness; ATC must restart the transmission application◐ source
Google Fort WayneFirst power2026-09-15First phase reported operational (September 2026)◐ source
Google Fort WaynePermits in hand2026-09-23Google seeks approval for 228 more backup generators at the Fort Wayne campus◐ source
Amazon RidgelandConstruction started2026-08-15Phase II: stormwater coverage issued for about 245 acres; construction estimated through August 2028 (Haskell)○ source
Crusoe Abilene ExpansionMajor equipment on site2026-09-25Crusoe drops plan for 29 Boom turbines● source
Anthropic Barber LakeSite secured2026-09-25Fluidstack lease extended to 300 MW and 20 years◐ source
Anthropic Barber LakeFirst power2026-09-30Phase 1 delivery target (168 MW)◐ source
CoreWeave Muskogee OKGrid supply agreed2026-08-01Polaris acquisition adds 440 MW OG&E service and an on-site substation● source
Meta KunaFirst power2026-09-03Serving traffic (Meta)● source
Nebius MantsalaSite secured2026-08-13Second Mäntsälä data center (up to 70 MW from 2027) announced; Caverion €15m substation due autumn 2027; site total 145 MW◐ source
Google Kansas City EastFirst power2026-08-01First power (Epoch)◐ source
Meta SarpyFirst power2026-08-02First power (Epoch)◐ source
Meta AikenFirst power2026-08-07First power (Epoch)● source
Microsoft-Nebius New JerseyPermits in hand2026-08-10City stop-work orders for the LNG tank (Aug 6) and the Bloom fuel cells (Aug 10); state air permit application withdrawn; generators reported running without permits◐ source
Microsoft-Nebius New JerseyPermits in hand2026-08-18Phase 2 approved● source
Record maintenance · 266 rows (backfilled facts and corrections)
CampusStepDateWhatSource
Microsoft Fairwater WisconsinSite secured2023-07-14Site work begins◐ source
Microsoft Fairwater WisconsinFirst power2026-04-16First power (Epoch)◐ source
Microsoft Fairwater WisconsinBuilding ready for IT2026-06-23First building complete◐ source
Microsoft Fairwater WisconsinBuilding ready for IT2026-06-23First Fairwater building fully operational (Microsoft); startup work began in April 2026◐ source
Microsoft Fairwater WisconsinFull build-out complete2028-05-13 planBuildings 3-11 estimated operational (Epoch)◐ source
Microsoft Fairwater WisconsinFull build-out complete2028-12-31 planSecond Fairwater facility under construction for 2028◐ source
Anthropic-Amazon New CarlisleSite secured2024-04-01Campus announced◐ source
Anthropic-Amazon New CarlisleFirst power2025-06-23First power (Epoch)◐ source
Anthropic-Amazon New CarlisleBuilding ready for IT2025-10-29Campus opened◐ source
Anthropic-Amazon New CarlisleSite secured2026-03-01South campus site prep and substation◐ source
Anthropic-Amazon New CarlisleFull build-out complete2028-03-17 planBuildings 19-32 estimated operational (Epoch)◐ source
OpenAI Stargate New MexicoSite secured2025-09-01Construction begins◐ source
OpenAI Stargate New MexicoSite secured2025-09-01Construction begins; $165bn industrial revenue bond approved◐ source
OpenAI Stargate New MexicoPermits in hand2026-01-15Air permit application filed for gas turbines and diesel (January 2026)◐ source
OpenAI Stargate New MexicoPermits in hand2026-04-27Power plan switched to a 2.45 GW Bloom fuel-cell microgrid (not yet built, no construction permit)○ source
OpenAI Stargate New MexicoPermits in hand2026-10-19 planNMED air-permit public hearing on the fuel-cell plan◐ source
OpenAI Stargate New MexicoNew generation online2026-12-31 planFuel-cell microgrid first block (announced initial operations)◐ source
OpenAI Stargate New MexicoMajor equipment on site2027-02-28 planNatural-gas pipeline feeding the microgrid in service (delayed from August 2026 per reporting on Oracle's force majeure notice)◐ source
OpenAI Stargate New MexicoFull build-out complete2028-12-31 planEstimated completion (Epoch)◐ source
Meta HyperionSite secured2024-12-20Campus announced (Richland Parish)● source
Meta HyperionGrid supply agreed2025-08-20LPSC approves Entergy plants, 500 kV line and substations● source
Meta HyperionPermits in hand2026-04-15LPSC fast-tracks seven more gas plants● source
Meta HyperionBuilding ready for IT2026-04-19Buildings 1 and 2 roofed, cooling at an advanced stage (Epoch timeline)◐ source
Meta HyperionSubstation and lines energized2026-12-01 planNew power stations in service for a 1.8 GW load at Holly Ridge (Epoch timeline note; data center not yet operational)◐ source
Meta HyperionNew generation online2028-06-30 planTwo Entergy combined-cycle units online (planned)● source
Meta HyperionNew generation online2029-06-30 planFranklin Farms 1,500 MW combined cycle online mid-2029 per Industrial Info (Entergy's groundbreaking release says late 2028; earlier date kept for the gate)◐ source
Meta HyperionNew generation online2029-12-31 planThird unit at Waterford online (planned)● source
Colossus 2Site secured2025-02-28Land clearing begins◐ source
Colossus 2First power2025-10-19First power (Epoch)◐ source
Colossus 2Permits in hand2026-03-10MDEQ air permit for 41 permanent turbines◐ source
Colossus 2Permits in hand2026-04-14NAACP and SELC file a Clean Air Act suit over 27 unpermitted turbines; MDEQ counted 46 turbines in May, 60 in June and 69 in July 2026◐ source
Colossus 2New generation online2027-06-30 planTurbine programme reaches 1.1 GW+ (Solaris, planned)◐ source
Colossus 2Permits in hand2027-12-31 planTemporary turbine permit expires◐ source
OpenAI Stargate ShackelfordSite secured2025-08-01Campus announced◐ source
OpenAI Stargate ShackelfordPermits in hand2025-11-15TCEQ air authorization for 210 VoltaGrid generators (700 MW) by emissions registration○ source
OpenAI Stargate ShackelfordConstruction started2025-12-15Groundbreaking (December 2025; TDLR window from 2025-09-26)○ source
OpenAI Stargate ShackelfordNew generation online2026-12-01 planOn-site microgrid first block (announced)◐ source
OpenAI Stargate ShackelfordFirst power2026-12-01 planFirst building delivery (announced)◐ source
OpenAI Stargate ShackelfordFirst power2027-08-15 planFirst power (Epoch estimate)◐ source
OpenAI Stargate ShackelfordFull build-out complete2028-05-11 planTDLR construction window ends (all buildings)○ source
OpenAI Stargate ShackelfordFull build-out complete2028-11-11 planBuild-out complete (Epoch estimate)◐ source
QTS Cedar RapidsSite secured2025-02-13Campus confirmed by Cedar Rapids and Alliant Energy● source
QTS Cedar RapidsGrid supply agreed2025-02-13Alliant Energy commits 1 GW at Big Cedar (161/69 kV lines, 345 kV proposed)● source
QTS Cedar RapidsConstruction started2025-04-01Ground broken on the first building (spring 2025)◐ source
QTS Cedar RapidsFirst power2026-11-15 planFirst power (Epoch estimate)● source
QTS Cedar RapidsBuilding ready for IT2026-12-15 planFirst phase complete (late 2026, QTS)◐ source
Meta PrometheusFirst power2025-10-14First power (Epoch)◐ source
Meta PrometheusFull build-out complete2028-07-01 planBuildings 22-27 estimated operational (Epoch)◐ source
GoodnightConstruction started2025-06-01Ground broken◐ source
GoodnightGrid supply agreed2026-01-09Net-metering application for Load 2 (260 MW) behind Goodnight Wind filed with the PUCT◐ source
GoodnightPermits in hand2026-03-01TCEQ air permit filed for a 933 MW on-site gas plant (no Google offtake)○ source
GoodnightGrid supply agreed2026-07-23PUCT order in Docket 59220 approves net metering with a 525.5 MW 30-minute curtailment obligation◐ source
GoodnightFirst power2027-03-15 planFirst power (Epoch estimate)◐ source
GoodnightFull build-out complete2027-10-01 planSix buildings operational (Epoch estimate)◐ source
OpenAI Stargate UAESite secured2025-05-22Stargate UAE announced◐ source
OpenAI Stargate UAEConstruction started2025-10-16First phase under construction, 5,000 workers on site◐ source
OpenAI Stargate UAEMajor equipment on site2025-12-05First deliveries of critical mechanical systems on site◐ source
OpenAI Stargate UAEBuilding ready for IT2026-09-30 planFirst 200 MW phase complete (Q3 2026, Khazna)◐ source
OpenAI Stargate UAEFirst power2026-12-31 planFirst 200 MW (announced)◐ source
OpenAI Stargate UAEFull build-out complete2028-01-01 plan1 GW operational (Epoch estimate)◐ source
OpenAI Stargate MichiganSite secured2025-10-30Announced as the largest investment in Michigan history◐ source
OpenAI Stargate MichiganGrid supply agreed2025-12-18MPSC approves DTE 1.4 GW contracts◐ source
OpenAI Stargate MichiganPermits in hand2026-02-15Construction allowed ahead of the final air-quality permit; wetlands permits◐ source
OpenAI Stargate MichiganConstruction started2026-03-01Construction start (planned early 2026)◐ source
OpenAI Stargate MichiganConstruction started2026-04-25Major construction underway; financing secured◐ source
OpenAI Stargate MichiganConstruction started2026-06-01Construction equipment and fencing on the Saline Township site◐ source
OpenAI Stargate MichiganFull build-out complete2028-12-31 planCompletion (projected Q4 2028)◐ source
OpenAI Stargate WisconsinSite secured2025-12-01Groundbreaking● source
OpenAI Stargate WisconsinGrid supply agreed2025-12-15ATC transmission application found complete by the PSC (December)◐ source
OpenAI Stargate WisconsinGrid supply agreed2026-12-15 planPSC decision on the refiled ATC line (expected Q4 2026)◐ source
OpenAI Stargate WisconsinSubstation and lines energized2027-12-15 planATC line in service (late 2027)◐ source
OpenAI Stargate WisconsinNew generation online2027-12-31 planWe Energies renewables and storage for the campus (planned)● source
OpenAI Stargate WisconsinGrid supply agreed2028-06-30 planATC transmission line (proposed)● source
OpenAI Stargate WisconsinFirst power2028-06-30 planCampus completion now seen no earlier than mid-2028 (analysis)○ source
OpenAI Stargate WisconsinFull build-out complete2028-12-31 planFour buildings complete (announced)● source
OpenAI Stargate WisconsinFull build-out complete2028-12-31 planLighthouse campus (four buildings) projected complete Q4 2028; 70% of power from solar, wind and storage◐ source
Google Fort WayneConstruction started2024-04-26Ground broken● source
Google Fort WayneGrid supply agreed2026-04-30IURC approves the Google-I&M demand-response arrangement◐ source
Google Fort WayneFirst power2026-12-01 planFirst power (Epoch estimate; city reports phase 1 operational)● source
Google Fort WayneFull build-out complete2028-06-23 planBuilding 6 estimated operational (Epoch)● source
OpenAI Stargate MilamNew generation online2024-10-01Adjacent Orion Solar Belt (900 MWdc) in commercial operation◐ source
OpenAI Stargate MilamConstruction started2025-10-15Ground broken (October 2025)◐ source
OpenAI Stargate MilamSite secured2026-01-09SB Energy partnership and $1bn investment◐ source
OpenAI Stargate MilamBuilding ready for IT2026-10-31 planFirst building delivery (regulatory filings)◐ source
OpenAI Stargate MilamBuilding ready for IT2026-10-31 planFirst building delivered by October 2026 (regulatory filings cited by Epoch)◐ source
OpenAI Stargate MilamFull build-out complete2028-12-31 planCompletion (projected Q4 2028)◐ source
OpenAI Stargate MilamFull build-out complete2028-12-31 plan1.2 GW campus complete (Q4 2028)◐ source
OpenAI Stargate AbileneSite secured2024-05-31Site work begins◐ source
OpenAI Stargate AbileneBuilding ready for IT2025-09-26First two buildings live (200+ MW)◐ source
OpenAI Stargate AbileneSite secured2026-03-09Oracle and OpenAI drop the planned 600 MW expansion (financing terms); the eight-building 1.2 GW campus continues, phase 2 due by end-2026◐ source
OpenAI Stargate AbileneMajor equipment on site2026-06-30On-site turbine fleet beyond the first 360 MW (announced, >1 GW of turbines)◐ source
OpenAI Stargate AbileneFull build-out complete2026-11-01 planBuildings 5-8 estimated operational (Epoch)◐ source
Amazon RidgelandGrid supply agreed2024-03-08Entergy Mississippi large-customer agreement◐ source
Amazon RidgelandSite secured2026-04-09Ridgeland expansion announced ($12bn)◐ source
Amazon RidgelandFirst power2026-05-15First power (Epoch)◐ source
Amazon RidgelandFull build-out complete2028-08-31 planPhase II construction complete (estimate from the stormwater filing)○ source
Amazon RidgelandFull build-out complete2028-09-29 planBuildings 6-14 estimated operational (Epoch)◐ source
Amazon Madison Mega SiteSite secured2024-01-24AWS $10bn Mississippi investment announced● source
Amazon Madison Mega SiteGrid supply agreed2024-03-08Entergy Mississippi large-customer agreement● source
Amazon Madison Mega SiteFirst power2025-06-23First power (Epoch)● source
Amazon Madison Mega SiteFull build-out complete2028-03-15 planBuildings 8-12 estimated operational (Epoch)● source
Crusoe Abilene ExpansionPermits in hand2025-01-22TCEQ standard permit for 360 MW of turbines (ten units) at the existing campus◐ source
Crusoe Abilene ExpansionSite secured2026-03-27Campus announced● source
Crusoe Abilene ExpansionConstruction started2026-03-27Land clearing and site preparation underway● source
Crusoe Abilene ExpansionPermits in hand2026-07-15Major TCEQ permit filed for 41 turbines (about 1.4 GW) and 18 diesel gensets; contested, not approved◐ source
Crusoe Abilene ExpansionFirst power2027-06-30 planFirst building energized (announced)● source
Crusoe Abilene ExpansionFirst power2027-09-17 planFirst power (Epoch estimate)● source
Microsoft Fairwater AtlantaFirst power2025-10-14First building online (about 340 MW IT)◐ source
Microsoft Fairwater AtlantaSite secured2025-12-01QTS East campus rezoned (313 acres)◐ source
Microsoft Fairwater AtlantaPermits in hand2026-03-01Fayetteville data-center prohibition takes effect◐ source
Coreweave HeliosSite secured2025-08-15$1.4bn project financing closed◐ source
Coreweave HeliosGrid supply agreed2026-01-15ERCOT approves 830 MW large-load interconnection◐ source
Coreweave HeliosFirst power2026-06-30Phase I (133 MW IT) delivered, rent starts Q2 2026◐ source
Coreweave HeliosFull build-out complete2029-01-01 planPhase II at full capacity (Epoch estimate)◐ source
DayOne NusajayaFirst power2024-12-31First power (Epoch)◐ source
DayOne NusajayaFirst power2026-01-30390 MW in service across Johor (DayOne)◐ source
Meta Bowling GreenSite secured2025-04-09Data center announced ($800m)◐ source
Meta Bowling GreenPermits in hand2025-11-05Apollo plant filed with the Ohio Power Siting Board (letter-of-notification track)● source
Meta Bowling GreenPermits in hand2026-02-03OPSB authorizes the 350 MW Apollo gas plant (6 recip engines, 21 turbines, 120 MW storage) without hearings● source
Meta Bowling GreenNew generation online2026-02-09Apollo on-site gas plant construction starts◐ source
Meta Bowling GreenFirst power2027-06-30 planPartial energization from Apollo (planned mid-2027)◐ source
Meta Bowling GreenNew generation online2027-12-31 planApollo full operation, campus at full capacity (planned)◐ source
DayOne KempasFirst power2026-01-22First power (Epoch)◐ source
CoreWeave Ellendale NDConstruction started2022-09-08Construction starts◐ source
CoreWeave Ellendale NDFirst power2025-10-27First 50 MW ready for service◐ source
CoreWeave Ellendale NDFirst power2025-11-24Building 1 fully energized (100 MW)◐ source
CoreWeave Ellendale NDFirst power2026-07-01Building 2 phase 1 ready (75 MW)◐ source
CoreWeave Ellendale NDBuilding ready for IT2027-06-01 planFull 400 MW (Epoch estimate)◐ source
Anthropic Lake MarinerSite secured2025-08-14Fluidstack leases 378 MW critical IT● source
Anthropic Lake MarinerFirst power2026-05-31First power (Epoch)● source
Anthropic Lake MarinerFirst power2026-06-30CB-3 delivered (102 MW revenue-generating)● source
Anthropic Lake MarinerBuilding ready for IT2026-07-05CB-3 delivered; 102 MW of revenue-generating IT capacity at Lake Mariner● source
Anthropic Lake MarinerBuilding ready for IT2026-12-31 planCB-4 phased delivery (H2 2026)● source
Anthropic Lake MarinerFull build-out complete2026-12-31 planCB-5 (160 MW, Fluidstack) due online H2 2026; contracted IT load 360 MW◐ source
Anthropic Lake MarinerBuilding ready for IT2027-03-31 planCB-5 phased delivery (now early 2027; announced H2 2026)● source
Meta MontgomerySite secured2024-05-01Data center announced (May 2024)◐ source
Meta MontgomeryFirst power2026-06-18First power (Epoch)◐ source
Meta MontgomeryFull build-out complete2027-02-23 planCampus estimated complete (Epoch)◐ source
STACK Infrastructure NVA02First power2024-10-01First power of the tracked expansion (Epoch)● source
STACK Infrastructure NVA02Full build-out complete2028-01-01 planBuild-out complete (Epoch estimate)● source
Colossus 1Construction started2024-04-24Construction starts in a former Electrolux plant◐ source
Colossus 1First power2024-08-11First training workload (35 MW)◐ source
Colossus 1Permits in hand2025-07-02Air permit for gas turbines (Shelby County, July 2025)◐ source
Colossus 1Substation and lines energized2025-11-07Third MLGW substation expected to power the building◐ source
AWS New AlbanyFirst power2024-12-01First power (Epoch)◐ source
AWS New AlbanyGrid supply agreed2025-07-01PUCO approves AEP Ohio data-center tariff (July 2025)◐ source
AWS New AlbanyFull build-out complete2027-07-01 planBuild-out complete (Epoch estimate)◐ source
QTS Eagle MountainPermits in hand2025-02-04Development agreement amended to allow on-site generation◐ source
QTS Eagle MountainPermits in hand2025-02-04Development agreement amended to allow on-site generation (200 MW gas plant approved later)◐ source
QTS Eagle MountainGrid supply agreed2025-09-01Rocky Mountain Power supply secured; QTS funds the infrastructure◐ source
QTS Eagle MountainConstruction started2025-10-01Construction starts (fall 2025)◐ source
QTS Eagle MountainBuilding ready for IT2026-04-17Building 3 topped out● source
QTS Eagle MountainFirst power2026-12-31 planFirst power (Epoch estimate)◐ source
QTS Eagle MountainFull build-out complete2027-07-01 planBuild-out complete (Epoch estimate)◐ source
Google LincolnFirst power2026-05-12First power (Epoch)◐ source
Google LincolnFull build-out complete2027-10-01 planBuild-out complete (Epoch estimate)◐ source
CoreWeave Denton TXFirst power2025-05-31First power (Epoch)◐ source
CoreWeave Denton TXSite secured2025-10-30CoreWeave-Core Scientific merger rejected by shareholders◐ source
CoreWeave Denton TXFull build-out complete2027-05-31 planFull conversion (Epoch estimate; planned 2027)◐ source
Google Cedar RapidsConstruction started2025-06-01Excavation and cranes across the site (summer 2025)◐ source
Google Cedar RapidsSite secured2025-06-04Google confirmed at Big Cedar● source
Google Cedar RapidsGrid supply agreed2025-06-04Alliant Energy announces the Google project at Big Cedar (utility-owned park with 1 GW)● source
Google Cedar RapidsFirst power2026-12-31 planFirst power (Epoch estimate)● source
Google Cedar RapidsBuilding ready for IT2026-12-31 planCurrent phase complete (2026)◐ source
QTS Richmond 3Grid supply agreed2024-08-29Dominion warns of up to seven-year waits for new large loads◐ source
QTS Richmond 3First power2026-02-13First power (Epoch)◐ source
QTS Richmond 3Full build-out complete2027-02-13 planBuild-out complete (Epoch estimate)◐ source
Start Campus Sines Data CampusGrid supply agreed2024-08-07REN raises grid allocation to 1.2 GW● source
Start Campus Sines Data CampusConstruction started2026-02-15SIN02 (up to 240 MW) construction starts; first customers expected mid-2027◐ source
Start Campus Sines Data CampusFirst power2026-04-03First power of the tracked expansion (Epoch)● source
Start Campus Sines Data CampusFull build-out complete2027-09-30 planTracked phase complete (Epoch estimate)● source
Start Campus Sines Data CampusFull build-out complete2030-12-31 planSix buildings complete (announced)● source
Stream PhoenixFirst power2026-05-01First power of the tracked expansion (Epoch)◐ source
Stream PhoenixBuilding ready for IT2029-12-31 planPhoenix IV (planned 2029)◐ source
Meta Los LunasConstruction started2025-04-01Phase 3 groundbreaking (spring 2025)◐ source
Meta Los LunasFirst power2026-03-01First power of the AI expansion (Epoch)◐ source
Meta Los LunasNew generation online2026-12-31 planPNM solar-plus-storage, first tranche (planned)◐ source
Meta Los LunasNew generation online2027-12-31 planPNM solar-plus-storage, second tranche (planned)◐ source
Meta Los LunasNew generation online2030-12-31 planXGS geothermal 150 MW (planned)◐ source
OpenAI Stargate LordstownSite secured2025-09-23Site announced; ground broken● source
OpenAI Stargate LordstownGrid supply agreed2025-09-23Existing plant substation provides grid supply (no new interconnection reported)◐ source
OpenAI Stargate LordstownConstruction started2025-10-01Site preparation begins◐ source
OpenAI Stargate LordstownBuilding ready for IT2026-07-30Roofing mostly in place, no building operational (imagery)◐ source
OpenAI Stargate LordstownConstruction started2026-09-30 planData center foundation work expected Q3 2026; Epoch imagery shows cleared land but no large-scale construction◐ source
OpenAI Stargate LordstownFirst power2027-03-01 planFirst power (Epoch estimate)● source
Meta CheyenneSite secured2024-07-08Data center announced● source
Anthropic Barber LakeSite secured2025-09-01168 MW lease signed◐ source
Anthropic Barber LakeSite secured2025-11-1239 MW expansion signed◐ source
Meta CheyenneFirst power2026-07-25First power (Epoch)● source
Anthropic Barber LakeFirst power2026-12-30 planFirst power (Epoch estimate)◐ source
Anthropic Barber LakeFull build-out complete2027-01-31 planPhase 2 delivery target (39 MW)◐ source
Meta CheyenneFull build-out complete2027-02-15 planBuild-out complete (Epoch estimate)● source
Meta CheyenneFirst power2027-03-31 planOnline in 2027 per Meta / Cheyenne LEADS (placeholder end of Q1)● source
Anthropic Barber LakeBuilding ready for IT2027-03-31 planData halls delivered to Fluidstack in phases from Q4 2026 through Q1 2027 (slightly later than planned); a second ten-year lease by an AI lab from Q4 2026◐ source
Meta TempleConstruction started2022-04-01Construction starts (spring 2022)◐ source
Meta TempleConstruction started2022-12-15Construction paused for AI redesign◐ source
Meta TempleConstruction started2023-10-01Construction resumes◐ source
Meta JeffersonvilleSite secured2024-01-25Data center announced; construction starts● source
Meta RosemountSite secured2024-03-14Data center announced for 2026◐ source
Meta TempleFirst power2025-12-09First power (Epoch)◐ source
Meta JeffersonvilleFirst power2026-06-04First power (Epoch)● source
Meta RosemountFirst power2026-06-19First power (Epoch)◐ source
AWS BerwickSite secured2024-03-04AWS buys the Cumulus campus ($650m)◐ source
AWS BerwickGrid supply agreed2024-11-01FERC rejects co-location interconnection agreement◐ source
AWS BerwickGrid supply agreed2025-04-15FERC upholds the rejection on rehearing◐ source
AWS BerwickFirst power2025-09-09First power (Epoch)◐ source
AWS BerwickGrid supply agreed2026-05-31Switch to front-of-meter supply after transmission work (targeted spring 2026)◐ source
AWS BerwickNew generation online2029-12-31 plan840-1,200 MW contracted from Susquehanna◐ source
AWS BerwickNew generation online2032-12-31 plan1,680-1,920 MW contracted◐ source
Google Red OakFirst power2025-08-25First power (Epoch)◐ source
Google Red OakBuilding ready for IT2025-11-14First building confirmed operational◐ source
Google Red OakFull build-out complete2026-12-01 planBuild-out complete (Epoch estimate)◐ source
CoreWeave Muskogee OKConstruction started2024-11-15Ground broken (November 2024)◐ source
CoreWeave Muskogee OKGrid supply agreed2024-11-15OG&E service for the 100 MW site at groundbreaking● source
CoreWeave Muskogee OKSubstation and lines energized2026-05-3170 MW building in final testing and commissioning (Q2 2026)● source
CoreWeave Muskogee OKFirst power2026-06-3070 MW building delivery (planned Q2 2026)◐ source
CoreWeave Muskogee OKFirst power2026-12-31 planFirst power (Epoch estimate)◐ source
CoreWeave Muskogee OKFull build-out complete2027-12-31 planSecond 82.5 MW building initial delivery (Q4 2027)◐ source
Meta KunaSite secured2022-02-15Kuna data center announced● source
Meta KunaConstruction started2022-12-15Construction paused for AI redesign● source
Meta KunaConstruction started2023-10-01Construction resumes with the AI design● source
Meta HuntsvilleSite secured2022-06-15Expansion announced◐ source
Meta HuntsvilleConstruction started2022-12-20Expansion paused for AI redesign◐ source
Meta HuntsvilleFirst power2026-03-04First power of the expansion (Epoch)◐ source
Nebius MantsalaSite secured2024-10-08Expansion to 75 MW announced◐ source
Nebius MantsalaBuilding ready for IT2026-03-3175 MW complete (early 2026)◐ source
Nebius MantsalaGrid supply agreed2027-10-31 plan70 MW substation for the second site (autumn 2027)◐ source
Nebius MantsalaFirst power2027-12-31 planSecond Mäntsälä site first capacity (planned 2027)◐ source
Meta Eagle MountainFirst power2021-07-01Campus live◐ source
Meta Eagle MountainFirst power2025-12-07First power of the expansion (Epoch)◐ source
Vantage TX1First power2026-02-15TX11 first power (Epoch)◐ source
Vantage TX1Full build-out complete2027-08-31 planTX12 estimated operational (Epoch)◐ source
Google Kansas City EastSite secured2026-02-12Second Kansas City campus (Project Mica) confirmed◐ source
Google MidlothianConstruction started2026-01-15Building 5 ($880m, 288,000 sq ft) construction begins◐ source
Google MidlothianFull build-out complete2027-02-28 planBuilding 5 completion targeted February 2027◐ source
CoreWeave Lancaster Greenfield siteSite secured2025-07-15Data center announced◐ source
CoreWeave Lancaster Greenfield siteGrid supply agreed2025-07-15PPL Electric supply with about $200m of upgrades and two on-site substations○ source
Microsoft Narvik NorwaySite secured2025-09-17Microsoft $6.2bn capacity agreement◐ source
CoreWeave Lancaster Greenfield sitePermits in hand2025-12-01Demolition permits granted for phase 1; building permits staged○ source
CoreWeave Lancaster Greenfield siteConstruction started2026-01-15Turner-Wohlsen JV construction underway◐ source
Microsoft Narvik NorwaySite secured2026-05-11$790m project financing◐ source
Microsoft Narvik NorwayGrid supply agreed2026-05-26Vattenfall renewable PPA signed for phase 1 (2027-2031)● source
Microsoft Narvik NorwayConstruction started2026-06-01About 350 workers on site (TIME)◐ source
Microsoft Narvik NorwayFirst power2026-12-31 planFirst staged deliveries (planned 2026)◐ source
Microsoft Narvik NorwayNew generation online2027-01-01 planVattenfall renewable PPA covers 2027-2031 for phase 1● source
CoreWeave Lancaster Greenfield siteFirst power2027-06-30 planFirst phase (Epoch estimate; announced summer 2027)◐ source
Microsoft Narvik NorwayFirst power2027-06-30 planOperations set to commence in 2027○ source
Microsoft Narvik NorwayFull build-out complete2027-12-31 planRubin GPU capacity delivered (planned 2027)◐ source
Meta SarpySite secured2022-07-28Springfield expansion announced◐ source
Meta AikenSite secured2024-08-29Data center announced for spring 2027● source
Microsoft-Nebius New JerseySite secured2025-03-06Site announced; DataOne colocation agreement● source
Microsoft-Nebius New JerseySite secured2025-09-08Microsoft capacity agreement● source
Microsoft-Nebius New JerseyFirst power2026-04-15First power (Epoch)● source
Microsoft-Nebius New JerseyPermits in hand2026-07-08Revised site plan with 328 MW on-site fuel cells● source
EcoDataCenter 2Construction started2025-09-15Ground broken● source
EcoDataCenter 2Grid supply agreed2025-09-15250 MW available at launch (up to 600 MW), per EcoDataCenter● source
EcoDataCenter 2Site secured2026-02-15Mistral AI €1.2bn long-term commitment for an AI data center at Borlänge; first facilities 2027, 250 MW first phase◐ source
EcoDataCenter 2First power2027-06-30 planFirst power (Epoch estimate; announced early 2027)● source
EcoDataCenter 2Building ready for IT2027-06-30 planFirst phase complete (mid-2027)◐ source
EcoDataCenter 2Full build-out complete2028-06-30 planPhase complete (Epoch estimate)● source
Nscale KeflavikSite secured2025-11-1515 MW lease at Verne◐ source
Nscale KeflavikFirst power2026-04-23First phase complete (Epoch)◐ source
Nscale KeflavikFull build-out complete2026-12-31 planFull deployment (planned 2026)◐ source
Meta GallatinConstruction started2020-01-01Construction starts◐ source
Meta GallatinConstruction started2022-12-15Meta pauses build for GPU redesign◐ source
Meta GallatinFirst power2024-11-14Starts serving traffic◐ source