AILoadmapAI gigawatts, campus by campus

Updates

The data is refreshed about once a month. What changed since the previous update, then every dated step row by the day it was collected. Events are things that happened in the world; corrections and backfills are record maintenance and never count as market changes.

Changes since 2026-10-05 · data version 2026-W45 · compared with 2026-W41 (2026-10-05)

12 material changes of 23.

CampusWhat changedFromTo
OpenAI Stargate Abilenestatusbuildingoperationalmaterial
Bridge Data Centres MY06campus—addedmaterial
Meta Aikenplanned MW69129material
Meta Gallatinplanned MW087material
Meta Gallatinstatusplannedoperationalmaterial
YTL Green Data Center Park Kulaiplanned MW6001200material
Campus AI Paris (Fouju)steps without a dateBuilding ready for IT, Grid supply agreed, Substation and lines energizedBuilding ready for IT, Substation and lines energizedmaterial
Nscale Loughton AI Campusfirst-power target2026-12-312032-12-31material
Nscale Loughton AI Campussteps without a dateBuilding ready for IT, Grid supply agreed, Substation and lines energizedBuilding ready for IT, Grid supply agreedmaterial
IREN Sweetwater Hubcampus—addedmaterial
Meta El Pasocampus—addedmaterial
AWS Comanche Peakcampus—addedmaterial
OpenAI Stargate Abileneplanned MW843824
Huawei Horingerfirst-power target2025-06-012025-06-11
Huawei Horingerexpected first power2025-06-012025-06-11
Huawei Horingerplanned MW346.4351.1
Huawei Wuhuplanned MW457453
Start Campus Sines Data Campusequipment rows01
QTS Cedar Rapidsexpected first power2026-11-152026-12-31
Campus AI Paris (Fouju)first-power target2028-06-302028-03-31
Campus AI Paris (Fouju)expected first power2028-06-302028-03-31
Nscale Loughton AI Campusexpected first power2027-03-312032-12-31
Nscale Loughton AI Campuslate stepsnoneSubstation and lines energized

2026-11-09 · 0 events · 3 record-maintenance rows across 1 campuses

Record maintenance · 3 rows (backfilled facts and corrections)
CampusStepDateWhatSource
IREN Sweetwater HubSubstation and lines energized2026-05-01Sweetwater 1 high-voltage substation energized and connected to ERCOT (announced 2026-05-01)◐ source
IREN Sweetwater HubConstruction started2026-09-08300 MW of gross data center capacity reported under construction◐ source
IREN Sweetwater HubFirst power2027-12-31 plan300 MW gross targeted for delivery in Q4 2027◐ source

2026-11-08 · 6 events · 15 record-maintenance rows across 6 campuses

CampusStepDateWhatSource
OpenAI Stargate New MexicoPermits in hand2026-10-02Retired federal judge James Browning appointed air-permit hearing officer after the previous officer recused◐ source
OpenAI Stargate New MexicoPermits in hand2026-10-27Hearing officer denies motion to dismiss the revised permit application, with operation capped at 1,600 MW (reported 2026-10-27)◐ source
OpenAI Stargate New MexicoPermits in hand2026-11-052026-12-07 air-permit hearing vacated on a joint NMED and developer motion; 2026-11-23 decision deadline waived; no new date set◐ source
Colossus 2Permits in hand2026-08-03Agreed order with MDEQ sets removal of all 69 temporary mobile turbines, by July 2027 on the company schedule (reported 2026-08-03)◐ source
Nscale Loughton AI CampusSubstation and lines energized2032-12-31 planPlaceholder: grid power reported as not sufficient until the early to mid-2030s; Nscale is exploring alternative power◐ source
Nscale Loughton AI CampusFirst power2032-12-31 planPlaceholder: first power follows the reported grid date unless on-site power is added◐ source
Record maintenance · 15 rows (backfilled facts and corrections)
CampusStepDateWhatSource
Meta Sturgeon CountyFinancing closed2026-07-02Pembina, Morgan Stanley Infrastructure Partners and Kineticor take final investment decision on the 932 MW Greenlight gas plant, startup targeted H2 2030◐ source
Meta Sturgeon CountySite secured2026-07-08Campus announced (reported)◐ source
Meta Sturgeon CountyConstruction started2026-07-08Construction start (reported)◐ source
Meta Sturgeon CountyFirst power2028-12-31 planFirst phase online (announced plan)◐ source
Campus AI Paris (Fouju)Site secured2025-02-06France-UAE AI partnership announced, the origin of the campus● source
Campus AI Paris (Fouju)Grid supply agreed2026-01-26RTE and Campus IA sign the accelerated "Fast Track" grid connection contract● source
Campus AI Paris (Fouju)Permits in hand2026-07-29Prefectoral orders grant the environmental authorizations for Campus AI and RTE and let operators run DC1, DC2 and DC4● source
Campus AI Paris (Fouju)Permits in hand2026-08-28Phase 1 building permit obtained● source
Campus AI Paris (Fouju)Construction started2026-09-15 planPhase 1 works scheduled to start in September 2026 (start not independently confirmed)● source
Campus AI Paris (Fouju)First power2028-03-31 planPhase 1 delivery estimated early 2028: first three data centers● source
Bell AI Fabric SherwoodSite secured2026-03-16300 MW campus announced by Bell and the Government of Saskatchewan● source
Bell AI Fabric SherwoodPermits in hand2026-04-20RM of Sherwood council approves the development agreement◐ source
Bell AI Fabric SherwoodConstruction started2026-06-01Construction start (reported)◐ source
Bell AI Fabric SherwoodFirst power2027-06-30 planFirst stage expected in the first half of 2027◐ source
Nscale Loughton AI CampusSite secured2025-09-16Campus announced with Microsoft as anchor◐ source

2026-10-05 · 2 events · 4 record-maintenance rows across 6 campuses

CampusStepDateWhatSource
OpenAI Stargate New MexicoWater supply secured2026-09-17Emergency authorization to draw from the new well stands after the Supreme Court lifted its stay; permanent water rights still contested◐ source
Anthropic Barber LakeFinancing closed2026-09-15Cipher's Barber Lake contracted revenue above $9bn after a second ten-year lease commitment (reported September 2026)◐ source
Record maintenance · 4 rows (backfilled facts and corrections)
CampusStepDateWhatSource
OpenAI Stargate MilamFinancing closed2026-01-09OpenAI and SoftBank commit $1bn to SB Energy for the 1.2 GW Milam County site● source
Coreweave HeliosFinancing closed2025-08-15Galaxy closes a $1.4bn debt facility for the Helios campus◐ source
Anthropic Lake MarinerFinancing closed2026-06-30Fluidstack leases totalling 360 MW ($6.7bn contracted) with Google backstop; CB-5 expansion lease◐ source
Microsoft Narvik NorwayFinancing closed2026-05-11$790m project financing from ABN AMRO, DNB, Eksfin, Nordea and SEB, with an uncommitted accordion for a 115 MW expansion◐ source

2026-10-04 · 19 events · 266 record-maintenance rows across 61 campuses

CampusStepDateWhatSource
Microsoft Fairwater WisconsinGrid supply agreed2026-08-09PSC contract terms disputed◐ source
OpenAI Stargate New MexicoPermits in hand2026-08-23New Mexico Supreme Court stays the NMED air permit hearing and the emergency well authorization◐ source
OpenAI Stargate New MexicoPermits in hand2026-09-17Supreme Court lifts the stay; air permit hearing re-set for 2026-10-19, public comments due 2026-10-23◐ source
Meta PrometheusNew generation online2026-09-30Socrates South on-site gas plant complete (estimated Q3 2026)◐ source
OpenAI Stargate WisconsinGrid supply agreed2026-08-07PSC revokes completeness; ATC must restart the transmission application◐ source
Google Fort WayneFirst power2026-09-15First phase reported operational (September 2026)◐ source
Google Fort WaynePermits in hand2026-09-23Google seeks approval for 228 more backup generators at the Fort Wayne campus◐ source
Amazon RidgelandConstruction started2026-08-15Phase II: stormwater coverage issued for about 245 acres; construction estimated through August 2028 (Haskell)○ source
Crusoe Abilene ExpansionMajor equipment on site2026-09-25Crusoe drops plan for 29 Boom turbines● source
Anthropic Barber LakeSite secured2026-09-25Fluidstack lease extended to 300 MW and 20 years◐ source
Anthropic Barber LakeFirst power2026-09-30Phase 1 delivery target (168 MW)◐ source
CoreWeave Muskogee OKGrid supply agreed2026-08-01Polaris acquisition adds 440 MW OG&E service and an on-site substation● source
Meta KunaFirst power2026-09-03Serving traffic (Meta)● source
Nebius MantsalaSite secured2026-08-13Second Mäntsälä data center (up to 70 MW from 2027) announced; Caverion €15m substation due autumn 2027; site total 145 MW◐ source
Meta AikenFirst power2026-08-07First power (Epoch)● source
Google Kansas City EastFirst power2026-08-01First power (Epoch)◐ source
Meta SarpyFirst power2026-08-02First power (Epoch)◐ source
Microsoft-Nebius New JerseyPermits in hand2026-08-10City stop-work orders for the LNG tank (Aug 6) and the Bloom fuel cells (Aug 10); state air permit application withdrawn; generators reported running without permits◐ source
Microsoft-Nebius New JerseyPermits in hand2026-08-18Phase 2 approved● source
Record maintenance · 266 rows (backfilled facts and corrections)
CampusStepDateWhatSource
Microsoft Fairwater WisconsinSite secured2023-07-14Site work begins◐ source
Microsoft Fairwater WisconsinFirst power2026-04-16First power (Epoch)◐ source
Microsoft Fairwater WisconsinBuilding ready for IT2026-06-23First building complete◐ source
Microsoft Fairwater WisconsinBuilding ready for IT2026-06-23First Fairwater building fully operational (Microsoft); startup work began in April 2026◐ source
Microsoft Fairwater WisconsinFull build-out complete2028-05-13 planBuildings 3-11 estimated operational (Epoch)◐ source
Microsoft Fairwater WisconsinFull build-out complete2028-12-31 planSecond Fairwater facility under construction for 2028◐ source
Anthropic-Amazon New CarlisleSite secured2024-04-01Campus announced◐ source
Anthropic-Amazon New CarlisleFirst power2025-06-23First power (Epoch)◐ source
Anthropic-Amazon New CarlisleBuilding ready for IT2025-10-29Campus opened◐ source
Anthropic-Amazon New CarlisleSite secured2026-03-01South campus site prep and substation◐ source
Anthropic-Amazon New CarlisleFull build-out complete2028-03-17 planBuildings 19-32 estimated operational (Epoch)◐ source
OpenAI Stargate New MexicoSite secured2025-09-01Construction begins◐ source
OpenAI Stargate New MexicoSite secured2025-09-01Construction begins; $165bn industrial revenue bond approved◐ source
OpenAI Stargate New MexicoPermits in hand2026-01-15Air permit application filed for gas turbines and diesel (January 2026)◐ source
OpenAI Stargate New MexicoPermits in hand2026-04-27Power plan switched to a 2.45 GW Bloom fuel-cell microgrid (not yet built, no construction permit)○ source
OpenAI Stargate New MexicoPermits in hand2026-10-19 planNMED air-permit public hearing on the fuel-cell plan◐ source
OpenAI Stargate New MexicoNew generation online2026-12-31 planFuel-cell microgrid first block (announced initial operations)◐ source
OpenAI Stargate New MexicoMajor equipment on site2027-02-28 planNatural-gas pipeline feeding the microgrid in service (delayed from August 2026 per reporting on Oracle's force majeure notice)◐ source
OpenAI Stargate New MexicoFull build-out complete2028-12-31 planEstimated completion (Epoch)◐ source
Meta HyperionSite secured2024-12-20Campus announced (Richland Parish)● source
Meta HyperionGrid supply agreed2025-08-20LPSC approves Entergy plants, 500 kV line and substations● source
Meta HyperionPermits in hand2026-04-15LPSC fast-tracks seven more gas plants● source
Meta HyperionBuilding ready for IT2026-04-19Buildings 1 and 2 roofed, cooling at an advanced stage (Epoch timeline)◐ source
Meta HyperionSubstation and lines energized2026-12-01 planNew power stations in service for a 1.8 GW load at Holly Ridge (Epoch timeline note; data center not yet operational)◐ source
Meta HyperionNew generation online2028-06-30 planTwo Entergy combined-cycle units online (planned)● source
Meta HyperionNew generation online2029-06-30 planFranklin Farms 1,500 MW combined cycle online mid-2029 per Industrial Info (Entergy's groundbreaking release says late 2028; earlier date kept for the gate)◐ source
Meta HyperionNew generation online2029-12-31 planThird unit at Waterford online (planned)● source
Colossus 2Site secured2025-02-28Land clearing begins◐ source
Colossus 2First power2025-10-19First power (Epoch)◐ source
Colossus 2Permits in hand2026-03-10MDEQ air permit for 41 permanent turbines◐ source
Colossus 2Permits in hand2026-04-14NAACP and SELC file a Clean Air Act suit over 27 unpermitted turbines; MDEQ counted 46 turbines in May, 60 in June and 69 in July 2026◐ source
Colossus 2New generation online2027-06-30 planTurbine programme reaches 1.1 GW+ (Solaris, planned)◐ source
Colossus 2Permits in hand2027-12-31 planTemporary turbine permit expires◐ source
OpenAI Stargate ShackelfordSite secured2025-08-01Campus announced◐ source
OpenAI Stargate ShackelfordPermits in hand2025-11-15TCEQ air authorization for 210 VoltaGrid generators (700 MW) by emissions registration○ source
OpenAI Stargate ShackelfordConstruction started2025-12-15Groundbreaking (December 2025; TDLR window from 2025-09-26)○ source
OpenAI Stargate ShackelfordNew generation online2026-12-01 planOn-site microgrid first block (announced)◐ source
OpenAI Stargate ShackelfordFirst power2026-12-01 planFirst building delivery (announced)◐ source
OpenAI Stargate ShackelfordFirst power2027-08-15 planFirst power (Epoch estimate)◐ source
OpenAI Stargate ShackelfordFull build-out complete2028-05-11 planTDLR construction window ends (all buildings)○ source
OpenAI Stargate ShackelfordFull build-out complete2028-11-11 planBuild-out complete (Epoch estimate)◐ source
QTS Cedar RapidsSite secured2025-02-13Campus confirmed by Cedar Rapids and Alliant Energy● source
QTS Cedar RapidsGrid supply agreed2025-02-13Alliant Energy commits 1 GW at Big Cedar (161/69 kV lines, 345 kV proposed)● source
QTS Cedar RapidsConstruction started2025-04-01Ground broken on the first building (spring 2025)◐ source
QTS Cedar RapidsFirst power2026-11-15 planFirst power (Epoch estimate)● source
QTS Cedar RapidsBuilding ready for IT2026-12-15 planFirst phase complete (late 2026, QTS)◐ source
Meta PrometheusFirst power2025-10-14First power (Epoch)◐ source
Meta PrometheusFull build-out complete2028-07-01 planBuildings 22-27 estimated operational (Epoch)◐ source
GoodnightConstruction started2025-06-01Ground broken◐ source
GoodnightGrid supply agreed2026-01-09Net-metering application for Load 2 (260 MW) behind Goodnight Wind filed with the PUCT◐ source
GoodnightPermits in hand2026-03-01TCEQ air permit filed for a 933 MW on-site gas plant (no Google offtake)○ source
GoodnightGrid supply agreed2026-07-23PUCT order in Docket 59220 approves net metering with a 525.5 MW 30-minute curtailment obligation◐ source
GoodnightFirst power2027-03-15 planFirst power (Epoch estimate)◐ source
GoodnightFull build-out complete2027-10-01 planSix buildings operational (Epoch estimate)◐ source
OpenAI Stargate UAESite secured2025-05-22Stargate UAE announced◐ source
OpenAI Stargate UAEConstruction started2025-10-16First phase under construction, 5,000 workers on site◐ source
OpenAI Stargate UAEMajor equipment on site2025-12-05First deliveries of critical mechanical systems on site◐ source
OpenAI Stargate UAEBuilding ready for IT2026-09-30 planFirst 200 MW phase complete (Q3 2026, Khazna)◐ source
OpenAI Stargate UAEFirst power2026-12-31 planFirst 200 MW (announced)◐ source
OpenAI Stargate UAEFull build-out complete2028-01-01 plan1 GW operational (Epoch estimate)◐ source
OpenAI Stargate MichiganSite secured2025-10-30Announced as the largest investment in Michigan history◐ source
OpenAI Stargate MichiganGrid supply agreed2025-12-18MPSC approves DTE 1.4 GW contracts◐ source
OpenAI Stargate MichiganPermits in hand2026-02-15Construction allowed ahead of the final air-quality permit; wetlands permits◐ source
OpenAI Stargate MichiganConstruction started2026-03-01Construction start (planned early 2026)◐ source
OpenAI Stargate MichiganConstruction started2026-04-25Major construction underway; financing secured◐ source
OpenAI Stargate MichiganConstruction started2026-06-01Construction equipment and fencing on the Saline Township site◐ source
OpenAI Stargate MichiganFull build-out complete2028-12-31 planCompletion (projected Q4 2028)◐ source
OpenAI Stargate WisconsinSite secured2025-12-01Groundbreaking● source
OpenAI Stargate WisconsinGrid supply agreed2025-12-15ATC transmission application found complete by the PSC (December)◐ source
OpenAI Stargate WisconsinGrid supply agreed2026-12-15 planPSC decision on the refiled ATC line (expected Q4 2026)◐ source
OpenAI Stargate WisconsinSubstation and lines energized2027-12-15 planATC line in service (late 2027)◐ source
OpenAI Stargate WisconsinNew generation online2027-12-31 planWe Energies renewables and storage for the campus (planned)● source
OpenAI Stargate WisconsinGrid supply agreed2028-06-30 planATC transmission line (proposed)● source
OpenAI Stargate WisconsinFirst power2028-06-30 planCampus completion now seen no earlier than mid-2028 (analysis)○ source
OpenAI Stargate WisconsinFull build-out complete2028-12-31 planFour buildings complete (announced)● source
OpenAI Stargate WisconsinFull build-out complete2028-12-31 planLighthouse campus (four buildings) projected complete Q4 2028; 70% of power from solar, wind and storage◐ source
Google Fort WayneConstruction started2024-04-26Ground broken● source
Google Fort WayneGrid supply agreed2026-04-30IURC approves the Google-I&M demand-response arrangement◐ source
Google Fort WayneFirst power2026-12-01 planFirst power (Epoch estimate; city reports phase 1 operational)● source
Google Fort WayneFull build-out complete2028-06-23 planBuilding 6 estimated operational (Epoch)● source
OpenAI Stargate MilamNew generation online2024-10-01Adjacent Orion Solar Belt (900 MWdc) in commercial operation◐ source
OpenAI Stargate MilamConstruction started2025-10-15Ground broken (October 2025)◐ source
OpenAI Stargate MilamSite secured2026-01-09SB Energy partnership and $1bn investment◐ source
OpenAI Stargate MilamBuilding ready for IT2026-10-31 planFirst building delivery (regulatory filings)◐ source
OpenAI Stargate MilamBuilding ready for IT2026-10-31 planFirst building delivered by October 2026 (regulatory filings cited by Epoch)◐ source
OpenAI Stargate MilamFull build-out complete2028-12-31 planCompletion (projected Q4 2028)◐ source
OpenAI Stargate MilamFull build-out complete2028-12-31 plan1.2 GW campus complete (Q4 2028)◐ source
Amazon RidgelandGrid supply agreed2024-03-08Entergy Mississippi large-customer agreement◐ source
Amazon RidgelandSite secured2026-04-09Ridgeland expansion announced ($12bn)◐ source
Amazon RidgelandFirst power2026-05-15First power (Epoch)◐ source
Amazon RidgelandFull build-out complete2028-08-31 planPhase II construction complete (estimate from the stormwater filing)○ source
Amazon RidgelandFull build-out complete2028-09-29 planBuildings 6-14 estimated operational (Epoch)◐ source
OpenAI Stargate AbileneSite secured2024-05-31Site work begins◐ source
OpenAI Stargate AbileneBuilding ready for IT2025-09-26First two buildings live (200+ MW)◐ source
OpenAI Stargate AbileneSite secured2026-03-09Oracle and OpenAI drop the planned 600 MW expansion (financing terms); the eight-building 1.2 GW campus continues, phase 2 due by end-2026◐ source
OpenAI Stargate AbileneMajor equipment on site2026-06-30On-site turbine fleet beyond the first 360 MW (announced, >1 GW of turbines)◐ source
OpenAI Stargate AbileneFull build-out complete2026-11-01 planBuildings 5-8 estimated operational (Epoch)◐ source
Amazon Madison Mega SiteSite secured2024-01-24AWS $10bn Mississippi investment announced● source
Amazon Madison Mega SiteGrid supply agreed2024-03-08Entergy Mississippi large-customer agreement● source
Amazon Madison Mega SiteFirst power2025-06-23First power (Epoch)● source
Amazon Madison Mega SiteFull build-out complete2028-03-15 planBuildings 8-12 estimated operational (Epoch)● source
Crusoe Abilene ExpansionPermits in hand2025-01-22TCEQ standard permit for 360 MW of turbines (ten units) at the existing campus◐ source
Crusoe Abilene ExpansionSite secured2026-03-27Campus announced● source
Crusoe Abilene ExpansionConstruction started2026-03-27Land clearing and site preparation underway● source
Crusoe Abilene ExpansionPermits in hand2026-07-15Major TCEQ permit filed for 41 turbines (about 1.4 GW) and 18 diesel gensets; contested, not approved◐ source
Crusoe Abilene ExpansionFirst power2027-06-30 planFirst building energized (announced)● source
Crusoe Abilene ExpansionFirst power2027-09-17 planFirst power (Epoch estimate)● source
Microsoft Fairwater AtlantaFirst power2025-10-14First building online (about 340 MW IT)◐ source
Microsoft Fairwater AtlantaSite secured2025-12-01QTS East campus rezoned (313 acres)◐ source
Microsoft Fairwater AtlantaPermits in hand2026-03-01Fayetteville data-center prohibition takes effect◐ source
Coreweave HeliosSite secured2025-08-15$1.4bn project financing closed◐ source
Coreweave HeliosGrid supply agreed2026-01-15ERCOT approves 830 MW large-load interconnection◐ source
Coreweave HeliosFirst power2026-06-30Phase I (133 MW IT) delivered, rent starts Q2 2026◐ source
Coreweave HeliosFull build-out complete2029-01-01 planPhase II at full capacity (Epoch estimate)◐ source
DayOne NusajayaFirst power2024-12-31First power (Epoch)◐ source
DayOne NusajayaFirst power2026-01-30390 MW in service across Johor (DayOne)◐ source
Meta Bowling GreenSite secured2025-04-09Data center announced ($800m)◐ source
Meta Bowling GreenPermits in hand2025-11-05Apollo plant filed with the Ohio Power Siting Board (letter-of-notification track)● source
Meta Bowling GreenPermits in hand2026-02-03OPSB authorizes the 350 MW Apollo gas plant (6 recip engines, 21 turbines, 120 MW storage) without hearings● source
Meta Bowling GreenNew generation online2026-02-09Apollo on-site gas plant construction starts◐ source
Meta Bowling GreenFirst power2027-06-30 planPartial energization from Apollo (planned mid-2027)◐ source
Meta Bowling GreenNew generation online2027-12-31 planApollo full operation, campus at full capacity (planned)◐ source
DayOne KempasFirst power2026-01-22First power (Epoch)◐ source
CoreWeave Ellendale NDConstruction started2022-09-08Construction starts◐ source
CoreWeave Ellendale NDFirst power2025-10-27First 50 MW ready for service◐ source
CoreWeave Ellendale NDFirst power2025-11-24Building 1 fully energized (100 MW)◐ source
CoreWeave Ellendale NDFirst power2026-07-01Building 2 phase 1 ready (75 MW)◐ source
CoreWeave Ellendale NDBuilding ready for IT2027-06-01 planFull 400 MW (Epoch estimate)◐ source
Anthropic Lake MarinerSite secured2025-08-14Fluidstack leases 378 MW critical IT● source
Anthropic Lake MarinerFirst power2026-05-31First power (Epoch)● source
Anthropic Lake MarinerFirst power2026-06-30CB-3 delivered (102 MW revenue-generating)● source
Anthropic Lake MarinerBuilding ready for IT2026-07-05CB-3 delivered; 102 MW of revenue-generating IT capacity at Lake Mariner● source
Anthropic Lake MarinerBuilding ready for IT2026-12-31 planCB-4 phased delivery (H2 2026)● source
Anthropic Lake MarinerFull build-out complete2026-12-31 planCB-5 (160 MW, Fluidstack) due online H2 2026; contracted IT load 360 MW◐ source
Anthropic Lake MarinerBuilding ready for IT2027-03-31 planCB-5 phased delivery (now early 2027; announced H2 2026)● source
Meta MontgomerySite secured2024-05-01Data center announced (May 2024)◐ source
Meta MontgomeryFirst power2026-06-18First power (Epoch)◐ source
Meta MontgomeryFull build-out complete2027-02-23 planCampus estimated complete (Epoch)◐ source
STACK Infrastructure NVA02First power2024-10-01First power of the tracked expansion (Epoch)● source
STACK Infrastructure NVA02Full build-out complete2028-01-01 planBuild-out complete (Epoch estimate)● source
Colossus 1Construction started2024-04-24Construction starts in a former Electrolux plant◐ source
Colossus 1First power2024-08-11First training workload (35 MW)◐ source
Colossus 1Permits in hand2025-07-02Air permit for gas turbines (Shelby County, July 2025)◐ source
Colossus 1Substation and lines energized2025-11-07Third MLGW substation expected to power the building◐ source
AWS New AlbanyFirst power2024-12-01First power (Epoch)◐ source
AWS New AlbanyGrid supply agreed2025-07-01PUCO approves AEP Ohio data-center tariff (July 2025)◐ source
AWS New AlbanyFull build-out complete2027-07-01 planBuild-out complete (Epoch estimate)◐ source
QTS Eagle MountainPermits in hand2025-02-04Development agreement amended to allow on-site generation◐ source
QTS Eagle MountainPermits in hand2025-02-04Development agreement amended to allow on-site generation (200 MW gas plant approved later)◐ source
QTS Eagle MountainGrid supply agreed2025-09-01Rocky Mountain Power supply secured; QTS funds the infrastructure◐ source
QTS Eagle MountainConstruction started2025-10-01Construction starts (fall 2025)◐ source
QTS Eagle MountainBuilding ready for IT2026-04-17Building 3 topped out● source
QTS Eagle MountainFirst power2026-12-31 planFirst power (Epoch estimate)◐ source
QTS Eagle MountainFull build-out complete2027-07-01 planBuild-out complete (Epoch estimate)◐ source
Google LincolnFirst power2026-05-12First power (Epoch)◐ source
Google LincolnFull build-out complete2027-10-01 planBuild-out complete (Epoch estimate)◐ source
CoreWeave Denton TXFirst power2025-05-31First power (Epoch)◐ source
CoreWeave Denton TXSite secured2025-10-30CoreWeave-Core Scientific merger rejected by shareholders◐ source
CoreWeave Denton TXFull build-out complete2027-05-31 planFull conversion (Epoch estimate; planned 2027)◐ source
Google Cedar RapidsConstruction started2025-06-01Excavation and cranes across the site (summer 2025)◐ source
Google Cedar RapidsSite secured2025-06-04Google confirmed at Big Cedar● source
Google Cedar RapidsGrid supply agreed2025-06-04Alliant Energy announces the Google project at Big Cedar (utility-owned park with 1 GW)● source
Google Cedar RapidsFirst power2026-12-31 planFirst power (Epoch estimate)● source
Google Cedar RapidsBuilding ready for IT2026-12-31 planCurrent phase complete (2026)◐ source
QTS Richmond 3Grid supply agreed2024-08-29Dominion warns of up to seven-year waits for new large loads◐ source
QTS Richmond 3First power2026-02-13First power (Epoch)◐ source
QTS Richmond 3Full build-out complete2027-02-13 planBuild-out complete (Epoch estimate)◐ source
Start Campus Sines Data CampusGrid supply agreed2024-08-07REN raises grid allocation to 1.2 GW● source
Start Campus Sines Data CampusConstruction started2026-02-15SIN02 (up to 240 MW) construction starts; first customers expected mid-2027◐ source
Start Campus Sines Data CampusFirst power2026-04-03First power of the tracked expansion (Epoch)● source
Start Campus Sines Data CampusFull build-out complete2027-09-30 planTracked phase complete (Epoch estimate)● source
Start Campus Sines Data CampusFull build-out complete2030-12-31 planSix buildings complete (announced)● source
Stream PhoenixFirst power2026-05-01First power of the tracked expansion (Epoch)◐ source
Stream PhoenixBuilding ready for IT2029-12-31 planPhoenix IV (planned 2029)◐ source
Meta Los LunasConstruction started2025-04-01Phase 3 groundbreaking (spring 2025)◐ source
Meta Los LunasFirst power2026-03-01First power of the AI expansion (Epoch)◐ source
Meta Los LunasNew generation online2026-12-31 planPNM solar-plus-storage, first tranche (planned)◐ source
Meta Los LunasNew generation online2027-12-31 planPNM solar-plus-storage, second tranche (planned)◐ source
Meta Los LunasNew generation online2030-12-31 planXGS geothermal 150 MW (planned)◐ source
OpenAI Stargate LordstownSite secured2025-09-23Site announced; ground broken● source
OpenAI Stargate LordstownGrid supply agreed2025-09-23Existing plant substation provides grid supply (no new interconnection reported)◐ source
OpenAI Stargate LordstownConstruction started2025-10-01Site preparation begins◐ source
OpenAI Stargate LordstownBuilding ready for IT2026-07-30Roofing mostly in place, no building operational (imagery)◐ source
OpenAI Stargate LordstownConstruction started2026-09-30 planData center foundation work expected Q3 2026; Epoch imagery shows cleared land but no large-scale construction◐ source
OpenAI Stargate LordstownFirst power2027-03-01 planFirst power (Epoch estimate)● source
Meta CheyenneSite secured2024-07-08Data center announced● source
Anthropic Barber LakeSite secured2025-09-01168 MW lease signed◐ source
Anthropic Barber LakeSite secured2025-11-1239 MW expansion signed◐ source
Meta CheyenneFirst power2026-07-25First power (Epoch)● source
Anthropic Barber LakeFirst power2026-12-30 planFirst power (Epoch estimate)◐ source
Anthropic Barber LakeFull build-out complete2027-01-31 planPhase 2 delivery target (39 MW)◐ source
Meta CheyenneFull build-out complete2027-02-15 planBuild-out complete (Epoch estimate)● source
Meta CheyenneFirst power2027-03-31 planOnline in 2027 per Meta / Cheyenne LEADS (placeholder end of Q1)● source
Anthropic Barber LakeBuilding ready for IT2027-03-31 planData halls delivered to Fluidstack in phases from Q4 2026 through Q1 2027 (slightly later than planned); a second ten-year lease by an AI lab from Q4 2026◐ source
Meta TempleConstruction started2022-04-01Construction starts (spring 2022)◐ source
Meta TempleConstruction started2022-12-15Construction paused for AI redesign◐ source
Meta TempleConstruction started2023-10-01Construction resumes◐ source
Meta JeffersonvilleSite secured2024-01-25Data center announced; construction starts● source
Meta RosemountSite secured2024-03-14Data center announced for 2026◐ source
Meta TempleFirst power2025-12-09First power (Epoch)◐ source
Meta JeffersonvilleFirst power2026-06-04First power (Epoch)● source
Meta RosemountFirst power2026-06-19First power (Epoch)◐ source
AWS BerwickSite secured2024-03-04AWS buys the Cumulus campus ($650m)◐ source
AWS BerwickGrid supply agreed2024-11-01FERC rejects co-location interconnection agreement◐ source
AWS BerwickGrid supply agreed2025-04-15FERC upholds the rejection on rehearing◐ source
AWS BerwickFirst power2025-09-09First power (Epoch)◐ source
AWS BerwickGrid supply agreed2026-05-31Switch to front-of-meter supply after transmission work (targeted spring 2026)◐ source
AWS BerwickNew generation online2029-12-31 plan840-1,200 MW contracted from Susquehanna◐ source
AWS BerwickNew generation online2032-12-31 plan1,680-1,920 MW contracted◐ source
Google Red OakFirst power2025-08-25First power (Epoch)◐ source
Google Red OakBuilding ready for IT2025-11-14First building confirmed operational◐ source
Google Red OakFull build-out complete2026-12-01 planBuild-out complete (Epoch estimate)◐ source
CoreWeave Muskogee OKConstruction started2024-11-15Ground broken (November 2024)◐ source
CoreWeave Muskogee OKGrid supply agreed2024-11-15OG&E service for the 100 MW site at groundbreaking● source
CoreWeave Muskogee OKSubstation and lines energized2026-05-3170 MW building in final testing and commissioning (Q2 2026)● source
CoreWeave Muskogee OKFirst power2026-06-3070 MW building delivery (planned Q2 2026)◐ source
CoreWeave Muskogee OKFirst power2026-12-31 planFirst power (Epoch estimate)◐ source
CoreWeave Muskogee OKFull build-out complete2027-12-31 planSecond 82.5 MW building initial delivery (Q4 2027)◐ source
Meta KunaSite secured2022-02-15Kuna data center announced● source
Meta KunaConstruction started2022-12-15Construction paused for AI redesign● source
Meta KunaConstruction started2023-10-01Construction resumes with the AI design● source
Meta HuntsvilleSite secured2022-06-15Expansion announced◐ source
Meta HuntsvilleConstruction started2022-12-20Expansion paused for AI redesign◐ source
Meta HuntsvilleFirst power2026-03-04First power of the expansion (Epoch)◐ source
Nebius MantsalaSite secured2024-10-08Expansion to 75 MW announced◐ source
Nebius MantsalaBuilding ready for IT2026-03-3175 MW complete (early 2026)◐ source
Nebius MantsalaGrid supply agreed2027-10-31 plan70 MW substation for the second site (autumn 2027)◐ source
Nebius MantsalaFirst power2027-12-31 planSecond Mäntsälä site first capacity (planned 2027)◐ source
Meta Eagle MountainFirst power2021-07-01Campus live◐ source
Meta Eagle MountainFirst power2025-12-07First power of the expansion (Epoch)◐ source
Meta AikenSite secured2024-08-29Data center announced for spring 2027● source
Vantage TX1First power2026-02-15TX11 first power (Epoch)◐ source
Vantage TX1Full build-out complete2027-08-31 planTX12 estimated operational (Epoch)◐ source
Google Kansas City EastSite secured2026-02-12Second Kansas City campus (Project Mica) confirmed◐ source
Google MidlothianConstruction started2026-01-15Building 5 ($880m, 288,000 sq ft) construction begins◐ source
Google MidlothianFull build-out complete2027-02-28 planBuilding 5 completion targeted February 2027◐ source
CoreWeave Lancaster Greenfield siteSite secured2025-07-15Data center announced◐ source
CoreWeave Lancaster Greenfield siteGrid supply agreed2025-07-15PPL Electric supply with about $200m of upgrades and two on-site substations○ source
Microsoft Narvik NorwaySite secured2025-09-17Microsoft $6.2bn capacity agreement◐ source
CoreWeave Lancaster Greenfield sitePermits in hand2025-12-01Demolition permits granted for phase 1; building permits staged○ source
CoreWeave Lancaster Greenfield siteConstruction started2026-01-15Turner-Wohlsen JV construction underway◐ source
Microsoft Narvik NorwaySite secured2026-05-11$790m project financing◐ source
Microsoft Narvik NorwayGrid supply agreed2026-05-26Vattenfall renewable PPA signed for phase 1 (2027-2031)● source
Microsoft Narvik NorwayConstruction started2026-06-01About 350 workers on site (TIME)◐ source
Microsoft Narvik NorwayFirst power2026-12-31 planFirst staged deliveries (planned 2026)◐ source
Microsoft Narvik NorwayNew generation online2027-01-01 planVattenfall renewable PPA covers 2027-2031 for phase 1● source
CoreWeave Lancaster Greenfield siteFirst power2027-06-30 planFirst phase (Epoch estimate; announced summer 2027)◐ source
Microsoft Narvik NorwayFirst power2027-06-30 planOperations set to commence in 2027○ source
Microsoft Narvik NorwayFull build-out complete2027-12-31 planRubin GPU capacity delivered (planned 2027)◐ source
Meta GallatinConstruction started2020-01-01Construction starts◐ source
Meta GallatinConstruction started2022-12-15Meta pauses build for GPU redesign◐ source
Meta GallatinFirst power2024-11-14Starts serving traffic◐ source
Meta SarpySite secured2022-07-28Springfield expansion announced◐ source
Microsoft-Nebius New JerseySite secured2025-03-06Site announced; DataOne colocation agreement● source
Microsoft-Nebius New JerseySite secured2025-09-08Microsoft capacity agreement● source
Microsoft-Nebius New JerseyFirst power2026-04-15First power (Epoch)● source
Microsoft-Nebius New JerseyPermits in hand2026-07-08Revised site plan with 328 MW on-site fuel cells● source
EcoDataCenter 2Construction started2025-09-15Ground broken● source
EcoDataCenter 2Grid supply agreed2025-09-15250 MW available at launch (up to 600 MW), per EcoDataCenter● source
EcoDataCenter 2Site secured2026-02-15Mistral AI €1.2bn long-term commitment for an AI data center at Borlänge; first facilities 2027, 250 MW first phase◐ source
EcoDataCenter 2First power2027-06-30 planFirst power (Epoch estimate; announced early 2027)● source
EcoDataCenter 2Building ready for IT2027-06-30 planFirst phase complete (mid-2027)◐ source
EcoDataCenter 2Full build-out complete2028-06-30 planPhase complete (Epoch estimate)● source
Nscale KeflavikSite secured2025-11-1515 MW lease at Verne◐ source
Nscale KeflavikFirst power2026-04-23First phase complete (Epoch)◐ source
Nscale KeflavikFull build-out complete2026-12-31 planFull deployment (planned 2026)◐ source