Meta Los Lunas · Los Lunas, NM

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 2026118 MW
Planned end state218 MW
First power2026-03-01
Build-out complete2028-01-01 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersPNM

Latest: XGS geothermal 150 MW (planned) · New generation online · 2030-12-31 (plan) · recorded 2026-10-04

Seven operational buildings and three more under construction in Valencia County; phase 3 ($800m) broke ground in spring 2025. PNM filed three more solar-plus-storage projects (Star Light, Windy Lane, Four Mile) targeting December 2026 and December 2027; XGS Energy and Meta plan a 150 MW geothermal plant by 2030. · source ◐ secondary, confidence medium

Recorded readiness — 1 of 5 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water· Financing● Construction 2025-04

Gate to first power — target 2026-03-01 (estimate) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
New generation online (context)2026-02-01 (1 mo before)12 mo after (n=1)2026-12-31 plancontextPNM solar-plus-storage, first tranche (planned) · ◐
Construction started (context)2024-03-01 (24 mo before)29 mo before (n=15)2025-04-01contextPhase 3 groundbreaking (spring 2025) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-04-01 Construction startedPhase 3 groundbreaking (spring 2025) · ◐
2026-03-01 First powerFirst power of the AI expansion (Epoch) · ◐
2026-12-31 plan New generation onlinePNM solar-plus-storage, first tranche (planned) · ◐
2027-12-31 plan New generation onlinePNM solar-plus-storage, second tranche (planned) · ◐
2030-12-31 plan New generation onlineXGS geothermal 150 MW (planned) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-07-24—Land clearing starts for new building.
2026-03-0187 MWBuilding 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.
2026-07-2887 MWBuilding 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months
2026-10-26118 MWBuilding 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
2028-01-01 est.218 MWBuilding 3 is estimated to be operational. This is estimated from the timeline of similar buildings at other Meta sites.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Meta fact sheet · Air quality permit for expansion · Construction contractor page for the site

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-11-09. Report a correction to contact@ailoadmap.com (campus id meta-los-lunas; include the row and a source link).