Meta Los Lunas · Los Lunas, NM

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 2026118 MW (est.)
Planned end state218 MW
First power2026-03-01
Build-out complete2028-01-01 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersPNM

Latest: XGS geothermal 150 MW (planned) · New generation online · 2030-12-31 (plan) · recorded 2026-10-04

Seven operational buildings and three more under construction in Valencia County; phase 3 ($800m) broke ground in spring 2025. PNM filed three more solar-plus-storage projects (Star Light, Windy Lane, Four Mile) targeting December 2026 and December 2027; XGS Energy and Meta plan a 150 MW geothermal plant by 2030. · source ◐ secondary, confidence medium

Recorded readiness — 1 of 5 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water· Financing● Construction 2025-04

Gate to first power — target 2026-03-01 (estimate) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
New generation online (context)2026-02-01 (1 mo before)12 mo after (n=1)2026-12-31 plancontextPNM solar-plus-storage, first tranche (planned) · ◐
Construction started (context)2024-03-01 (24 mo before)29 mo before (n=15)2025-04-01contextPhase 3 groundbreaking (spring 2025) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-04-01 Construction startedPhase 3 groundbreaking (spring 2025) · ◐
2026-03-01 First powerFirst power of the AI expansion (Epoch) · ◐
2026-12-31 plan New generation onlinePNM solar-plus-storage, first tranche (planned) · ◐
2027-12-31 plan New generation onlinePNM solar-plus-storage, second tranche (planned) · ◐
2030-12-31 plan New generation onlineXGS geothermal 150 MW (planned) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-07-24—Land clearing starts for new building.
2026-03-0187 MWBuilding 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.
2026-10-26 est.118 MWBuilding 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
2028-01-01 est.218 MWBuilding 3 is estimated to be operational. This is estimated from the timeline of similar buildings at other Meta sites.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Meta fact sheet · Air quality permit for expansion · Construction contractor page for the site

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-los-lunas; include the row and a source link).