AILoadmapAI gigawatts, campus by campus

Opportunities

Two views for people who sell into these campuses. Everything is derived from the dated, sourced facts on each campus page. "No supplier in public records" is a statement about the record: an order may not exist yet, may be confidential, or may not have been found.

Gas turbines

11 relevant campuses not yet energized · 22 GW

No supplier in public records: 10 of 11

Reciprocating engines

Not yet tracked: fewer than five campuses have a recorded supplier in this category, so a "none found" count would describe our research, not the market.

Fuel cells

Not yet tracked: fewer than five campuses have a recorded supplier in this category, so a "none found" count would describe our research, not the market.

Battery storage

Not yet tracked: fewer than five campuses have a recorded supplier in this category, so a "none found" count would describe our research, not the market.

Backup generation

Not yet tracked: fewer than five campuses have a recorded supplier in this category, so a "none found" count would describe our research, not the market.

Transformers

Not yet tracked: fewer than five campuses have a recorded supplier in this category, so a "none found" count would describe our research, not the market.

Switchgear

Not yet tracked: fewer than five campuses have a recorded supplier in this category, so a "none found" count would describe our research, not the market.

Cooling

Not yet tracked: fewer than five campuses have a recorded supplier in this category, so a "none found" count would describe our research, not the market.

Who got the order — campuses that need new generation × equipment category

Bold = primary source or high confidence; plain = reported; "unnamed" = units or MW on record without a make. empty = nothing on record. Transformer, switchgear and cooling columns have no recorded vendor yet.

CampusPlannedGas turbinesRecip enginesFuel cellsBattery storageBackup gensetsSolar / windTransformersSwitchgearCoolingNothing on record
Wonder Valley
MD of Greenview (south of Grande Prairie), Alberta, Canada
7.5 GW9 of 9
Haenam Solar City AI Data Center
Haenam, Jeollanam-do, South Korea
3.0 GW9 of 9
Microsoft Fairwater Wisconsin
Mount Pleasant, WI · energized
2.3 GWunnamedunnamed7 of 9
Anthropic-Amazon New Carlisle
New Carlisle, IN · energized
1.9 GWunnamed8 of 9
Meta Sturgeon County
Sturgeon County, Alberta, Canada
1.8 GW9 of 9
OpenAI Stargate New Mexico
Doña Ana County, NM
1.8 GWBloom Energy8 of 9
Meta Hyperion
Holly Ridge, Richland Parish, LA
1.6 GWMitsubishi Power8 of 9
Colossus 2
South Memphis, TN · energized
1.5 GWunnamed8 of 9
Reliance Visakhapatnam AI Cluster
Visakhapatnam, Andhra Pradesh, India
1.5 GW9 of 9
OpenAI Stargate Shackelford
Shackelford County, TX
1.4 GWINNIO Jenbacher8 of 9
Meta Prometheus
New Albany, OH · energized
1.0 GWSolar Turbines (Caterpillar)Caterpillar7 of 9
Goodnight
Claude (Armstrong County), TX
1.0 GWunnamedunnamed7 of 9
OpenAI Stargate Wisconsin
Port Washington, WI
902 MWunnamed8 of 9
Google Fort Wayne
Fort Wayne, IN · energized
863 MWunnamed8 of 9
OpenAI Stargate Milam
Milam County, TX
857 MWSB Energy8 of 9
OpenAI Stargate Abilene
Abilene, TX · energized
843 MWSolar Turbines (Caterpillar)unnamed7 of 9
Amazon Ridgeland
Ridgeland, MS · energized
840 MWMitsubishi Power8 of 9
Amazon Madison Mega Site
Madison County, MS · energized
683 MWunnamed8 of 9
Crusoe Abilene Expansion
Abilene, TX
672 MWunnamedunnamed7 of 9
Meta Bowling Green
Bowling Green, OH
422 MWunnamedunnamedunnamed6 of 9
Colossus 1
South Memphis, TN · energized
340 MWSolar Turbines (Caterpillar)8 of 9
QTS Eagle Mountain
Eagle Mountain, UT
304 MWunnamed8 of 9
Microsoft-Nebius New Jersey
Vineland, NJ · energized
50 MWBloom Energy8 of 9

Where equipment is still open — campuses not yet energized whose power path needs new generation

CampusPathTargetPlannedEquipment on recordRequired steps without a public date
Wonder Valley
MD of Greenview (south of Grande Prairie), Alberta, Canada
On-site generation—7.5 GWnone in public recordsPermits in hand, New generation online, Major equipment on site, Building ready for IT
Haenam Solar City AI Data Center
Haenam, Jeollanam-do, South Korea
Hybrid: on-site bridge, then grid2028-12-313.0 GWnone in public recordsPermits in hand, Grid supply agreed, New generation online, Major equipment on site, Building ready for IT
Meta Sturgeon County
Sturgeon County, Alberta, Canada
Grid, with new utility generation2028-12-311.8 GWnone in public recordsGrid supply agreed, Substation and lines energized, New generation online, Building ready for IT
OpenAI Stargate New Mexico
Doña Ana County, NM
On-site generation2026-12-311.8 GWBloom Energy solid-oxide fuel cell 2.5 GW (permit pending)Building ready for IT
Meta Hyperion
Holly Ridge, Richland Parish, LA
Grid, with new utility generation2028-01-011.6 GW2 combined-cycle gas turbine 1.5 GW (under construction); 1 Mitsubishi Power M501JAC 754 MW (planned)—
Reliance Visakhapatnam AI Cluster
Visakhapatnam, Andhra Pradesh, India
Hybrid: on-site bridge, then grid2028-10-311.5 GWnone in public recordsPermits in hand, Grid supply agreed, New generation online, Major equipment on site, Building ready for IT
OpenAI Stargate Shackelford
Shackelford County, TX
Hybrid: on-site bridge, then grid2026-12-011.4 GW210 INNIO Jenbacher gas reciprocating engine 700 MW (permitted)Grid supply agreed, Major equipment on site, Building ready for IT
Goodnight
Claude (Armstrong County), TX
Hybrid: on-site bridge, then grid2027-12-311.0 GWgas turbine 933 MW (permit pending); 2 wind 531 MW (operating / under construction)New generation online, Major equipment on site, Building ready for IT
OpenAI Stargate Milam
Milam County, TX
Hybrid: on-site bridge, then grid2026-10-31857 MWSB Energy solar (planned)Permits in hand, Grid supply agreed, Major equipment on site
Crusoe Abilene Expansion
Abilene, TX
Hybrid: on-site bridge, then grid2027-06-30672 MWgas turbine 900 MW (planned); battery storage (planned)Grid supply agreed, New generation online, Building ready for IT
Meta Bowling Green
Bowling Green, OH
On-site generation2027-06-30422 MW21 gas turbine (under construction); 6 gas reciprocating engine (under construction); battery storage 120 MW (under construction)Major equipment on site, Building ready for IT

(make not reported) · 20 entries · 14 GW where sized

CampusCategoryModelUnitsMWStatusDate
Colossus 2gas turbine—69495 MWoperating (temporary)2026-07-15
Colossus 2gas turbine—411.2 GWpermitted2026-03-10
Anthropic-Amazon New Carlislecombined-cycle gas turbine—1870 MWacquired2026-12-31
Anthropic-Amazon New Carlislecombined-cycle gas turbine—11.5 GWproposed2030-06-30
OpenAI Stargate Abilenediesel genset—62—operating2025-09-26
OpenAI Stargate Abilenegas turbine—411.4 GWpermit pending2026-07-15
Microsoft Fairwater Wisconsingas turbine—51.1 GWunder construction2028-03-31
Microsoft Fairwater Wisconsingas reciprocating engine——128 MWunder construction2027-12-31
Amazon Madison Mega Sitecombined-cycle gas turbine—21.5 GWunder construction2028-08-31
Crusoe Abilene Expansiongas turbine——900 MWplanned2027-06-30
Crusoe Abilene Expansionbattery storage———planned2027-06-30
Goodnightgas turbine——933 MWpermit pending2026-01-15
Goodnightwind—2531 MWoperating / under construction2026-12-31
Google Fort Waynediesel genset—228—permit pending2026-09-23
Meta Bowling Greengas turbine—21—under construction2026-02-09
Meta Bowling Greengas reciprocating engine—6—under construction2026-02-09
Meta Bowling Greenbattery storage——120 MWunder construction2026-02-09
Meta Hyperioncombined-cycle gas turbine—21.5 GWunder construction2028-10-31
OpenAI Stargate Wisconsingas turbine—51.1 GWunder construction2028-03-31
QTS Eagle Mountaingas turbine——200 MWapproved (not pursued)2025-06-30

Bloom Energy · 2 entries · 2.8 GW where sized

CampusCategoryModelUnitsMWStatusDate
Microsoft-Nebius New Jerseyfuel cellsolid-oxide fuel cell—328 MWunder construction2026-04-15
OpenAI Stargate New Mexicofuel cellsolid-oxide fuel cell—2.5 GWpermit pending2026-10-19

Mitsubishi Power · 2 entries · 1.5 GW where sized

CampusCategoryModelUnitsMWStatusDate
Amazon Ridgelandcombined-cycle gas turbineM501JAC1754 MWplanned2029-12-31
Meta Hyperioncombined-cycle gas turbineM501JAC1754 MWplanned2029-12-31

INNIO Jenbacher · 1 entry · 700 MW where sized

CampusCategoryModelUnitsMWStatusDate
OpenAI Stargate Shackelfordgas reciprocating engine—210700 MWpermitted2025-11-15

Solar Turbines (Caterpillar) · 4 entries · 631 MW where sized

CampusCategoryModelUnitsMWStatusDate
Meta Prometheusgas turbineTitan 250366 MWoperating (partial)2026-08-31
Meta Prometheusgas turbinePGM 1309144 MWoperating (partial)2026-08-31
OpenAI Stargate Abilenegas turbineTitan 3505190 MWoperating2025-09-26
Colossus 1gas turbineTitan 130 (SMT-130)14231 MWoperating2025-07-02

GE Vernova · 2 entries · 171 MW where sized

CampusCategoryModelUnitsMWStatusDate
OpenAI Stargate Abilenegas turbineLM25005171 MWoperating2025-09-26
Colossus 1gas turbineTM250027—operating2025-07-02

Siemens Energy · 1 entry · 39 MW where sized

CampusCategoryModelUnitsMWStatusDate
Meta Prometheusgas turbineSGT-400339 MWoperating (partial)2026-08-31

Caterpillar · 1 entry · 35 MW where sized

CampusCategoryModelUnitsMWStatusDate
Meta Prometheusgas reciprocating engineG35201535 MWoperating (partial)2026-08-31

SB Energy · 1 entry · 0 MW where sized

CampusCategoryModelUnitsMWStatusDate
OpenAI Stargate Milamsolar———planned2028-12-31