Goodnight · Claude (Armstrong County), TX

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerGoogle
UsersGoogle DeepMind
IT power, end of 20260 MW
Planned end state1.0 GW
First power2027-03-15 (est.)
Build-out complete2027-10-01 (est.)
Power pathHybrid: on-site bridge, then grid
Binding step Grid interconnection (from reporting)
First power vs announcedon time (announced 2027-12-31)
Full build-out vs announcedNo announced date on record
Utility / power partnersSerena (Goodnight Wind); Crusoe

Latest: Six buildings operational (Epoch estimate) · Full build-out complete · 2027-10-01 (plan) · recorded 2026-10-04

Google campus developed by Crusoe near Claude: about 1 GW IT, expected operational in 2027. 525.5 MW of load (Crusoe Load 1, 265.5 MW; Load 2, 260 MW, transferred to Ensign in March 2026) is netted behind the 265.5 MW Goodnight I wind farm. The PUCT's 2026-07-23 order in Docket 59220, the first under Senate Bill 6, approved the arrangement but requires full 30-minute curtailment of the whole 525.5 MW in grid emergencies, which Crusoe is contesting. Crusoe also filed a TCEQ air permit for a 933 MW on-site gas plant without a Google offtake. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

○ Land● Permits 2026-03● Grid supply 2026-01○ Generation○ Water· Financing● Construction 2025-06

Gate to first power — target 2027-12-31 (announced) · path: Hybrid: on-site bridge, then grid · each step must finish its lead time before the target

2 of 5 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Permits in hand2027-12-28 (0 mo before)4 mo after (n=8)2026-03-01on record in timeTCEQ air permit filed for a 933 MW on-site gas plant (no Google offtake) · ○
Grid supply agreed2027-03-28 (9 mo before)7 mo before (n=11)2026-01-09on record in timeNet-metering application for Load 2 (260 MW) behind Goodnight Wind filed with the PUCT · ◐
New generation online2027-11-28 (1 mo before)12 mo after (n=1)no public dateno public date · would need to be done by 2027-11-28No date on record
Major equipment on site2027-06-28 (6 mo before)9 mo after (n=1)no public dateno public date · would need to be done by 2027-06-28No date on record
Construction started (context)2025-12-28 (24 mo before)29 mo before (n=15)2025-06-01contextGround broken · ◐
Building ready for IT2027-12-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2027-12-28No date on record
Full build-out complete (context)2028-12-28 (-12 mo before)—2027-10-01 plancontextSix buildings operational (Epoch estimate) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-06-01 Construction startedGround broken · ◐
2026-01-09 Grid supply agreedNet-metering application for Load 2 (260 MW) behind Goodnight Wind filed with the PUCT · ◐
2026-03-01 Permits in handTCEQ air permit filed for a 933 MW on-site gas plant (no Google offtake) · ○
2026-07-23 Grid supply agreedPUCT order in Docket 59220 approves net metering with a 525.5 MW 30-minute curtailment obligation · ◐
2027-03-15 plan First powerFirst power (Epoch estimate) · ◐
2027-10-01 plan Full build-out completeSix buildings operational (Epoch estimate) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbine——933 MWpermit pending2026-01-15TCEQ permit filed January 2026 for a 933 MW on-site gas plant; Google later agreed to acquire it (September 2026 reporting) · ◐
wind—2 × 265.5 MW531 MWoperating / under construction2026-12-31Goodnight I (operating) and II (under construction) wind farms netted against the load · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-05-19—Land clearing begins
2025-10-16—Building 1 and 2 under construction.
2025-12-23—Construction on Building 1 and 2 looks about halfway to completion. Foundations and utility trenches are visible for Building 3-4. Building 5-6 have an outline. The substation appears to be expanding.
2026-04-16—Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.
2027-03-15 est.103 MWBuilding 1 operational. This [regulatory document](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2025027064) lists the completion date for Building 1 as 2026-09-12, the current status suggests this estimate will not
2027-05-15 est.206 MWBuilding 2 operational. The completion date for [Building 2 Tenant Improvement](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2025027065) is 2026-11-07, about 2 months later than Building 1. We therefore add 2 month
2027-10-01 est.1.0 GW6 buildings are operational. This is based on: 1. A [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026010861) for Building 6 with a completion date of 2027-07-30. Normally there is a follow-up fi

Recorded fact No public date for new generation online, major equipment on site, building ready for it.

Calculated requirement Major equipment on site must finish by 2027-06-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2027-12-31 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Amended tax abatement agreement, with updated blueprints on p.46 · Original tax abatement agreement, with original blueprints and specs on the last page · TABS database, with "Llano" data centers in the city of Claude · Press release reports Google investing in a new data center in Armstrong County · Clean Air Act Initial Prevention of Significant Deterioration permit application.

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id goodnight; include the row and a source link).