AILoadmapAI gigawatts, campus by campus

The AI Infrastructure Race

Who is bringing AI capacity online, and where the next wave is waiting for power. Comparison, not verdicts: every chart shows tracked campuses only, and coverage differs by country. Chinese campuses are far less documented in public sources than American ones, so a gap between the two reflects coverage as well as construction.

Capacity online, by region · cumulative IT GW at year end · 2023–2030
0 GW10 GW20 GW30 GW40 GW20232024202520262027202820292030today35.6 GW9.8 GW3.0 GW1.4 GW9.7 GW4.9 GW
United States (n=80) China (n=8) Europe (n=17) Middle East & Gulf (n=4) Rest of Asia (n=26) Other regions (n=15)solid = observed · dashed = Epoch AI estimates and announced plans · each line ends where its announced plans end
Tracked campuses only. Coverage differs by country; China is undercounted.Data 2026-W45 (2026-11-09) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers
Waiting for first power, by power path · planned IT GW · 61 GW across 64 campuses not yet energized · by target first-power year
2025400 MW100% grid
202613 GW68% grid
202713 GW83% grid
202818 GW50% grid
203290 MW100% grid
no date17 GW55% grid
Grid supply Grid + new utility generation Hybrid On-site generation
Tracked campuses only. Coverage differs by country; China is undercounted.Data 2026-W45 (2026-11-09) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers
Waiting for first power, US vs rest of world · planned IT GW of campuses not yet energized · by target first-power year
2025400 MWUS 0%
202613 GWUS 50%
202713 GWUS 44%
202818 GWUS 20%
203290 MWUS 0%
no date17 GWUS 6%
United States Rest of world"no date" = announced without a date
Tracked campuses only. Coverage differs by country; China is undercounted.Data 2026-W45 (2026-11-09) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers
Planned IT power, by operator · planned IT GW, all tracked campuses · announced end state · data 2026-11-09
Meta10.0 GW
Others9.9 GW
ByteDance7.8 GW
Google7.8 GW
Wonder Valley7.5 GW
Amazon6.2 GW
Microsoft6.1 GW
Oracle / Stargate5.9 GW
Scala4.8 GW
OpenAI3.8 GW
Elea3.2 GW
Stock Farm Road (Haenam)3.0 GW
Anthropic2.7 GW
Syncline Energy2.4 GW
Envision2.0 GW
IREN2.0 GW
xAI1.9 GW
Reliance1.5 GW
CDC1.4 GW
Mistral AI / MGX (Paris)1.4 GW
YTL Power1.2 GW
Bell1.2 GW
QTS (Blackstone)1.0 GW

Operator = the owner when it is a hyperscaler, else the named hyperscaler tenant, else the owner; any operator with 1 GW+ planned gets its own colour. Largest in "Others": CloudHQ Querétaro 900 MW, Brookfield Strängnäs AI Hub 750 MW, Racks Central Johor AI Factory Campus 510 MW.

Tracked campuses only. Coverage differs by country; China is undercounted.Data 2026-W45 (2026-11-09) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers
Planned IT power, by country · planned IT GW · top 14 of 28 countries · announced end state · data 2026-11-09
United States37 GW80 campuses
Canada11 GW4 campuses
China9.8 GW8 campuses
Brazil8.9 GW3 campuses
Australia6.4 GW5 campuses
South Korea4.3 GW5 campuses
Malaysia3.3 GW7 campuses
India2.7 GW3 campuses
France1.4 GW1 campus
United Arab Emirates1.2 GW2 campuses
Kenya1.0 GW1 campus
Japan927 MW4 campuses
Mexico900 MW1 campus
United Kingdom898 MW3 campuses
Owned by or built for a hyperscaler Domestic and other developers
Tracked campuses only. Coverage differs by country; China is undercounted.Data 2026-W45 (2026-11-09) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers

ERCOT: the queue and the campuses

Texas interconnection requests run far ahead of what is being built. These figures are context and are not added to any total on this site.

MeasureCapacityBasis
AI campuses tracked here9.7 GW16 campuses with named operators: 1.7 GW online, 0.9 GW under construction. Coverage is partial.
Large-load interconnection requests474.7 GW420.8 GW identified as data centers. Requests, which can overlap and may never be built. June 2026, ERCOT testimony, via POWER
Eligible for the Batch Zero studyabout 205 GWRequests eligible for the one-time batch study approved by Texas regulators. August 2026, POWER
Data center projects tracked by Modo Energy92 GW11 GW operating or expanding, 12 GW under construction, 15 GW committed, 54 GW proposed. All data centers, not only AI. October 21, 2026, Modo Energy
Large load observed energized5.8 GWA further 3.2 GW was approved to energize but not yet operating. March 26, 2026, ERCOT status data, via Corley Energy

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row).