The AI Infrastructure Race
Who is bringing AI capacity online, and where the next wave is waiting for power. Comparison, not verdicts: every chart shows tracked campuses only, and coverage differs by country. Chinese campuses are far less documented in public sources than American ones, so a gap between the two reflects coverage as well as construction.
Operator = the owner when it is a hyperscaler, else the named hyperscaler tenant, else the owner; any operator with 1 GW+ planned gets its own colour. Largest in "Others": CloudHQ Querétaro 900 MW, Brookfield Strängnäs AI Hub 750 MW, Racks Central Johor AI Factory Campus 510 MW.
ERCOT: the queue and the campuses
Texas interconnection requests run far ahead of what is being built. These figures are context and are not added to any total on this site.
| Measure | Capacity | Basis |
|---|---|---|
| AI campuses tracked here | 9.7 GW | 16 campuses with named operators: 1.7 GW online, 0.9 GW under construction. Coverage is partial. |
| Large-load interconnection requests | 474.7 GW | 420.8 GW identified as data centers. Requests, which can overlap and may never be built. June 2026, ERCOT testimony, via POWER |
| Eligible for the Batch Zero study | about 205 GW | Requests eligible for the one-time batch study approved by Texas regulators. August 2026, POWER |
| Data center projects tracked by Modo Energy | 92 GW | 11 GW operating or expanding, 12 GW under construction, 15 GW committed, 54 GW proposed. All data centers, not only AI. October 21, 2026, Modo Energy |
| Large load observed energized | 5.8 GW | A further 3.2 GW was approved to energize but not yet operating. March 26, 2026, ERCOT status data, via Corley Energy |
Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row).