Start Campus Sines Data Campus · Sines, Portugal

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerNscale
UsersMicrosoft
IT power, end of 202633 MW
Planned end state233 MW
First power2026-04-03
Build-out complete2027-09-30 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersREN; EDP

Latest: Six buildings complete (announced) · Full build-out complete · 2030-12-31 (plan) · recorded 2026-10-04

SINES DC south of Lisbon: six buildings (SIN01-06) built in steps to 2030, €8.5bn. REN, the Portuguese TSO, raised the secured grid allocation from 495 MW to 1.2 GW IT in August 2024 and is reinforcing the Sines network; EDP is a renewable-supply partner. SIN01 (26 MW) is the first phase. · source ● primary, confidence high

Recorded readiness — 2 of 6 applicable milestones have a dated public record

○ Land○ Permits● Grid supply 2024-08· Generation○ Water○ Financing● Construction 2026-02

Gate to first power — target 2026-04-03 (estimate) · path: Grid supply · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Grid supply agreed2025-07-03 (9 mo before)7 mo before (n=11)2024-08-07on record in timeREN raises grid allocation to 1.2 GW · ●
Construction started (context)2024-04-03 (24 mo before)29 mo before (n=15)2026-02-15contextSIN02 (up to 240 MW) construction starts; first customers expected mid-2027 · ◐
Full build-out complete (context)2027-04-03 (-12 mo before)—2027-09-30 plancontextTracked phase complete (Epoch estimate) · ●

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-08-07 Grid supply agreedREN raises grid allocation to 1.2 GW · ●
2026-02-15 Construction startedSIN02 (up to 240 MW) construction starts; first customers expected mid-2027 · ◐
2026-04-03 First powerFirst power of the tracked expansion (Epoch) · ●
2027-09-30 plan Full build-out completeTracked phase complete (Epoch estimate) · ●
2030-12-31 plan Full build-out completeSix buildings complete (announced) · ●

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2022-01-01—Land clearing begins for Building 1 (SIN01)
2024-10-31—Building 1 (SIN01) is completed, but at this point it likely not being used for AI as the collaboration with Microsoft that resulted in GB300s did not occur until Q1 2026. The completion is based both on satellite imager
2026-04-0333 MWBuilding 1 (SIN01) operational for AI, with the first deployment of 12,600 Nvidia GB300 NVL72s to the site being reported completed "Q1 2026" based on the [corporate announcement](https://lp.startcampus.pt/start-campus-h
2026-08-1633 MWSatellite imagery shows two black outlines, suggesting two buildings going up on a second adjacent site. There is an outline of another building as well. Further to the east, there is land clearing.
2027-09-30 est.233 MWBuilding 2 (SIN02) projected to be operational. This is based on the timeline provided in the [factsheet](https://23712035.hs-sites.com/hubfs/SINES_02.PDF.pdf?hsCtaAttrib=199407154715) for the site. We expect VR200 GPUs

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Website for the site · Factsheet for the full site · Article detailing Microsoft collaboration and GPU amounts

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id start-campus-sines-data-campus; include the row and a source link).