Meta Bowling Green · Bowling Green, OH

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 20260 MW
Planned end state422 MW
First power2027-02-01 (est.)
Build-out complete2028-01-01 (est.)
Power pathOn-site generation
Binding step New generation (from reporting)
First power vs announcedon time (announced 2027-06-30)
Full build-out vs announcedNo announced date on record

Latest: Apollo full operation, campus at full capacity (planned) · New generation online · 2027-12-31 (plan) · recorded 2026-10-04

Project Accordion, Middleton Township, Wood County: $800m, 715,000 sq ft on 280 acres, announced April 2025. Primary supply is the behind-the-meter Apollo gas plant (Will-Power OH, 147 acres next door), not connected to the grid; Toledo Edison (FirstEnergy) provides standby only. Apollo construction from about 2026-02-09; partial operation and partial data-center energization expected mid-2027, full in late 2027. The plant was fast-tracked without public hearings. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 5 applicable milestones have a dated public record

● Land 2025-04● Permits 2025-11· Grid supply● Generation 2026-02○ Water· Financing○ Construction

Gate to first power — target 2027-06-30 (announced) · path: On-site generation · each step must finish its lead time before the target

2 of 4 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2026-03-28 (15 mo before)13 mo before (n=26)2025-04-09contextData center announced ($800m) · ◐
Permits in hand2027-06-28 (0 mo before)4 mo after (n=8)2025-11-05on record in timeApollo plant filed with the Ohio Power Siting Board (letter-of-notification track) · ●
New generation online2027-05-28 (1 mo before)12 mo after (n=1)2026-02-09on record in timeApollo on-site gas plant construction starts · ◐
Major equipment on site2026-12-28 (6 mo before)9 mo after (n=1)no public dateno public date · would need to be done by 2026-12-28No date on record
Building ready for IT2027-06-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2027-06-28No date on record
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-04-09 Site securedData center announced ($800m) · ◐
2025-11-05 Permits in handApollo plant filed with the Ohio Power Siting Board (letter-of-notification track) · ●
2026-02-03 Permits in handOPSB authorizes the 350 MW Apollo gas plant (6 recip engines, 21 turbines, 120 MW storage) without hearings · ●
2026-02-09 New generation onlineApollo on-site gas plant construction starts · ◐
2027-06-30 plan First powerPartial energization from Apollo (planned mid-2027) · ◐
2027-12-31 plan New generation onlineApollo full operation, campus at full capacity (planned) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbine—21—under construction2026-02-09Apollo plant (Will-Power OH): 21 turbines + 6 recip engines + 2 diesel emergency engines; 350 MW; partial operation mid-2027 · ●
gas reciprocating engine—6—under construction2026-02-09Apollo plant · ●
battery storage——120 MWunder construction2026-02-09About 120 MW of BESS at the Apollo plant · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-11-01—Land clearing begins.
2026-02-14—Buildings 1 and 2 under construction. Building 1's chillers are almost all in place, while only half of Building 2's are. Optimus substation, which is the substation on site, and the expansion of Dowling Substation, an e
2026-07-30—Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the [Apollo Power Generation Projec
2027-02-01 est.86 MWBuilding 1 is operational, based on a 5 month extrapolation from its roof completion date.
2027-04-01 est.163 MWBuilding 2 is operational, based on construction progress as of Sep 2026 and foundations being laid around 2 months after Building 1.
2028-01-01 est.422 MWBuildings 3 and 4 are operational, based on their construction starting 11 months after Building 1. We assume they are powered by the 350 MW Apollo Power Generation Project.

Recorded fact No public date for major equipment on site, building ready for it.

Calculated requirement Major equipment on site must finish by 2026-12-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2027-06-30 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Meta letter to Middleton Township · Construction notice for new transmission lines to data center substation · Ohio Power Siting Board announcement · Apollo Power Generation Project Letter of Notice Appendix A, with a project timeline

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-bowling-green; include the row and a source link).