Meta Hyperion · Holly Ridge, Richland Parish, LA

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 20260 MW (est.)
Planned end state1.6 GW
First power2028-01-01 (est.)
Build-out complete2028-01-01 (est.)
Power pathGrid, with new utility generation
Binding step New generation online (computed)
First power vs announcedon time (announced 2028-01-01)
Full build-out vs announcedNo announced date on record
Utility / power partnersEntergy Louisiana

Latest: Third unit at Waterford online (planned) · New generation online · 2029-12-31 (plan) · recorded 2026-10-04

Served by Entergy Louisiana. LPSC approved three combined-cycle plants (2,260 MW) on 2025-08-20: two online in 2028, the third (Waterford) in late 2029; a $1.2bn 100-mile 500 kV line plus substations and eight 230 kV lines. In April 2026 the LPSC fast-tracked Entergy's application for seven more gas plants (about 7.5 GW with the first three). First phase announced for 2028; the campus is sized to 2 GW now and up to 5 GW later. · source ● primary, confidence high

Recorded readiness — 4 of 6 applicable milestones have a dated public record

● Land 2024-12● Permits 2026-04● Grid supply 2025-08◐ Generation○ Water· Financing● Construction 2026-04

Gate to first power — target 2028-01-01 (announced) · path: Grid, with new utility generation · each step must finish its lead time before the target

4 of 4 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2026-10-01 (15 mo before)13 mo before (n=26)2024-12-20contextCampus announced (Richland Parish) · ●
Permits in hand (context)2028-01-01 (0 mo before)4 mo after (n=8)2026-04-15contextLPSC fast-tracks seven more gas plants · ●
Grid supply agreed2027-04-01 (9 mo before)7 mo before (n=11)2025-08-20on record in timeLPSC approves Entergy plants, 500 kV line and substations · ●
Substation and lines energized2027-11-01 (2 mo before)15 mo after (n=1)2026-12-01 planplan inside the deadlineNew power stations in service for a 1.8 GW load at Holly Ridge (Epoch timeline note; data center not yet operational) · ◐
New generation online2027-12-01 (1 mo before)12 mo after (n=1)2028-06-30 planplan 7 mo past the deadlineTwo Entergy combined-cycle units online (planned) · ●
Building ready for IT2028-01-01 (0 mo before)2 mo after (n=7)2026-04-19on record in timeBuildings 1 and 2 roofed, cooling at an advanced stage (Epoch timeline) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-12-20 Site securedCampus announced (Richland Parish) · ●
2025-08-20 Grid supply agreedLPSC approves Entergy plants, 500 kV line and substations · ●
2026-04-15 Permits in handLPSC fast-tracks seven more gas plants · ●
2026-04-19 Building ready for ITBuildings 1 and 2 roofed, cooling at an advanced stage (Epoch timeline) · ◐
2026-12-01 plan Substation and lines energizedNew power stations in service for a 1.8 GW load at Holly Ridge (Epoch timeline note; data center not yet operational) · ◐
2028-06-30 plan New generation onlineTwo Entergy combined-cycle units online (planned) · ●
2029-06-30 plan New generation onlineFranklin Farms 1,500 MW combined cycle online mid-2029 per Industrial Info (Entergy's groundbreaking release says late 2028; earlier date kept for the gate) · ◐
2029-12-31 plan New generation onlineThird unit at Waterford online (planned) · ●

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
combined-cycle gas turbine—2 × 754 MW1.5 GWunder construction2028-10-31Entergy Franklin Farms: two 1x1 CCGT units (754 MW each) near Holly Ridge; hydrogen co-firing ready; operational late 2028; turbine OEM not confirmed · ◐
combined-cycle gas turbineMitsubishi Power M501JAC1 × 754 MW754 MWplanned2029-12-31Entergy Waterford units 5-6 (St. Charles Parish) for the same load; late 2029; OEM per Compute Atlas · ○

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-12-20—Land clearing begins.
2025-10-19—Foundations are underway for the main buildings, and the overall layout aligns with the [architectural renderings](https://engineering.fb.com/2025/09/29/data-infrastructure/metas-infrastructure-evolution-and-the-advent-o
2026-04-19—Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress.
2026-12-01 est.—New [power stations](https://drive.google.com/file/d/1D4eUHwEuirNi0g3IU_xGOti3PcC8fcXi/view?usp=sharing) are in service for a 1.8 GW load at Holly Ridge. However, the data center is still not operational.
2028-01-01 est.1.6 GWFirst phase is operational, based on a [Meta blog post](https://drive.google.com/file/d/1PmFNgOwkPepwjpGIbNUuPJP0LNgIqe7l/view?usp=sharing). We assume that this aligns with the three natural gas turbines being completed,

Recorded fact new generation online has a recorded date later than the rule-based deadline for a 2028-01-01 first power.

Calculated requirement Substation and lines energized must finish by 2027-11-01; the recorded plan is 2026-12-01. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2028-07-28 (7 mo after the announced target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Data center profile by Meta · Entergy's application for generation and transmission resources · MISO update with 1.8 GW substation plan · S&P Global ratings research with 2.064 GW campus details

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-hyperion; include the row and a source link).