Meta Prometheus · New Albany, OH

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 2026676 MW (est.)
Planned end state1.0 GW
First power2025-10-14
Build-out complete2028-07-01 (est.)
Power pathHybrid: on-site bridge, then grid
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersWilliams (Will-Power OH); AEP Ohio

Latest: Buildings 22-27 estimated operational (Epoch) · Full build-out complete · 2028-07-01 (plan) · recorded 2026-10-04

1 GW+ campus in New Albany. Behind-the-meter supply from Williams' Socrates South gas plant (about $1.6bn, OPSB-approved; 200 MW firm, 258 MW at design ambient), construction from Q3 2025 with completion estimated Q3 2026, plus AEP grid service; Meta also contracted more than 2.1 GW from Vistra nuclear plants. Reported in September 2025 as due online the following year; Epoch records first power in October 2025. · source ◐ secondary, confidence medium

Recorded readiness — 1 of 6 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply● Generation 2026-09○ Water· Financing○ Construction

Gate to first power — target 2025-10-14 (estimate) · path: Hybrid: on-site bridge, then grid · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
New generation online2025-09-14 (1 mo before)12 mo after (n=1)2026-09-30recorded 13 mo after the deadlineSocrates South on-site gas plant complete (estimated Q3 2026) · ◐
Full build-out complete (context)2026-10-14 (-12 mo before)—2028-07-01 plancontextBuildings 22-27 estimated operational (Epoch) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-10-14 First powerFirst power (Epoch) · ◐
2026-09-30 New generation onlineSocrates South on-site gas plant complete (estimated Q3 2026) · ◐
2028-07-01 plan Full build-out completeBuildings 22-27 estimated operational (Epoch) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbineSolar Turbines (Caterpillar) Titan 2503 × 22 MW66 MWoperating (partial)2026-08-31Socrates South (138.8 MW of nameplate running on 2026-08-31 per infrared drone video; Epoch) (Williams / Will-Power OH): 200 MW firm (258 MW design); construction from Q3 2025; completion estimated Q3 2026 · ◐
gas turbineSolar Turbines (Caterpillar) PGM 1309 × 16 MW144 MWoperating (partial)2026-08-31Socrates South (138.8 MW of nameplate running on 2026-08-31 per infrared drone video; Epoch) · ◐
gas turbineSiemens Energy SGT-4003 × 13 MW39 MWoperating (partial)2026-08-31Socrates South (138.8 MW of nameplate running on 2026-08-31 per infrared drone video; Epoch) · ◐
gas reciprocating engineCaterpillar G352015 × 2.3 MW35 MWoperating (partial)2026-08-31Socrates South (138.8 MW of nameplate running on 2026-08-31 per infrared drone video; Epoch) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2022-04-14—Land clearing begins for Building 1-2
2025-06-01—Roof complete on Building 5 (QTS-owned). In the northernmost area, land clearing begins on a new Meta site for Buildings 16-20. Building 1 still has construction work around the building and cooling equipment, so it's un
2025-09-20—Building 4 operational. Based on our default estimate of roof-to-operational time.
2025-10-1476 MWBuilding 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power at
2026-01-18368 MWBuildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their ri
2026-03-12368 MWThe Socrates South power plant to the right of Buildings 7-12 now has 10 natural gas turbines in place, judging by the number of exhaust stacks. Battery backup has been installed nearby. To the north, a new section of te
2026-05-18368 MWBuilding 7-11 (Meta tents) look structurally complete but not operational, given there is still construction activity, including at the adjacent Socrates South power plant. Northern tents (Buildings 16-27) are all roofed
2026-08-31471 MWBuildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power pl
2026-11-30 est.676 MWSocrates South and Socrates North gas power plants are fully operational, enabling the operability of Buildings 11-12 and 16-21. This completes the 2 sets of 6 tents associated with Socrates South and Socrates North. Thi
2027-01-15 est.740 MWBuilding 13 (Vantage) is operational, based on the pace of construction seen in earlier images.
2027-04-15 est.804 MWBuilding 14 (Vantage) is operational, based on it starting construction about 3 months after Building 13.
2027-07-14 est.868 MWBuilding 15 (Vantage) operational, based on it starting construction about 3 months after Building 14.
2028-07-01 est.1.0 GWBuildings 22-27 (3rd set of 6 Meta tents) are operational. This is a conservative estimate to align with the operability of the [Socrates the Younger](https://drive.google.com/file/d/1Gqu84nBqkyrrwMQy6nSiPykpyQsgLoao/vie

Recorded fact new generation online has a recorded date later than the rule-based deadline for a 2025-10-14 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Meta blog post with details on Prometheus · New Albany Business Park land use map · Letter on Socrates South Power Generation Project

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-prometheus; include the row and a source link).