OpenAI Stargate Wisconsin · Port Washington, WI

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerOracle
UsersOpenAI
IT power, end of 20260 MW
Planned end state902 MW
First power2028-12-31 (est.)
Build-out complete2028-12-31 (est.)
Power pathGrid supply
Binding step Grid interconnection (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedon time (announced 2028-12-31)

Latest: Four buildings complete (announced) · Full build-out complete · 2028-12-31 (plan) · recorded 2026-10-04

Vantage Lighthouse campus, Port Washington: four buildings, close to 1 GW, $15bn+, completion announced for 2028. We Energies' renewables and storage for it are due by end of 2027. ATC's 100-mile transmission line ($1.4bn): the PSC revoked its completeness determination on 2026-08-07 after 500+ amendments, ATC refiled, a decision is expected Q4 2026 and service in late 2027; an analysis puts campus completion no earlier than mid-2028. · source ◐ secondary, confidence medium

Recorded readiness — 2 of 5 applicable milestones have a dated public record

● Land 2025-12○ Permits● Grid supply 2025-12· Generation○ Water· Financing○ Construction

Gate to first power — target 2028-06-30 (estimate) · path: Grid supply · each step must finish its lead time before the target

2 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2027-03-28 (15 mo before)13 mo before (n=26)2025-12-01contextGroundbreaking · ●
Grid supply agreed2027-09-28 (9 mo before)7 mo before (n=11)2025-12-15on record in timeATC transmission application found complete by the PSC (December) · ◐
Substation and lines energized2028-04-28 (2 mo before)15 mo after (n=1)2027-12-15 planplan inside the deadlineATC line in service (late 2027) · ◐
New generation online (context)2028-05-28 (1 mo before)12 mo after (n=1)2027-12-31 plancontextWe Energies renewables and storage for the campus (planned) · ●
Building ready for IT2028-06-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2028-06-28No date on record
Full build-out complete (context)2029-06-28 (-12 mo before)—2028-12-31 plancontextFour buildings complete (announced) · ●
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-12-01 Site securedGroundbreaking · ●
2025-12-15 Grid supply agreedATC transmission application found complete by the PSC (December) · ◐
2026-08-07 Grid supply agreedPSC revokes completeness; ATC must restart the transmission application · ◐
2026-12-15 plan Grid supply agreedPSC decision on the refiled ATC line (expected Q4 2026) · ◐
2027-12-15 plan Substation and lines energizedATC line in service (late 2027) · ◐
2027-12-31 plan New generation onlineWe Energies renewables and storage for the campus (planned) · ●
2028-06-30 plan Grid supply agreedATC transmission line (proposed) · ●
2028-06-30 plan First powerCampus completion now seen no earlier than mid-2028 (analysis) · ○
2028-12-31 plan Full build-out completeFour buildings complete (announced) · ●
2028-12-31 plan Full build-out completeLighthouse campus (four buildings) projected complete Q4 2028; 70% of power from solar, wind and storage · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbine—5 × 220 MW1.1 GWunder construction2028-03-31Same We Energies Oak Creek plant also cited for the Port Washington campus (first four buildings need about 1.3 GW) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2026-01-02—Ground broken for the facility, land clearing begins for all buildings
2026-02-14—Land clearing continues, foundation construction clearly begins for eastern and northern buildings (Building 1-2)
2026-07-24—Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.
2028-12-31 est.902 MWBuilding 4 and supporting facilities/buildings operational, whole facility now operational. Based on the [environmental analysis (page 6)](https://drive.google.com/file/d/1ft2ZzqAYZtsTqMwyML4eo_EFYuclVxE6/view?usp=sharin

Recorded fact No public date for building ready for it.

Calculated requirement Substation and lines energized must finish by 2028-04-28; the recorded plan is 2027-12-15. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2028-06-30 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Data center page on Vantage website · Environmental Analysis Summary

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id openai-stargate-wisconsin; include the row and a source link).