AILoadmapAI gigawatts, campus by campus
← Map · All projects

OpenAI Stargate New Mexico · Doña Ana County, NM

Last change recorded 2026-10-05 · Last checked 2026-10-04

OwnerOracle
UsersOpenAI
IT power, end of 20260 MW
Planned end state1.8 GW
First power2028-12-31 (est.)
Build-out complete2028-12-31 (est.)
Power pathOn-site generation
Binding step Major equipment on site (computed)
First power vs announcedannounced 2026-12-31; current estimate not confirmed
Full build-out vs announcedNo announced date on record

Latest: Emergency authorization to draw from the new well stands after the Supreme Court lifted its stay; permanent water rights still contested · Water supply secured · 2026-09-17 · recorded 2026-10-05

Project Jupiter, Santa Teresa (Doña Ana County): Oracle/OpenAI campus developed by STACK Infrastructure with a Bloom fuel-cell microgrid (up to 2.45 GW) replacing the earlier gas turbines. Air permit: NMED hearing was moved to September, then stayed by the New Mexico Supreme Court on 2026-08-23 (together with the emergency well authorization); the stay was lifted on 2026-09-17 and the hearing re-set for 2026-10-19 with comments due 2026-10-23. In September 2026 Oracle issued a force majeure notice to the developer over schedule risk (gas pipeline in-service pushed from August 2026 to February 2027, air permit pending) while stating publicly that the project remains on schedule and reaffirming the 2.4 GW Bloom contract. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 5 applicable milestones have a dated public record

● Land 2025-09● Permits 2026-01· Grid supply◐ Generation● Water 2026-09· Financing○ Construction

Gate to first power — target 2026-12-31 (announced) · path: On-site generation · each step must finish its lead time before the target

3 of 4 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-09-28 (15 mo before)13 mo before (n=26)2025-09-01contextConstruction begins · ◐
Permits in hand2026-12-28 (0 mo before)4 mo after (n=8)2026-01-15on record in timeAir permit application filed for gas turbines and diesel (January 2026) · ◐
New generation online2026-11-28 (1 mo before)12 mo after (n=1)2026-12-31 planplan inside the deadlineFuel-cell microgrid first block (announced initial operations) · ◐
Major equipment on site2026-06-28 (6 mo before)9 mo after (n=1)2027-02-28 planplan 8 mo past the deadlineNatural-gas pipeline feeding the microgrid in service (delayed from August 2026 per reporting on Oracle's force majeure notice) · ◐
Building ready for IT2026-12-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2026-12-28No date on record
Full build-out complete (context)2027-12-28 (-12 mo before)—2028-12-31 plancontextEstimated completion (Epoch) · ◐
Water supply secured (context)2025-12-28 (12 mo before)—2026-09-17contextEmergency authorization to draw from the new well stands after the Supreme Court lifted its stay; permanent water rights still contested · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-09-01 Site securedConstruction begins · ◐
2025-09-01 Site securedConstruction begins; $165bn industrial revenue bond approved · ◐
2026-01-15 Permits in handAir permit application filed for gas turbines and diesel (January 2026) · ◐
2026-04-27 Permits in handPower plan switched to a 2.45 GW Bloom fuel-cell microgrid (not yet built, no construction permit) · ○
2026-08-23 Permits in handNew Mexico Supreme Court stays the NMED air permit hearing and the emergency well authorization · ◐
2026-09-17 Permits in handSupreme Court lifts the stay; air permit hearing re-set for 2026-10-19, public comments due 2026-10-23 · ◐
2026-09-17 Water supply securedEmergency authorization to draw from the new well stands after the Supreme Court lifted its stay; permanent water rights still contested · ◐
2026-10-19 plan Permits in handNMED air-permit public hearing on the fuel-cell plan · ◐
2026-12-31 plan New generation onlineFuel-cell microgrid first block (announced initial operations) · ◐
2027-02-28 plan Major equipment on siteNatural-gas pipeline feeding the microgrid in service (delayed from August 2026 per reporting on Oracle's force majeure notice) · ◐
2028-12-31 plan Full build-out completeEstimated completion (Epoch) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
fuel cellBloom Energy solid-oxide fuel cell—2.5 GWpermit pending2026-10-19Up to 2.45 GW fuel-cell microgrid replacing gas turbines and diesel; construction permit not yet issued; NMED hearing 2026-10-19. September 2026: Oracle sent the developer a force majeure notice over schedule risk (gas pipeline in-service pushed to February 2027, air permit pending) while reaffirming the 2.4 GW Bloom contract · ○

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-10-01—Construction and land clearing begins
2026-02-06—Land clearing continues, foundation construction begins 2 of the main buildings (Building B & D). Construction also beginning on modular chiller plants.
2026-06-22—Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large s
2028-12-31 est.1.8 GWEstimated construction completion date of the site. Stormwater permitting says 2027-12-31 for stormwater construction to finish, but for a more conservative estimate and based on the current state of the site, we pushed

Recorded fact major equipment on site has a recorded date later than the rule-based deadline for a 2026-12-31 first power.

Calculated requirement Major equipment on site must finish by 2026-06-28; the recorded plan is 2027-02-28 (8 mo past the deadline). Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2027-08-28 (8 mo after the announced target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Project Jupiter Website · Stormwater Permitting · Oracle, BorderPlex and Bloom Energy to power Project Jupiter with fuel cell technology (Apr 27, 2026)

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id openai-stargate-new-mexico; include the row and a source link).