OpenAI Stargate Abilene · Abilene, TX

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerOracle
UsersOpenAI
IT power, end of 2026843 MW (est.)
Planned end state843 MW
First power2025-09-26
Build-out complete2026-11-01 (est.)
Power pathHybrid: on-site bridge, then grid
Binding step Equipment delivery (from reporting)
First power vs announcedon time (announced 2025-09-30)
Full build-out vs announced+4 months (announced 2026-06-30)
Utility / power partnersAEP Texas; Crusoe

Latest: Buildings 5-8 estimated operational (Epoch) · Full build-out complete · 2026-11-01 (plan) · recorded 2026-10-04

Crusoe campus for Oracle/OpenAI. Two buildings (200+ MW) live September 2025; six more buildings to 1.2 GW across eight were announced for completion by end of 2026 (Epoch estimates the last buildings in November 2026). Air permit covers about 360 MW of behind-the-meter simple-cycle turbines (ten units) for on-site use; the rest is AEP grid power including local wind. Parker Hannifin equipment for more than 1 GW of gas turbines was announced for the campus. A third Crusoe campus of 900 MW for Microsoft was announced next door on 2026-03-27. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2024-05○ Permits○ Grid supply● Generation 2026-06○ Water· Financing● Construction 2025-09

Gate to first power — target 2025-09-30 (announced) · path: Hybrid: on-site bridge, then grid · each step must finish its lead time before the target

2 of 2 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2024-06-28 (15 mo before)13 mo before (n=26)2024-05-31contextSite work begins · ◐
Major equipment on site2025-03-28 (6 mo before)9 mo after (n=1)2026-06-30recorded 15 mo after the deadlineOn-site turbine fleet beyond the first 360 MW (announced, >1 GW of turbines) · ◐
Building ready for IT2025-09-28 (0 mo before)2 mo after (n=7)2025-09-26on record in timeFirst two buildings live (200+ MW) · ◐
Full build-out complete (context)2026-09-28 (-12 mo before)—2026-11-01 plancontextBuildings 5-8 estimated operational (Epoch) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-05-31 Site securedSite work begins · ◐
2025-09-26 Building ready for ITFirst two buildings live (200+ MW) · ◐
2026-03-09 Site securedOracle and OpenAI drop the planned 600 MW expansion (financing terms); the eight-building 1.2 GW campus continues, phase 2 due by end-2026 · ◐
2026-06-30 Major equipment on siteOn-site turbine fleet beyond the first 360 MW (announced, >1 GW of turbines) · ◐
2026-11-01 plan Full build-out completeBuildings 5-8 estimated operational (Epoch) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbineSolar Turbines (Caterpillar) Titan 3505 × 38 MW190 MWoperating2025-09-26Behind-the-meter simple-cycle fleet under the TCEQ standard permit approved 2025-01-22 · ◐
gas turbineGE Vernova LM25005 × 34.1 MW171 MWoperating2025-09-26Aeroderivative units in the same 360 MW standard-permit fleet · ◐
diesel genset—62—operating2025-09-26Backup diesel generators on the existing campus · ◐
gas turbine—411.4 GWpermit pending2026-07-15Major TCEQ permit filed July 2026 for 41 more turbines (about 1.4 GW) plus 18 diesel gensets; contested by residents · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-05-31—Land clearing begins for northern two buildings (Building 1-2)
2025-06-28—Building 1 looks close to finishing construction, with chillers in place. OpenAI [stated](https://openai.com/index/five-new-stargate-sites/) that "Oracle began delivering the first NVIDIA GB200 racks in June." The "tenan
2025-09-26105 MWBuilding 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe [announcement](https://www.crusoe.ai/resources/newsroom/crusoe-announces-flagship-abilene-data-center-is-liv
2025-12-24211 MWBuilding 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a [TDLR filing](https://www.tdlr.texas.gov/T
2026-01-15211 MWThe 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation in 3 months. Building
2026-03-24211 MWBuilding 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according to a [regulatory fili
2026-05-23421 MWBuildings 3 and 4 are estimated to be operational. On April 22nd, Oracle [posted](https://x.com/i/status/2047012589302153558) that "In Abilene, 200MW is already operational". This suggests that there was still only Build
2026-07-28421 MWBuildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete.
2026-11-01 est.843 MWBuildings 5-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Buil

Recorded fact major equipment on site has a recorded date later than the rule-based deadline for a 2025-09-30 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Crusoe 2024 Impact Report, with details on Abilene · Air Permit Application for buildings 1-2, featuring blueprints on p.157 · Mortensen’s profile of the project, with details of substations

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id openai-stargate-abilene; include the row and a source link).