Microsoft Fairwater Wisconsin · Mount Pleasant, WI

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMicrosoft
UsersOpenAI, Microsoft
IT power, end of 2026369 MW
Planned end state2.3 GW
First power2026-04-16
Build-out complete2028-05-13 (est.)
Power pathGrid supply
Binding step Grid interconnection (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersWe Energies (WEC)

Latest: Second Fairwater facility under construction for 2028 · Full build-out complete · 2028-12-31 (plan) · recorded 2026-10-04

Grid supply from We Energies (WEC expects about 2.6 GW of new Microsoft demand on the I-94 corridor; Fairwater is the largest single load Wisconsin Electric has served). First building completed June 2026 for AI training, second under construction for 2028, 15 more approved. The Microsoft-We Energies contract kept a provision the PSC had struck down (reported August 2026). · source ◐ secondary, confidence medium

Recorded readiness — 3 of 5 applicable milestones have a dated public record

● Land 2023-07○ Permits● Grid supply 2026-08· Generation○ Water· Financing● Construction 2026-06

Gate to first power — target 2026-04-16 (estimate) · path: Grid supply · each step must finish its lead time before the target

2 of 2 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-01-16 (15 mo before)13 mo before (n=26)2023-07-14contextSite work begins · ◐
Grid supply agreed2025-07-16 (9 mo before)7 mo before (n=11)2026-08-09recorded 13 mo after the deadlinePSC contract terms disputed · ◐
Building ready for IT2026-04-16 (0 mo before)2 mo after (n=7)2026-06-23on record in timeFirst building complete · ◐
Full build-out complete (context)2027-04-16 (-12 mo before)—2028-05-13 plancontextBuildings 3-11 estimated operational (Epoch) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2023-07-14 Site securedSite work begins · ◐
2026-04-16 First powerFirst power (Epoch) · ◐
2026-06-23 Building ready for ITFirst building complete · ◐
2026-06-23 Building ready for ITFirst Fairwater building fully operational (Microsoft); startup work began in April 2026 · ◐
2026-08-09 Grid supply agreedPSC contract terms disputed · ◐
2028-05-13 plan Full build-out completeBuildings 3-11 estimated operational (Epoch) · ◐
2028-12-31 plan Full build-out completeSecond Fairwater facility under construction for 2028 · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbine—5 × 220 MW1.1 GWunder construction2028-03-31We Energies Oak Creek plant: five 220 MW combustion turbines ($1.2bn), PSC approved May 2025; first turbine delivery May 2026; operation winter 2027 to summer 2028; sized for the I-94 corridor data centers · ◐
gas reciprocating engine——128 MWunder construction2027-12-31We Energies Paris RICE plant ($280m) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2023-07-14—Land clearing begins for Building 1.
2025-09-26—Building 1 cooling and backup generators all look complete from above but there is still construction visible around the building. Building 2 is well underway with a foundation and a complete substation. Large carpark an
2026-01-28—Building 1 looks complete, but based on Microsoft announcements, it's not fully operational yet. Steel framing is underway for Building 2.
2026-04-16369 MWBuilding 1 is operational. [X post](https://x.com/satyanadella/status/2044767391293509761?s=61) from Microsoft saying this date for Fairwater becoming operational.
2026-05-15369 MWThe main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new [9-building design](https://www.mtpleasantwi.gov
2027-02-20 est.737 MWBuilding 2 is operational. This is estimated based on (1) the delay between Building 1 and Building 2 starting land clearing, (2) in March 2025, a Microsoft spokesperson [said](https://www.wpr.org/news/microsoft-pauses-c
2028-05-13 est.2.3 GWBuildings 3-11 are estimated to be operational. The grading for this revised 9-building plan was underway in May 2026, and we assume an average 2-year [build time](https://epoch.ai/data-insights/data-centers-buildout-spe

Recorded fact grid supply agreed has a recorded date later than the rule-based deadline for a 2026-04-16 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Microsoft blog with engineering details · Microsoft blog with more general information · Construction Permit Application for building 1 · Plan for 9-building and 6-building expansions · OpenAI article mentioning they use Microsoft's Fairwater supercomputers

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id microsoft-fairwater-wisconsin; include the row and a source link).