Colossus 1 · South Memphis, TN

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerSpaceXAI
UsersAnthropic
IT power, end of 2026340 MW
Planned end state340 MW
First power2024-08-11
Build-out completeno further build-out tracked
Power pathHybrid: on-site bridge, then grid
Binding step Permitting (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersMLGW (TVA); Solaris Energy Infrastructure

Latest: Third MLGW substation expected to power the building · Substation and lines energized · 2025-11-07 · recorded 2026-10-04

Built in 122 days; 35 portable gas turbines on site plus MLGW service; turbine air permits disputed (Sherwood News, Sept 2025) · source ◐ secondary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

○ Land● Permits 2025-07● Grid supply 2025-11○ Generation○ Water· Financing● Construction 2024-04

Gate to first power — target 2024-08-11 (estimate) · path: Hybrid: on-site bridge, then grid · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Permits in hand2024-08-11 (0 mo before)4 mo after (n=8)2025-07-02recorded 11 mo after the deadlineAir permit for gas turbines (Shelby County, July 2025) · ◐
Substation and lines energized (context)2024-06-11 (2 mo before)15 mo after (n=1)2025-11-07contextThird MLGW substation expected to power the building · ◐
Construction started (context)2022-08-11 (24 mo before)29 mo before (n=15)2024-04-24contextConstruction starts in a former Electrolux plant · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-04-24 Construction startedConstruction starts in a former Electrolux plant · ◐
2024-08-11 First powerFirst training workload (35 MW) · ◐
2025-07-02 Permits in handAir permit for gas turbines (Shelby County, July 2025) · ◐
2025-11-07 Substation and lines energizedThird MLGW substation expected to power the building · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbineSolar Turbines (Caterpillar) Titan 130 (SMT-130)14 × 16.5 MW231 MWoperating2025-07-02As-built fleet per MeasuredAI; Shelby County air permit granted July 2025 for the permanent turbines · ○
gas turbineGE Vernova TM250027 × 34 MW—operating2025-07-02Aeroderivative trailer units reported in the as-built configuration (fleet count not confirmed by the permit) · ○

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-04-24—Construction starts with a road added on site, retrofitting a former Electrolux building.
2024-08-1135 MWFirst [significant/useful training workload](https://x.ai/colossus) on 25k H100s.
2024-09-02139 MW[100k H100s online](https://archive.is/z39uN).
2025-02-17278 MW150k H100s and 50k H200s online. This is roughly when [Musk](https://archive.is/z39uN) [said](https://archive.is/z39uN), plus on this date they reported "running jobs with 150K+ GPUs".
2025-03-06278 MWSecond substation almost connected (red cables)
2025-07-22340 MW30k B200s [added](https://archive.is/oHQSA) (in GB200 configuration).
2025-09-17268 MWThird substation looks completed, but it doesn't appear to be connected to the building yet. Some air-cooled chillers removed, while large cooling towers are added.
2025-10-19268 MWThere is still construction visible in the third substation yard and next to the new cooling towers.
2025-11-07340 MWThird substation was expected to power the building in Fall.
2026-02-11340 MWAll air-cooled chillers have been disconnected and/or removed from the site, leaving only the cooling towers for cooling. The third substation looks complete, with red cables connected to the building.
2026-05-06340 MWAnthropic [announces](https://www.anthropic.com/news/higher-limits-spacex) their agreement with SpaceX to use all of the compute capacity at Colossus 1. They state that this corresponds to more than 300 MW (presumably IT
2026-06-01340 MWWe assume that Anthropic has started using Colossus 1 now, since the announcement said they would get access to 300 MW "within the month" of May.
2026-06-15340 MWNo major changes to the data center since February. Solar panels have been placed next to the facility.

Recorded fact permits in hand has a recorded date later than the rule-based deadline for a 2024-08-11 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): May 2025 Electricity Provider Disclosure · July 2025 Permit for Gas Turbines · Southern Environmental Law Center Gas Permit Appeal, with additional satellite images · Disclosure on X (formerly Twitter) by Elon Musk of the breakdown of GPUs · Anthropic announcement

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id colossus-1; include the row and a source link).