Amazon Ridgeland · Ridgeland, MS

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerAmazon
UsersAnthropic
IT power, end of 2026228 MW
Planned end state840 MW
First power2026-05-15
Build-out complete2028-09-29 (est.)
Power pathGrid, with new utility generation
Binding step New generation (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersEntergy Mississippi

Latest: Buildings 6-14 estimated operational (Epoch) · Full build-out complete · 2028-09-29 (plan) · recorded 2026-10-04

One of two AWS campuses in Madison County (with Canton), together 2.2 GW of facility power and at least $21bn. Entergy Mississippi signed the large-customer agreement on 2024-03-08 and in 2025 announced three new gas plants (Greenville, Ridgeland, Vicksburg) and two solar farms, nearly $4bn. The Ridgeland expansion was announced in April 2026 and has drawn opposition from Mississippi power companies. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2026-04○ Permits● Grid supply 2024-03○ Generation○ Water· Financing● Construction 2026-08

Gate to first power — target 2026-05-15 (estimate) · path: Grid, with new utility generation · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-02-15 (15 mo before)13 mo before (n=26)2026-04-09contextRidgeland expansion announced ($12bn) · ◐
Grid supply agreed2025-08-15 (9 mo before)7 mo before (n=11)2024-03-08on record in timeEntergy Mississippi large-customer agreement · ◐
Construction started (context)2024-05-15 (24 mo before)29 mo before (n=15)2026-08-15contextPhase II: stormwater coverage issued for about 245 acres; construction estimated through August 2028 (Haskell) · ○
Full build-out complete (context)2027-05-15 (-12 mo before)—2028-08-31 plancontextPhase II construction complete (estimate from the stormwater filing) · ○

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-03-08 Grid supply agreedEntergy Mississippi large-customer agreement · ◐
2026-04-09 Site securedRidgeland expansion announced ($12bn) · ◐
2026-05-15 First powerFirst power (Epoch) · ◐
2026-08-15 Construction startedPhase II: stormwater coverage issued for about 245 acres; construction estimated through August 2028 (Haskell) · ○
2028-08-31 plan Full build-out completePhase II construction complete (estimate from the stormwater filing) · ○
2028-09-29 plan Full build-out completeBuildings 6-14 estimated operational (Epoch) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
combined-cycle gas turbineMitsubishi Power M501JAC1 × 754 MW754 MWplanned2029-12-31Entergy Mississippi Traceview Advanced Power Station (Ridgeland): 1x1 CCGT; in service 2029; part of three 754 MW plants and two solar farms (~$4bn) tied to the Amazon load · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-02-24—Land clearing begins
2025-10-04—Roof complete on Buildings 3
2026-05-15228 MWBuildings 1-4 are operational, based on the buildings shells and backup generators and most of the landscaping looking complete. Building 5 roof is complete but still lacks cooling equipment.
2027-02-09 est.284 MWBuilding 5 is operational (estimate).
2028-09-29 est.840 MWBuildings 6-14 are operational (estimate). Buildings 1-4 took an estimated 2.25 years on this site. We assume Buildings 6-14 get underway by July 2026, and take the same time as Buildings 1-4. This is later than the [exp

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Air Construction Permit · Permit review document · Backup diesel generator referenced in the permit · New York Times article on Project Rainier

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id amazon-ridgeland; include the row and a source link).