QTS Eagle Mountain · Eagle Mountain, UT

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 2026203 MW (est.)
Planned end state304 MW
First power2026-12-31 (est.)
Build-out complete2027-07-01 (est.)
Power pathGrid supply
Binding step Grid interconnection (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announced+6 months (announced 2026-12-31)
Utility / power partnersRocky Mountain Power

Latest: Build-out complete (Epoch estimate) · Full build-out complete · 2027-07-01 (plan) · recorded 2026-10-04

193-acre campus: buildings 1-3 under construction since fall 2025 (building 3 topped out 2026-04-17), completion expected by the end of 2026; buildings 4-5 follow over several years. Grid-served by Rocky Mountain Power with QTS paying for the infrastructure; a 200 MW on-site gas plant was approved by the city but QTS says it secured Rocky Mountain Power supply instead. · source ● primary, confidence medium

Recorded readiness — 3 of 5 applicable milestones have a dated public record

○ Land● Permits 2025-02● Grid supply 2025-09· Generation○ Water· Financing● Construction 2025-10

Gate to first power — target 2026-12-31 (estimate) · path: Grid supply · each step must finish its lead time before the target

2 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Permits in hand (context)2026-12-28 (0 mo before)4 mo after (n=8)2025-02-04contextDevelopment agreement amended to allow on-site generation · ◐
Grid supply agreed2026-03-28 (9 mo before)7 mo before (n=11)2025-09-01on record in timeRocky Mountain Power supply secured; QTS funds the infrastructure · ◐
Substation and lines energized2026-10-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2026-10-28No date on record
Construction started (context)2024-12-28 (24 mo before)29 mo before (n=15)2025-10-01contextConstruction starts (fall 2025) · ◐
Building ready for IT2026-12-28 (0 mo before)2 mo after (n=7)2026-04-17on record in timeBuilding 3 topped out · ●
Full build-out complete (context)2027-12-28 (-12 mo before)—2027-07-01 plancontextBuild-out complete (Epoch estimate) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-02-04 Permits in handDevelopment agreement amended to allow on-site generation · ◐
2025-02-04 Permits in handDevelopment agreement amended to allow on-site generation (200 MW gas plant approved later) · ◐
2025-09-01 Grid supply agreedRocky Mountain Power supply secured; QTS funds the infrastructure · ◐
2025-10-01 Construction startedConstruction starts (fall 2025) · ◐
2026-04-17 Building ready for ITBuilding 3 topped out · ●
2026-12-31 plan First powerFirst power (Epoch estimate) · ◐
2027-07-01 plan Full build-out completeBuild-out complete (Epoch estimate) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbine——200 MWapproved (not pursued)2025-06-30City approved a 20-acre 200 MW gas plant; QTS says it secured Rocky Mountain Power supply instead · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2023-10-01—First signs of site preparation show up on satellite imagery.
2025-09-08—Site preparation continues. Outline of a first building that is not the data center of interest Buildings 1 or 2 is visible.
2026-05-02—Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emerg
2026-12-31 est.203 MWWe estimate Buildings 1 and 2 will be fully operational by the end of 2026 because there are at least seven months since cooling and emergency generators have started to be installed. This estimate is also in line with s
2027-07-01 est.304 MWWe estimate Building 3 will be fully operational by H2 2027 following a similar time line to Buildings 1 and 2 of 14 months from land clearing to operational.

Recorded fact No public date for substation and lines energized.

Calculated requirement Substation and lines energized must finish by 2026-10-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2026-12-31 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): QTS Eagle Mountain website · DEQ Approval listing emergency generators

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id qts-eagle-mountain; include the row and a source link).