AILoadmapAI gigawatts, campus by campus
← Map · All projects

Haenam Solar City AI Data Center · Haenam, Jeollanam-do, South Korea

Last change recorded — · Last checked 2026-10-05

OwnerStock Farm Road
Users—
IT power, end of 20260 MW
Planned end state3.0 GW
First power2028-12-31 (est.)
Build-out complete2028-12-31 (est.)
Power pathHybrid: on-site bridge, then grid
Binding step 5 required steps without a date
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersNo data yet

Jeollanam-do's 3 GW AI data center (Fir Hills / Stock Farm Road, up to $35bn, Nvidia partnership) on the Solar City reclaimed-land site; approved February 2025, completion targeted for 2028, but reporting in July 2026 said detailed plans were still unclear. Separately, the government's National AI Computing Center (2.4 trn won, 15,000 GPUs by 2028) broke ground at Haenam on 2026-08-03. No first-power date published for the 3 GW project. · source ◐ secondary, confidence low

Recorded readiness — 1 of 7 applicable milestones have a dated public record

● Land 2025-02○ Permits○ Grid supply○ Generation○ Water○ Financing○ Construction

Gate to first power — target 2028-12-31 (estimate) · path: Hybrid: on-site bridge, then grid · each step must finish its lead time before the target

0 of 5 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2027-09-28 (15 mo before)13 mo before (n=26)2025-02-16contextCampus announced (reported) · ◐
Permits in hand2028-12-28 (0 mo before)4 mo after (n=8)no public dateno public date · would need to be done by 2028-12-28No date on record
Grid supply agreed2028-03-28 (9 mo before)7 mo before (n=11)no public dateno public date · would need to be done by 2028-03-28No date on record
New generation online2028-11-28 (1 mo before)12 mo after (n=1)no public dateno public date · would need to be done by 2028-11-28No date on record
Major equipment on site2028-06-28 (6 mo before)9 mo after (n=1)no public dateno public date · would need to be done by 2028-06-28No date on record
Building ready for IT2028-12-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2028-12-28No date on record
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-02-16 Site securedCampus announced (reported) · ◐
2028-12-31 plan First powerFirst phase online (announced plan) · ◐

Build-out timeline (announced phases from public reporting; rows after today are plans)

2028-12-31 est.3.0 GWFirst phase online (announced plan)

Recorded fact No public date for permits in hand, grid supply agreed, new generation online, major equipment on site, building ready for it.

Calculated requirement Grid supply agreed must finish by 2028-03-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2028-12-31 (on the target). This is a floor set by the record, not a forecast.

Sources: Pouring in 17 trillion won but detailed plans still unclear: the dilemma of Haenam's SolarCity (Asia Business Daily, 2026-07-23)

Campus outside the Epoch AI dataset: facts from the public reporting linked above (tools/campuses.csv), coordinates hand-entered. Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id haenam-solar-city-ai-data-center; include the row and a source link).