Anthropic-Amazon New Carlisle · New Carlisle, IN

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerAmazon
UsersAnthropic
IT power, end of 20261.0 GW (est.)
Planned end state1.9 GW
First power2025-06-23
Build-out complete2028-03-17 (est.)
Power pathGrid, with new utility generation
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersIndiana Michigan Power (AEP)

Latest: Buildings 19-32 estimated operational (Epoch) · Full build-out complete · 2028-03-17 (plan) · recorded 2026-10-04

Project Rainier: announced April 2024 ($11bn), online October 2025 with about 500k Trainium2 chips for Anthropic; 2.2 GW across 30 buildings planned. Served by Indiana Michigan Power, its largest customer ever; I&M is acquiring a gas plant in Oregon, Ohio to help serve the load. South-campus site prep (substation, pads) began Q1 2026. · source ◐ secondary, confidence medium

Recorded readiness — 2 of 6 applicable milestones have a dated public record

● Land 2024-04○ Permits○ Grid supply○ Generation○ Water· Financing● Construction 2025-10

Gate to first power — target 2025-06-23 (estimate) · path: Grid, with new utility generation · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2024-03-23 (15 mo before)13 mo before (n=26)2024-04-01contextCampus announced · ◐
Building ready for IT2025-06-23 (0 mo before)2 mo after (n=7)2025-10-29recorded 4 mo after the deadlineCampus opened · ◐
Full build-out complete (context)2026-06-23 (-12 mo before)—2028-03-17 plancontextBuildings 19-32 estimated operational (Epoch) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-04-01 Site securedCampus announced · ◐
2025-06-23 First powerFirst power (Epoch) · ◐
2025-10-29 Building ready for ITCampus opened · ◐
2026-03-01 Site securedSouth campus site prep and substation · ◐
2028-03-17 plan Full build-out completeBuildings 19-32 estimated operational (Epoch) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
combined-cycle gas turbine—1 × 870 MW870 MWacquired2026-12-31I&M purchase of the Oregon Clean Energy Center (870 MW, Oregon OH) approved by the IURC; part of the plan to serve the 2.25 GW campus · ●
combined-cycle gas turbine—1 × 1520 MW1.5 GWproposed2030-06-30I&M Rockport Energy Center (1, 520 MW CCGT) filed July 2026; construction 2027 and service summer 2030 if approved · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-02-09—Land clearing begins in the northern section
2024-06-10—Land clearing begins in the southern section
2025-05-10—Roof complete on building 11
2025-06-23398 MWBuildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.
2025-09-26398 MWRoof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car par
2025-10-17398 MWConfirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an [interview](https://www.youtube.com/watch?v=jwgW_gHI1Vs&t=220s), AWS CEO says "they're already running...about 500,000 [Trainium2] c
2025-12-23626 MWBuildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.
2026-02-09626 MWBuildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines o
2026-03-23910 MWBuildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.
2026-06-03910 MWBuildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.
2026-10-19 est.1.0 GWBuildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to acco
2028-03-17 est.1.9 GWBuildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundation of several buildings and a substation was visible at the site of Buildings 19-

Recorded fact building ready for it has a recorded date later than the rule-based deadline for a 2025-06-23 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Air Construction Permit application for the northern portion · Backup diesel generator referenced in the permit · Announcement of Project Rainier coming online · Air permit for Buildings 19-32, suggesting expansion to 2.3 GW total facility power

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id anthropic-amazon-new-carlisle; include the row and a source link).