OpenAI Stargate Milam · Milam County, TX

Last change recorded 2026-10-05 · Last checked 2026-10-04

OwnerSoftbank
UsersOpenAI
IT power, end of 20260 MW
Planned end state857 MW
First power2028-12-31 (est.)
Build-out complete2028-12-31 (est.)
Power pathHybrid: on-site bridge, then grid
Binding step 3 required steps without a date
First power vs announcedannounced 2026-10-31; current estimate not confirmed
Full build-out vs announcedon time (announced 2028-12-31)
Utility / power partnersSB Energy

Latest: OpenAI and SoftBank commit $1bn to SB Energy for the 1.2 GW Milam County site · Financing closed · 2026-01-09 · recorded 2026-10-05

SB Energy (SoftBank) builds and operates the 1.2 GW fast-build Stargate site in Milam County next to its 900 MWdc Orion Solar Belt (operating since October 2024 under a Google PPA); new on-site solar and storage are to supply most of the campus. Ground broken October 2025; SoftBank and OpenAI each invested $500m in SB Energy in January 2026. March 2026 imagery shows steel and roofing on building 1, with filings pointing to delivery by October 2026; completion projected Q4 2028. · source ◐ secondary, confidence medium

Recorded readiness — 4 of 7 applicable milestones have a dated public record

● Land 2026-01○ Permits○ Grid supply● Generation 2024-10○ Water● Financing 2026-01● Construction 2025-10

Gate to first power — target 2026-10-31 (announced) · path: Hybrid: on-site bridge, then grid · each step must finish its lead time before the target

2 of 5 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-07-28 (15 mo before)13 mo before (n=26)2026-01-09contextSB Energy partnership and $1bn investment · ◐
Permits in hand2026-10-28 (0 mo before)4 mo after (n=8)no public dateno public date · would need to be done by 2026-10-28No date on record
Grid supply agreed2026-01-28 (9 mo before)7 mo before (n=11)no public dateno public date · would need to be done by 2026-01-28No date on record
New generation online2026-09-28 (1 mo before)12 mo after (n=1)2024-10-01on record in timeAdjacent Orion Solar Belt (900 MWdc) in commercial operation · ◐
Major equipment on site2026-04-28 (6 mo before)9 mo after (n=1)no public dateno public date · would need to be done by 2026-04-28No date on record
Construction started (context)2024-10-28 (24 mo before)29 mo before (n=15)2025-10-15contextGround broken (October 2025) · ◐
Building ready for IT2026-10-28 (0 mo before)2 mo after (n=7)2026-10-31 planplan inside the deadlineFirst building delivery (regulatory filings) · ◐
Full build-out complete (context)2027-10-28 (-12 mo before)—2028-12-31 plancontextCompletion (projected Q4 2028) · ◐
Financing closed (context)2025-10-28 (12 mo before)12 mo before (n=2)2026-01-09contextOpenAI and SoftBank commit $1bn to SB Energy for the 1.2 GW Milam County site · ●
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-10-01 New generation onlineAdjacent Orion Solar Belt (900 MWdc) in commercial operation · ◐
2025-10-15 Construction startedGround broken (October 2025) · ◐
2026-01-09 Site securedSB Energy partnership and $1bn investment · ◐
2026-01-09 Financing closedOpenAI and SoftBank commit $1bn to SB Energy for the 1.2 GW Milam County site · ●
2026-10-31 plan Building ready for ITFirst building delivery (regulatory filings) · ◐
2026-10-31 plan Building ready for ITFirst building delivered by October 2026 (regulatory filings cited by Epoch) · ◐
2028-12-31 plan Full build-out completeCompletion (projected Q4 2028) · ◐
2028-12-31 plan Full build-out complete1.2 GW campus complete (Q4 2028) · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
solarSB Energy——planned2028-12-31New on-site solar and battery storage by SB Energy to supply most of the 1.2 GW campus; sizes not disclosed; adjacent Orion Solar Belt 900 MWdc operating · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-09-27—Land clearing begins for the site
2026-01-04—Small sections of building foundation construction begins, and land clearing appears to be mostly finished
2026-03-23—Steel framing and roofing is underway for Building 1.
2028-12-31 est.857 MWAll buildings finished, site is fully operational. Our reasoning is that examples so far take a median of 2-2.5 years to go from land clearing to 1 GW. This suggests around 2028-01-01 here. However, due to delays being m

Recorded fact No public date for permits in hand, grid supply agreed, major equipment on site.

Calculated requirement Grid supply agreed must finish by 2026-01-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2026-10-31 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Data Center Dynamics article on the site · SB Energy article, source for 1.2 GW capacity · TDLR page for the first building of the site, indicating construction completion date

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id openai-stargate-milam; include the row and a source link).