Colossus 2 · South Memphis, TN

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerSpaceXAI
UsersAnthropic, Cursor, SpaceXAI
IT power, end of 2026946 MW
Planned end state1.5 GW
First power2025-10-19
Build-out complete2027-02-25 (est.)
Power pathHybrid: on-site bridge, then grid
Binding step Permitting (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersMLGW (TVA); Solaris Energy Infrastructure

Latest: Temporary turbine permit expires · Permits in hand · 2027-12-31 (plan) · recorded 2026-10-04

Operational since late 2025 (Epoch: first power October 2025; press: January 2026). Power from Solaris Energy Infrastructure gas turbines (about 400 MW serving xAI of a 1.1 GW+ programme by Q2 2027) plus two MLGW substations on the campus. MDEQ approved an air permit on 2026-03-10 for 41 permanent turbines (about 1.2 GW) in Southaven; earlier operation of unpermitted turbines is the subject of an NAACP/SELC action, and the temporary turbine permit expires in 2027. · source ◐ secondary, confidence medium

Recorded readiness — 2 of 6 applicable milestones have a dated public record

● Land 2025-02● Permits 2026-03○ Grid supply◐ Generation○ Water· Financing○ Construction

Gate to first power — target 2025-10-19 (estimate) · path: Hybrid: on-site bridge, then grid · each step must finish its lead time before the target

2 of 2 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2024-07-19 (15 mo before)13 mo before (n=26)2025-02-28contextLand clearing begins · ◐
Permits in hand2025-10-19 (0 mo before)4 mo after (n=8)2026-03-10on record in timeMDEQ air permit for 41 permanent turbines · ◐
New generation online2025-09-19 (1 mo before)12 mo after (n=1)2027-06-30 planplan 21 mo past the deadlineTurbine programme reaches 1.1 GW+ (Solaris, planned) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-02-28 Site securedLand clearing begins · ◐
2025-10-19 First powerFirst power (Epoch) · ◐
2026-03-10 Permits in handMDEQ air permit for 41 permanent turbines · ◐
2026-04-14 Permits in handNAACP and SELC file a Clean Air Act suit over 27 unpermitted turbines; MDEQ counted 46 turbines in May, 60 in June and 69 in July 2026 · ◐
2027-06-30 plan New generation onlineTurbine programme reaches 1.1 GW+ (Solaris, planned) · ◐
2027-12-31 plan Permits in handTemporary turbine permit expires · ◐

Power equipment (from permits, filings and reporting; blank cells were not disclosed)

CategoryMake / modelUnitsMWStatusDateNote
gas turbine—69495 MWoperating (temporary)2026-07-15Southaven plant: MDEQ counted 46 temporary turbines in May, 60 in June and 69 in July 2026 (xAI had acknowledged 27); NAACP/SELC Clean Air Act suit filed 2026-04-14; 495 MW reported earlier · ◐
gas turbine—411.2 GWpermitted2026-03-10Permanent fleet approved by MDEQ (appealed by SELC/NAACP); Solaris JV targets 1.1 GW+ by Q2 2027 · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-02-28—Land clearing begins next to the existing building.
2025-09-08—Battery facility connected to the building. 121 air-cooled chillers installed, which could support 200 MW. In the Duke faciltiy in nearby Mississippi, several natural gas turbines are in place but not fully connected up.
2025-10-19239 MWBattery facility looks complete (though more might be added). Turbines look connected up, minimal construction around them. We believe this state corresponds to the first compute cluster brought online at this site of "a
2026-01-13239 MWSince October, an array of dry cooling air-cooled condensers has been added (the array of large fans to the left of the building), and appears almost complete. Two more similar arrays appear to be under construction. Mor
2026-04-06490 MWThe first array of dry cooling air-cooled condensers for Building 1 has been completed and is operational. A second array, with larger fans, is about halfway complete (located to the south of the first array). More chill
2026-06-15946 MWThe site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of exp
2027-02-25 est.1.5 GWBuilding 3 is estimated to be completed. The site is predicted to have enough power infrastructure installed for a total of 1.5 GW of IT Power. Based on building plans we predict the addition of three more cooling arrays

Recorded fact new generation online has a recorded date later than the rule-based deadline for a 2025-10-19 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): WSJ profile of the Colossus data centers · Final GPU count reported by Elon Musk · MLGW update mentioning power requests for Colossus 2 · SpaceX-Cursor partnership to use Colossus · Anthropic to use Colossus 2 from June 2026 · SpaceX S-1 filing, mentioning exact compute and power for Colossus 2

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id colossus-2; include the row and a source link).