Google Red Oak · Red Oak, TX

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerGoogle
Users—
IT power, end of 2026154 MW (est.)
Planned end state154 MW
First power2025-08-25
Build-out complete2026-12-01 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersOncor (ERCOT) (verify)

Latest: Build-out complete (Epoch estimate) · Full build-out complete · 2026-12-01 (plan) · recorded 2026-10-04

Google's Red Oak (Ellis County) campus: $600m announced, the first $400m phase about 285,000 sq ft taking two years; first building confirmed operational in November 2025 as part of Google's $40bn Texas plan through 2027. · source ◐ secondary, confidence medium

Recorded readiness — 1 of 5 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water· Financing● Construction 2025-11

Gate to first power — target 2025-08-25 (estimate) · path: Grid supply · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Building ready for IT2025-08-25 (0 mo before)2 mo after (n=7)2025-11-14on record in timeFirst building confirmed operational · ◐
Full build-out complete (context)2026-08-25 (-12 mo before)—2026-12-01 plancontextBuild-out complete (Epoch estimate) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-08-25 First powerFirst power (Epoch) · ◐
2025-11-14 Building ready for ITFirst building confirmed operational · ◐
2026-12-01 plan Full build-out completeBuild-out complete (Epoch estimate) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2023-04-30—First signs of development/land clearing
2025-08-2577 MWBuilding 1 is operational, based on a Google Earth [image](https://earth.google.com/web/@32.53855187,-96.7936939,182.71625265a,4648.56607908d,30.00094375y,3.66969189h,0t,0r/) showing a completed building shell and equipm
2026-02-0677 MWBuilding 1 appears active - the surrounding land is finished including the site entrance and the parking lot. The dry coolers for Building 2 are nearly complete although the building is still clearly a construction zone.
2026-12-01 est.154 MWBuilding 2 is estimated to be operational.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Media coverage confirming location, project name, investment size, and some timing · Google PUE data listing the Red Oak site from Q1 2026

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id google-red-oak; include the row and a source link).