OpenAI Stargate UAE · Abu Dhabi, United Arab Emirates

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerG42
UsersOpenAI
IT power, end of 2026200 MW (est.)
Planned end state1.0 GW
First power2026-12-01 (est.)
Build-out complete2028-01-01 (est.)
Power pathGrid supply
Binding step 2 required steps without a date
First power vs announced+2 months (announced 2026-09-30)
Full build-out vs announcedNo announced date on record
Utility / power partnersEWEC / Khazna (G42) (verify)

Latest: 1 GW operational (Epoch estimate) · Full build-out complete · 2028-01-01 (plan) · recorded 2026-10-04

Khazna (G42) builds the 1 GW Stargate UAE cluster inside the 5 GW UAE-US AI campus in Abu Dhabi; operated by OpenAI and Oracle. First 200 MW phase announced for Q3 2026 (The National, December 2025): civil and structural work well advanced, mechanical and electrical being finalised, first critical mechanical deliveries on site. Full 1 GW targeted in about three years from October 2025. Supply described as Barakah nuclear, utility solar and gas backup. · source ◐ secondary, confidence medium

Recorded readiness — 2 of 6 applicable milestones have a dated public record

● Land 2025-05○ Permits○ Grid supply· Generation○ Water○ Financing● Construction 2025-10

Gate to first power — target 2026-09-30 (announced) · path: Grid supply · each step must finish its lead time before the target

1 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-06-28 (15 mo before)13 mo before (n=26)2025-05-22contextStargate UAE announced · ◐
Grid supply agreed2025-12-28 (9 mo before)7 mo before (n=11)no public dateno public date · would need to be done by 2025-12-28No date on record
Substation and lines energized2026-07-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2026-07-28No date on record
Major equipment on site (context)2026-03-28 (6 mo before)9 mo after (n=1)2025-12-05contextFirst deliveries of critical mechanical systems on site · ◐
Construction started (context)2024-09-28 (24 mo before)29 mo before (n=15)2025-10-16contextFirst phase under construction, 5,000 workers on site · ◐
Building ready for IT2026-09-28 (0 mo before)2 mo after (n=7)2026-09-30 planplan inside the deadlineFirst 200 MW phase complete (Q3 2026, Khazna) · ◐
Full build-out complete (context)2027-09-28 (-12 mo before)—2028-01-01 plancontext1 GW operational (Epoch estimate) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-05-22 Site securedStargate UAE announced · ◐
2025-10-16 Construction startedFirst phase under construction, 5,000 workers on site · ◐
2025-12-05 Major equipment on siteFirst deliveries of critical mechanical systems on site · ◐
2026-09-30 Building ready for ITFirst 200 MW phase complete (Q3 2026, Khazna) · ◐
2026-12-31 plan First powerFirst 200 MW (announced) · ◐
2028-01-01 plan Full build-out complete1 GW operational (Epoch estimate) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-06-09—Land clearing begins for Building 1 and 2
2025-11-16—Building 1 and 2 are partly constructed. No clear evidence of more buildings starting construction.
2026-12-01 est.200 MWBuilding 1 and 2 are operational. The similar data center in Ajman, UAE was delayed by over a year, now due in December 2026 (compare [1](https://khaznadatacenters.com/press-release/khazna-expands-infrastructure-to-accel
2028-01-01 est.1.0 GW1 GW of IT power is operational. We haven’t seen expansion beyond 200 MW as of November 2025. Optimistically, 8 more 100 MW buildings start construction in December 2025, in parallel, and take 1.5 years like the first tw

Recorded fact No public date for grid supply agreed, substation and lines energized.

Calculated requirement Grid supply agreed must finish by 2025-12-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2026-09-30 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): News update with timelapse of construction · Announcement of the (separate) 100 MW Khazna Ajman data center · News about the US approval of NVIDIA chips in the UAE

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id openai-stargate-uae; include the row and a source link).