AILoadmapAI gigawatts, campus by campus
← Map · All projects

Meta Jeffersonville · Jeffersonville, IN

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 2026178 MW
Planned end state178 MW
First power2026-06-04
Build-out completeno further build-out tracked
Power pathGrid supply
Binding stepNo data yet
First power vs announcedon time (announced 2026-12-31)
Full build-out vs announcedNo announced date on record
Utility / power partnersDuke Energy Indiana (verify)

Latest: First power (Epoch) · First power · 2026-06-04 · recorded 2026-10-04

Announced 2024-01-25 at River Ridge Commerce Center ($800m, 700,000 sq ft) with construction starting that month and operation in 2026. · source ● primary, confidence high

Recorded readiness — 1 of 5 applicable milestones have a dated public record

● Land 2024-01○ Permits○ Grid supply· Generation○ Water· Financing○ Construction

Gate to first power — target 2026-12-31 (announced) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-09-28 (15 mo before)13 mo before (n=26)2024-01-25contextData center announced; construction starts · ●

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-01-25 Site securedData center announced; construction starts · ●
2026-06-04 First powerFirst power (Epoch) · ●

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-02-01—Land clearing begins.
2026-03-06—Building 1 and 2 shell and cooling look complete, but there's still construction activity. We give it another 3 months to operational.
2026-06-04178 MWBuilding 1 and 2 are operational.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Official Meta Fact Sheet · Turner Construction contractor presenting their involvement in the project. · Air Quality Permit for initial buildout

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-jeffersonville; include the row and a source link).