Microsoft Narvik Norway · Narvik, Norway

Last change recorded 2026-10-05 · Last checked 2026-10-04

OwnerNscale
UsersMicrosoft
IT power, end of 202692 MW (est.)
Planned end state92 MW
First power2026-12-31 (est.)
Build-out complete2026-12-31 (est.)
Power pathGrid supply
Binding step 2 required steps without a date
First power vs announcedannounced 2027-06-30; current estimate not confirmed
Full build-out vs announcedNo announced date on record
Utility / power partnersStatnett; Vattenfall (PPA)

Latest: $790m project financing from ABN AMRO, DNB, Eksfin, Nordea and SEB, with an uncommitted accordion for a 115 MW expansion · Financing closed · 2026-05-11 · recorded 2026-10-05

Nscale/Aker campus at Kvandal outside Narvik (230 MW first phase, 115 MW expansion option): announced as Stargate Norway with OpenAI in July 2025; in April 2026 OpenAI dropped out and Microsoft took the capacity (30,000 Rubin GPUs). $790m project financing May 2026; Vattenfall PPA for 2027-2031; about 350 workers on site in June 2026 rising toward 1,500; operations from 2027. · source ◐ secondary, confidence medium

Recorded readiness — 4 of 6 applicable milestones have a dated public record

● Land 2025-09○ Permits● Grid supply 2026-05· Generation○ Water● Financing 2026-05● Construction 2026-06

Gate to first power — target 2027-06-30 (announced) · path: Grid supply · each step must finish its lead time before the target

1 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2026-03-28 (15 mo before)13 mo before (n=26)2025-09-17contextMicrosoft $6.2bn capacity agreement · ◐
Grid supply agreed2026-09-28 (9 mo before)7 mo before (n=11)2026-05-26on record in timeVattenfall renewable PPA signed for phase 1 (2027-2031) · ●
Substation and lines energized2027-04-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2027-04-28No date on record
New generation online (context)2027-05-28 (1 mo before)12 mo after (n=1)2027-01-01 plancontextVattenfall renewable PPA covers 2027-2031 for phase 1 · ●
Construction started (context)2025-06-28 (24 mo before)29 mo before (n=15)2026-06-01contextAbout 350 workers on site (TIME) · ◐
Building ready for IT2027-06-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2027-06-28No date on record
Full build-out complete (context)2028-06-28 (-12 mo before)—2027-12-31 plancontextRubin GPU capacity delivered (planned 2027) · ◐
Financing closed (context)2026-06-28 (12 mo before)12 mo before (n=2)2026-05-11context$790m project financing from ABN AMRO, DNB, Eksfin, Nordea and SEB, with an uncommitted accordion for a 115 MW expansion · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-09-17 Site securedMicrosoft $6.2bn capacity agreement · ◐
2026-05-11 Site secured$790m project financing · ◐
2026-05-11 Financing closed$790m project financing from ABN AMRO, DNB, Eksfin, Nordea and SEB, with an uncommitted accordion for a 115 MW expansion · ◐
2026-05-26 Grid supply agreedVattenfall renewable PPA signed for phase 1 (2027-2031) · ●
2026-06-01 Construction startedAbout 350 workers on site (TIME) · ◐
2026-12-31 plan First powerFirst staged deliveries (planned 2026) · ◐
2027-01-01 plan New generation onlineVattenfall renewable PPA covers 2027-2031 for phase 1 · ●
2027-06-30 plan First powerOperations set to commence in 2027 · ○
2027-12-31 plan Full build-out completeRubin GPU capacity delivered (planned 2027) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2023-07-01—Land clearing and site prep begins at least as early as July 2023.
2025-06-27—Site prep continues for Buildings 1, 2, and 3.
2025-08-01—Building 1 starts to go up.
2026-05-31—Building 1 cooling looks complete. Backup generator install continues adjacent to B1. Building 2 cooling install continues. Ground prep for generators next to B2. Cooling install appears to continue on Building 3. Constr
2026-07-05—Building 1 cooling looks complete. Backup generator install continues adjacent to B1. Building 2 cooling install continues. Backup generator concrete pads are there, but no equipment install visible. Cooling install appe
2026-12-31 est.92 MWWe believe Buildings 1 and 2 will be fully operational by the end of H2 2026

Recorded fact No public date for substation and lines energized, building ready for it.

Calculated requirement Substation and lines energized must finish by 2027-04-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2027-06-30 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Nscale announcing more than 30.000 Rubin GPUs · NScale announcing 230 initial MW and possibly an additional 290MW, mentioning 100.000 Nvidia GPUs · Local hydropower facilities will fulfill new demand at 4 to 5 cents per unit for electricity

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id microsoft-narvik-norway; include the row and a source link).