AILoadmapAI gigawatts, campus by campus
← Map · All projects

EcoDataCenter 2 · Borlänge, Sweden

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMistral AI
UsersMistral AI
IT power, end of 20260 MW
Planned end state48 MW
First power2027-06-30 (est.)
Build-out complete2028-06-30 (est.)
Power pathGrid supply
Binding step 1 required step without a date
First power vs announced+3 months (announced 2027-03-31)
Full build-out vs announcedNo announced date on record

Latest: Phase complete (Epoch estimate) · Full build-out complete · 2028-06-30 (plan) · recorded 2026-10-04

Kvarnsveden mega campus in Borlänge on the former paper mill bought in 2024: 250 MW at launch, up to 600 MW, up to nine buildings. Construction from September 2025; first phase by mid-2027. · source ● primary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2026-02○ Permits● Grid supply 2025-09· Generation○ Water○ Financing● Construction 2025-09

Gate to first power — target 2027-03-31 (announced) · path: Grid supply · each step must finish its lead time before the target

2 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-12-28 (15 mo before)13 mo before (n=26)2026-02-15contextMistral AI €1.2bn long-term commitment for an AI data center at Borlänge; first facilities 2027, 250 MW first phase · ◐
Grid supply agreed2026-06-28 (9 mo before)7 mo before (n=11)2025-09-15on record in time250 MW available at launch (up to 600 MW), per EcoDataCenter · ●
Substation and lines energized2027-01-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2027-01-28No date on record
Construction started (context)2025-03-28 (24 mo before)29 mo before (n=15)2025-09-15contextGround broken · ●
Building ready for IT2027-03-28 (0 mo before)2 mo after (n=7)2027-06-30 planplan inside the deadlineFirst phase complete (mid-2027) · ◐
Full build-out complete (context)2028-03-28 (-12 mo before)—2028-06-30 plancontextPhase complete (Epoch estimate) · ●
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-09-15 Construction startedGround broken · ●
2025-09-15 Grid supply agreed250 MW available at launch (up to 600 MW), per EcoDataCenter · ●
2026-02-15 Site securedMistral AI €1.2bn long-term commitment for an AI data center at Borlänge; first facilities 2027, 250 MW first phase · ◐
2027-06-30 plan First powerFirst power (Epoch estimate; announced early 2027) · ●
2027-06-30 plan Building ready for ITFirst phase complete (mid-2027) · ◐
2028-06-30 plan Full build-out completePhase complete (Epoch estimate) · ●

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-09-01—Land clearing begins. [EcoDataCenter](https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556) announces on September 24th that construction has started on EcoDataCenter 2, so we mo
2026-05-09—Buildings 1 and 2 still under construction. The first two building shells are visibly well into construction, with lots of additional ground work visible all across the campus. Based on high-resolution satellite imagery
2026-08-17—Buildings 1 and 2 look fully roofed, with active construction showing cooling and power equipment still being installed. Buildings 3-4 look like their foundations have been laid out and are early in construction.
2027-06-30 est.24 MWBuildings 1-2 operational. Based on [Bravida](https://www.bravida.se/en/press/press-releases/2026/bravida-carries-out-installations-in-two-data-centres-for-around-sek-200-million/) stating that installation work in two E
2028-06-30 est.48 MWBuildings 3-4 operational. Based on [Bravida](https://www.bravida.se/en/press/press-releases/2026/bravida-awarded-sek-650-million-installation-contract-in-borlange-by-ecodatacenter/) stating that installation work in ano

Recorded fact No public date for substation and lines energized.

Calculated requirement Substation and lines energized must finish by 2027-01-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2027-06-28 (3 mo after the announced target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): EcoDataCenter 2 campus overview · EcoDataCenter 2025 Annual Report · EcoDataCenter groundbreaking announcement · Mistral AI partnership announcement

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id ecodatacenter-2; include the row and a source link).