Campus AI Paris (Fouju) · Fouju, Seine-et-Marne, France
Last change recorded 2026-11-08 · Last checked 2026-11-08
Latest: Phase 1 delivery estimated early 2028: first three data centers · First power · 2028-03-31 (plan) · recorded 2026-11-08
Europe's largest planned AI campus, 1.4 GW at Fouju south-east of Paris; the local authority calendar (September 2026) puts phase 1 works from September 2026 and delivery of the first three data centers in early 2028. RTE Fast Track connection contract signed 2026-01-26, with 700 MW contracted as of July 2026 and talks to raise it; environmental authorizations 2026-07-29 and phase 1 building permit 2026-08-28. Eiffage selected for the high-voltage substation and common infrastructure (over €120m, June 2026); the partners now target up to 3 GW across France. The opposition collective Stop IA à Fouju said in August 2026 it would file an appeal (Next); no filing confirmed. · source ◐ secondary, confidence high
Recorded readiness — 3 of 6 applicable milestones have a dated public record
Gate to first power — target 2028-03-31 (announced) · path: Grid supply · each step must finish its lead time before the target
1 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.
| Step | Must finish by | Others did it | Known date | Status | Basis | |
|---|---|---|---|---|---|---|
| Site secured (context) | 2026-12-28 (15 mo before) | 13 mo before (n=26) | 2025-02-06 | context | France-UAE AI partnership announced, the origin of the campus · ● | |
| Permits in hand (context) | 2028-03-28 (0 mo before) | 5 mo after (n=9) | 2026-07-29 | context | Prefectoral orders grant the environmental authorizations for Campus AI and RTE and let operators run DC1, DC2 and DC4 · ● | |
| Grid supply agreed | 2027-06-28 (9 mo before) | 7 mo before (n=11) | 2026-01-26 | on record in time | RTE and Campus IA sign the accelerated "Fast Track" grid connection contract · ● | |
| Substation and lines energized | 2028-01-28 (2 mo before) | 15 mo after (n=1) | no public date | no public date · would need to be done by 2028-01-28 | No date on record | |
| Construction started (context) | 2026-03-28 (24 mo before) | 29 mo before (n=15) | 2026-09-15 plan | context | Phase 1 works scheduled to start in September 2026 (start not independently confirmed) · ● | |
| Building ready for IT | 2028-03-28 (0 mo before) | 2 mo after (n=7) | no public date | no public date · would need to be done by 2028-03-28 | No date on record |
Lead-time assumptions
- Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
- Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
- Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
- Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
- New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
- Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
- Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
- Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
- Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
- Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
- Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.
Dated steps (from the sources; later dates are plans)
Build-out timeline (announced phases from public reporting; rows after today are plans)
Recorded fact No public date for substation and lines energized, building ready for it.
Calculated requirement Substation and lines energized must finish by 2028-01-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2028-03-31 (on the target). This is a floor set by the record, not a forecast.
Sources: MGX Bpifrance Nvidia and Mistral AI plan 1.4GW Paris campus (DCD)
Campus outside the Epoch AI dataset: facts from the public reporting linked above (tools/campuses.csv), coordinates hand-entered. Data retrieved 2026-11-09. Report a correction to contact@ailoadmap.com (campus id campus-ai-paris-fouju; include the row and a source link).