AILoadmapAI gigawatts, campus by campus
← Map · All projects

Campus AI Paris (Fouju) · Fouju, Seine-et-Marne, France

Last change recorded 2026-11-08 · Last checked 2026-11-08

OwnerMGX / Bpifrance / Mistral AI / Nvidia
UsersMistral AI
IT power, end of 20260 MW
Planned end state1.4 GW
First power2028-03-31 (est.)
Build-out complete2028-03-31 (est.)
Power pathGrid supply
Binding step 2 required steps without a date
First power vs announcedon time (announced 2028-03-31)
Full build-out vs announcedNo announced date on record
Utility / power partnersRTE / EDF

Latest: Phase 1 delivery estimated early 2028: first three data centers · First power · 2028-03-31 (plan) · recorded 2026-11-08

Europe's largest planned AI campus, 1.4 GW at Fouju south-east of Paris; the local authority calendar (September 2026) puts phase 1 works from September 2026 and delivery of the first three data centers in early 2028. RTE Fast Track connection contract signed 2026-01-26, with 700 MW contracted as of July 2026 and talks to raise it; environmental authorizations 2026-07-29 and phase 1 building permit 2026-08-28. Eiffage selected for the high-voltage substation and common infrastructure (over €120m, June 2026); the partners now target up to 3 GW across France. The opposition collective Stop IA à Fouju said in August 2026 it would file an appeal (Next); no filing confirmed. · source ◐ secondary, confidence high

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2025-02● Permits 2026-07● Grid supply 2026-01· Generation○ Water○ Financing◐ Construction

Gate to first power — target 2028-03-31 (announced) · path: Grid supply · each step must finish its lead time before the target

1 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2026-12-28 (15 mo before)13 mo before (n=26)2025-02-06contextFrance-UAE AI partnership announced, the origin of the campus · ●
Permits in hand (context)2028-03-28 (0 mo before)5 mo after (n=9)2026-07-29contextPrefectoral orders grant the environmental authorizations for Campus AI and RTE and let operators run DC1, DC2 and DC4 · ●
Grid supply agreed2027-06-28 (9 mo before)7 mo before (n=11)2026-01-26on record in timeRTE and Campus IA sign the accelerated "Fast Track" grid connection contract · ●
Substation and lines energized2028-01-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2028-01-28No date on record
Construction started (context)2026-03-28 (24 mo before)29 mo before (n=15)2026-09-15 plancontextPhase 1 works scheduled to start in September 2026 (start not independently confirmed) · ●
Building ready for IT2028-03-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2028-03-28No date on record
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-02-06 Site securedFrance-UAE AI partnership announced, the origin of the campus · ●
2026-01-26 Grid supply agreedRTE and Campus IA sign the accelerated "Fast Track" grid connection contract · ●
2026-07-29 Permits in handPrefectoral orders grant the environmental authorizations for Campus AI and RTE and let operators run DC1, DC2 and DC4 · ●
2026-08-28 Permits in handPhase 1 building permit obtained · ●
2026-09-15 Construction startedPhase 1 works scheduled to start in September 2026 (start not independently confirmed) · ●
2028-03-31 plan First powerPhase 1 delivery estimated early 2028: first three data centers · ●

Build-out timeline (announced phases from public reporting; rows after today are plans)

2028-03-31 est.1.4 GWFirst phase online (announced plan)

Recorded fact No public date for substation and lines energized, building ready for it.

Calculated requirement Substation and lines energized must finish by 2028-01-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2028-03-31 (on the target). This is a floor set by the record, not a forecast.

Sources: MGX Bpifrance Nvidia and Mistral AI plan 1.4GW Paris campus (DCD)

Campus outside the Epoch AI dataset: facts from the public reporting linked above (tools/campuses.csv), coordinates hand-entered. Data retrieved 2026-11-09. Report a correction to contact@ailoadmap.com (campus id campus-ai-paris-fouju; include the row and a source link).