Anthropic Lake Mariner · Barker, NY

Last change recorded 2026-10-05 · Last checked 2026-10-04

OwnerAI XPV Platform
UsersAnthropic
IT power, end of 2026210 MW (est.)
Planned end state378 MW
First power2026-05-31
Build-out complete2027-03-31 (est.)
Power pathGrid supply
Binding step Construction (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announced+3 months (announced 2026-12-31)
Utility / power partnersNew York Power Authority; National Grid (verify)

Latest: Fluidstack leases totalling 360 MW ($6.7bn contracted) with Google backstop; CB-5 expansion lease · Financing closed · 2026-06-30 · recorded 2026-10-05

TeraWulf's Lake Mariner campus at a former 700 MW coal-plant site in Barker, NY. Fluidstack leases 378 MW of critical IT (August 2025), with Google credit support. CB-3 delivered by mid-2026 (102 MW revenue-generating). CB-4 in commissioning with phased delivery in H2 2026; CB-5 (160 MW) was announced for operations in H2 2026 and is now targeted for phased delivery from early 2027. · source ● primary, confidence high

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2025-08○ Permits○ Grid supply· Generation○ Water● Financing 2026-06● Construction 2026-07

Gate to first power — target 2026-05-31 (estimate) · path: Grid supply · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-02-28 (15 mo before)13 mo before (n=26)2025-08-14contextFluidstack leases 378 MW critical IT · ●
Building ready for IT2026-05-28 (0 mo before)2 mo after (n=7)2026-07-05on record in timeCB-3 delivered; 102 MW of revenue-generating IT capacity at Lake Mariner · ●
Full build-out complete (context)2027-05-28 (-12 mo before)—2026-12-31 plancontextCB-5 (160 MW, Fluidstack) due online H2 2026; contracted IT load 360 MW · ◐
Financing closed (context)2025-05-28 (12 mo before)12 mo before (n=2)2026-06-30contextFluidstack leases totalling 360 MW ($6.7bn contracted) with Google backstop; CB-5 expansion lease · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-08-14 Site securedFluidstack leases 378 MW critical IT · ●
2026-05-31 First powerFirst power (Epoch) · ●
2026-06-30 First powerCB-3 delivered (102 MW revenue-generating) · ●
2026-06-30 Financing closedFluidstack leases totalling 360 MW ($6.7bn contracted) with Google backstop; CB-5 expansion lease · ◐
2026-07-05 Building ready for ITCB-3 delivered; 102 MW of revenue-generating IT capacity at Lake Mariner · ●
2026-12-31 plan Building ready for ITCB-4 phased delivery (H2 2026) · ●
2026-12-31 plan Full build-out completeCB-5 (160 MW, Fluidstack) due online H2 2026; contracted IT load 360 MW · ◐
2027-03-31 plan Building ready for ITCB-5 phased delivery (now early 2027; announced H2 2026) · ●

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-06-11—Land clearing begins for Building 1 (AKA CB3).
2026-03-02—Building 1 appears to have a complete shell and cooling equipment. Building 2 shell is still under construction, but 17 cooling units are already loaded on the roof. The outline of Building 3 is visible at the foundation
2026-05-3142 MWBuilding 1 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB3 was expected to be en
2026-07-2342 MWBuilding 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is co
2026-10-31 est.210 MWBuilding 2 (AKA CB4) is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB4 was expecte
2027-03-31 est.378 MWBuilding 3 (AKA CB5) is operational. On February 26, 2026, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB5 was e

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Terawulf press release with details and timeline for Buildings 1-5 · DCD article suggesting that Fluidstack will deploy Google TPUs at Lake Mariner · Announcement of Anthropic-Fluidstack partnership, including data center(s) in New York

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id anthropic-lake-mariner; include the row and a source link).