Google Kansas City East · Kansas City, MO

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerGoogle
Users—
IT power, end of 2026105 MW
Planned end state105 MW
First power2026-08-01
Build-out completeno further build-out tracked
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersEvergy

Latest: First power (Epoch) · First power · 2026-08-01 · recorded 2026-10-04

Google's Kansas City campuses are served by Evergy, with Google covering the full energy cost. A second campus (Project Mica, about $10bn, five buildings on 500 acres) was confirmed on 2026-02-12 with an 18-month first phase. · source ◐ secondary, confidence low

Recorded readiness — 1 of 5 applicable milestones have a dated public record

● Land 2026-02○ Permits○ Grid supply· Generation○ Water· Financing○ Construction

Gate to first power — target 2026-08-01 (estimate) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-05-01 (15 mo before)13 mo before (n=26)2026-02-12contextSecond Kansas City campus (Project Mica) confirmed · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2026-02-12 Site securedSecond Kansas City campus (Project Mica) confirmed · ◐
2026-08-01 First powerFirst power (Epoch) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-01-01—Land clearing has begun for the site
2024-03-01—Foundation work begins on Building 1
2024-10-01—Foundation work begins on Building 2. Building 1 roof is fully black.
2025-07-01—Foundation work begins for Building 3. Building 1 generators seem complete.
2025-11-01—Foundation work begins for Building 4. Building 2 roof is almost complete, and construction appears to have started on cooling. Building 1 cooling construction continues, and the substation right next to it seems finishe
2026-04-16—Building 1 is almost complete, with only cooling needing 4 more fans. Building 2 backup generator construction has begun, and cooling tower installation is about halfway complete. Building 3's roof is almost complete, an
2026-08-01105 MWBuilding 1 operational. Estimated based on present construction progress and typical timelines.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Hunt Midwest Business Center press release linking data center with Google · DCD article on the site

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id google-kansas-city-east; include the row and a source link).