Meta Sarpy · Springfield, NE

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 202680 MW
Planned end state80 MW
First power2026-08-02
Build-out completeno further build-out tracked
Power pathGrid supply
Binding step Construction (from reporting)
First power vs announced+19 months (announced 2024-12-31)
Full build-out vs announcedNo announced date on record
Utility / power partnersOmaha Public Power District

Latest: First power (Epoch) · First power · 2026-08-02 · recorded 2026-10-04

Springfield expansion of the Sarpy campus announced in July 2022 (to nine buildings, 4 million sq ft), with completion reported for the end of 2024; Epoch records first power for the tracked building in August 2026. The announced date comes from secondary reporting. · source ◐ secondary, confidence low

Recorded readiness — 1 of 5 applicable milestones have a dated public record

● Land 2022-07○ Permits○ Grid supply· Generation○ Water· Financing○ Construction

Gate to first power — target 2024-12-31 (announced) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2023-09-28 (15 mo before)13 mo before (n=26)2022-07-28contextSpringfield expansion announced · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2022-07-28 Site securedSpringfield expansion announced · ◐
2026-08-02 First powerFirst power (Epoch) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-08-01—Building 1 grading underway.
2026-05-04—Building 1 shell, electrical and cooling equipment looks complete, with minimal construction work, so we expect it to be operational within 3 months.
2026-08-0280 MWBuilding 1 is operational (estimate).

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Meta Sarpy info sheet (PDF)

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-sarpy; include the row and a source link).