Nscale Loughton AI Campus · Loughton, Essex, United Kingdom
Last change recorded 2026-11-08 · Last checked 2026-11-08
Latest: Placeholder: grid power reported as not sufficient until the early to mid-2030s; Nscale is exploring alternative power · Substation and lines energized · 2032-12-31 (plan) · recorded 2026-11-08
Announced September 2025 as the UK's largest AI supercomputer (50 MW scalable to 90 MW, about 23,000 GB300 GPUs). The Telegraph reported on 2026-10-18 that Microsoft ended its anchor agreement (Microsoft did not comment; Nscale says the relationship remains strong). Reports say the site may not get enough grid power until the early to mid-2030s; Nscale says it is exploring alternative power and has cleared the land. The original plan had construction complete by end-2026 and GPUs from early 2027; no new date has been announced, and 2032-12-31 is a placeholder inside the reported window. · source ◐ secondary, confidence low
Recorded readiness — 1 of 6 applicable milestones have a dated public record
Gate to first power — target 2032-12-31 (estimate) · path: Grid supply · each step must finish its lead time before the target
1 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.
| Step | Must finish by | Others did it | Known date | Status | Basis | |
|---|---|---|---|---|---|---|
| Site secured (context) | 2031-09-28 (15 mo before) | 13 mo before (n=26) | 2025-09-16 | context | Campus announced with Microsoft as anchor · ◐ | |
| Grid supply agreed | 2032-03-28 (9 mo before) | 7 mo before (n=11) | no public date | no public date · would need to be done by 2032-03-28 | No date on record | |
| Substation and lines energized | 2032-10-28 (2 mo before) | 15 mo after (n=1) | 2032-12-31 plan | plan 2 mo past the deadline | Placeholder: grid power reported as not sufficient until the early to mid-2030s; Nscale is exploring alternative power · ◐ | |
| Building ready for IT | 2032-12-28 (0 mo before) | 2 mo after (n=7) | no public date | no public date · would need to be done by 2032-12-28 | No date on record |
Lead-time assumptions
- Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
- Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
- Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
- Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
- New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
- Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
- Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
- Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
- Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
- Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
- Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.
Dated steps (from the sources; later dates are plans)
Build-out timeline (announced phases from public reporting; rows after today are plans)
Recorded fact substation and lines energized has a recorded date later than the rule-based deadline for a 2032-12-31 first power.
Calculated requirement Grid supply agreed must finish by 2032-03-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2033-02-28 (2 mo after the estimated target). This is a floor set by the record, not a forecast.
Sources: Microsoft abandons UK AI supercomputer as grid struggles to keep up (The Register)
Campus outside the Epoch AI dataset: facts from the public reporting linked above (tools/campuses.csv), coordinates hand-entered. Data retrieved 2026-11-09. Report a correction to contact@ailoadmap.com (campus id nscale-loughton-ai-campus; include the row and a source link).