AILoadmapAI gigawatts, campus by campus
← Map · All projects

CoreWeave Denton TX · Denton, TX

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerCoreWeave
UsersOpenAI
IT power, end of 2026262 MW
Planned end state282 MW
First power2025-05-31
Build-out complete2027-05-31 (est.)
Power pathGrid supply
Binding step Construction (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersDenton Municipal Electric

Latest: Full conversion (Epoch estimate; planned 2027) · Full build-out complete · 2027-05-31 (plan) · recorded 2026-10-04

Core Scientific's Denton crypto site being converted to AI for CoreWeave (up to $6.1bn), with access to 394 MW from the city utility and about 260 MW critical IT after the February 2025 expansion. Reported as delayed; CoreWeave had more than 16,000 GPUs deployed by January 2026, with full launch planned for 2027. CoreWeave's acquisition of Core Scientific was voted down on 2025-10-30. · source ◐ secondary, confidence medium

Recorded readiness — 1 of 6 applicable milestones have a dated public record

● Land 2025-10○ Permits○ Grid supply· Generation○ Water○ Financing○ Construction

Gate to first power — target 2025-05-31 (estimate) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2024-02-28 (15 mo before)13 mo before (n=26)2025-10-30contextCoreWeave-Core Scientific merger rejected by shareholders · ◐
Full build-out complete (context)2026-05-28 (-12 mo before)—2027-05-31 plancontextFull conversion (Epoch estimate; planned 2027) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-05-31 First powerFirst power (Epoch) · ◐
2025-10-30 Site securedCoreWeave-Core Scientific merger rejected by shareholders · ◐
2027-05-31 plan Full build-out completeFull conversion (Epoch estimate; planned 2027) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-11-01—Construction start - The [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/TABS/Search/Print/TABS2025005706) reports Core Scientific is converting existing Bitcoin mining buildings into AI data ce
2025-05-318 MWFirst 8 MW billable tranche dedicated to AI [starts running at the site](https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001628280-25-023161/q12025corescientificinc-ea.htm), with another 40 sche
2025-12-3167 MWHalf the campus energized. 67 billable MW [are now dedicated](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1085/11265/presentation/Q4+FY25+earnings+deck+vfinal.2+PDF.pdf) to Co
2026-02-23131 MWBuildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. Th
2026-03-02131 MWBuildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an [earnings call](https://www.fool.com/earnings/call-transcripts/2026/03/
2026-07-03262 MWBuildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the [Q2 2026 Earnings call](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea4
2026-09-01262 MWBuilding 8 interior fit-out scheduled to begin. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a da
2027-05-31 est.282 MWBuilding 8 projected operational. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules Building A's data-hall fit-out for completion by this date.

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Core Scientific - CoreWeave Announce 1.2B expansion in Denton, TX · Core Scientific - Denton Datacenter Official Site · TMF - Core Scientific Q4 2025 Earnings Transcript · WSJ - plans to rent to OpenAI

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id coreweave-denton-tx; include the row and a source link).