Meta Kuna · Kuna, ID

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerMeta
UsersMeta
IT power, end of 2026152 MW
Planned end state152 MW
First power2026-06-01
Build-out completeno further build-out tracked
Power pathGrid supply
Binding step Construction (from reporting)
First power vs announced+8 months (announced 2025-12-31)
Full build-out vs announcedNo announced date on record
Utility / power partnersIdaho Power

Latest: Serving traffic (Meta) · First power · 2026-09-03 · recorded 2026-10-04

Announced February 2022 ($800m, 960,000 sq ft) with construction from September 2022 through 2025; caught in the late-2022 redesign pause and resumed with the AI design. Meta announced it was serving traffic on 2026-09-03 at a final $1.2bn. Supplied through Idaho Power's Clean Energy Your Way programme. · source ● primary, confidence high

Recorded readiness — 2 of 5 applicable milestones have a dated public record

● Land 2022-02○ Permits○ Grid supply· Generation○ Water· Financing● Construction 2022-12

Gate to first power — target 2025-12-31 (announced) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2024-09-28 (15 mo before)13 mo before (n=26)2022-02-15contextKuna data center announced · ●
Construction started (context)2023-12-28 (24 mo before)29 mo before (n=15)2022-12-15contextConstruction paused for AI redesign · ●

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2022-02-15 Site securedKuna data center announced · ●
2022-12-15 Construction startedConstruction paused for AI redesign · ●
2023-10-01 Construction startedConstruction resumes with the AI design · ●
2026-09-03 First powerServing traffic (Meta) · ●

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2022-10-03—Land clearing begins.
2026-03-15—Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Construction has started on 2 smaller buildings to the north. Meta announced the arrival of the first server rack the foll
2026-06-01152 MWBuilding 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Official Pamphlet from Meta · Application for Power Purchase Agreement, Pleasant Valley Solar 1  · Application for Power Purchase Agreement, Pleasant Valley Solar 2 · Approval to move start date of Solar 2 to May 31, 2026 · staff comments · Notice of Application for 3rd PPA (Blacks Creek Energy Center)

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id meta-kuna; include the row and a source link).