OpenAI Stargate Michigan · Saline Township, MI

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerOracle
UsersOpenAI
IT power, end of 20260 MW
Planned end state988 MW
First power2028-12-31 (est.)
Build-out complete2028-12-31 (est.)
Power pathGrid supply
Binding step Grid interconnection (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedon time (announced 2028-12-31)
Utility / power partnersDTE Electric

Latest: Completion (projected Q4 2028) · Full build-out complete · 2028-12-31 (plan) · recorded 2026-10-04

Related Digital's $16bn campus in Saline Township for Oracle/OpenAI: three 550,000 sq ft buildings, an 80,000 sq ft core building and two dedicated substations; 1.4 GW from DTE under 19-year contracts the MPSC conditionally approved 3-0 on 2025-12-18 (under appeal). Full construction from Q1 2026; by April 2026 major construction was underway and financing secured. The state allowed construction before the final air-quality permit. · source ◐ secondary, confidence medium

Recorded readiness — 4 of 5 applicable milestones have a dated public record

● Land 2025-10● Permits 2026-02● Grid supply 2025-12· Generation○ Water· Financing● Construction 2026-03

Gate to first power — target unknown · path: Grid supply · each step must finish its lead time before the target

1 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)— (15 mo before)13 mo before (n=26)2025-10-30contextAnnounced as the largest investment in Michigan history · ◐
Permits in hand (context)— (0 mo before)4 mo after (n=8)2026-02-15contextConstruction allowed ahead of the final air-quality permit; wetlands permits · ◐
Grid supply agreed— (9 mo before)7 mo before (n=11)2025-12-18contextMPSC approves DTE 1.4 GW contracts · ◐
Substation and lines energized— (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by —No date on record
Construction started (context)— (24 mo before)29 mo before (n=15)2026-03-01contextConstruction start (planned early 2026) · ◐
Building ready for IT— (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by —No date on record
Full build-out complete (context)— (-12 mo before)—2028-12-31 plancontextCompletion (projected Q4 2028) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-10-30 Site securedAnnounced as the largest investment in Michigan history · ◐
2025-12-18 Grid supply agreedMPSC approves DTE 1.4 GW contracts · ◐
2026-02-15 Permits in handConstruction allowed ahead of the final air-quality permit; wetlands permits · ◐
2026-03-01 Construction startedConstruction start (planned early 2026) · ◐
2026-04-25 Construction startedMajor construction underway; financing secured · ◐
2026-06-01 Construction startedConstruction equipment and fencing on the Saline Township site · ◐
2028-12-31 plan Full build-out completeCompletion (projected Q4 2028) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-12-04—Land clearing begins for the entire site
2026-01-20—Land clearing continues for all buildings (1-3)
2026-03-12—Groundwork is visible for Building 1, at the left end of the site.
2028-12-31 est.988 MWBuildings 1-3 operational. Based on when maximum power load will be provided by DTE energy (Dec 2027), which can be extended by a year. [Source, page 3](https://mi-psc.my.site.com/sfc/servlet.shepherd/version/download/06

Recorded fact No public date for substation and lines energized, building ready for it.

Calculated requirement No first-power target on record, so no deadlines can be computed.

Sources (Epoch AI selection): Related Digital website for this site · Michigan Public Service Commission Energy Contract Approval, reports 1,383 MW as the site capacity · Air Permitting, calls the site Project Mitten, includes site map · DTE Electric’s contract approval · Website with more details for locals about the site

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id openai-stargate-michigan; include the row and a source link).