Anthropic Barber Lake · Mitchell County, TX

Last change recorded 2026-10-05 · Last checked 2026-10-04

OwnerCipher Mining
UsersAnthropic
IT power, end of 2026168 MW (est.)
Planned end state207 MW
First power2026-12-30 (est.)
Build-out complete2027-04-30 (est.)
Power pathGrid supply
Binding step Building ready for IT (computed)
First power vs announced+3 months (announced 2026-09-30)
Full build-out vs announced+3 months (announced 2027-01-31)
Utility / power partnersOncor (ERCOT) (verify)

Latest: Cipher's Barber Lake contracted revenue above $9bn after a second ten-year lease commitment (reported September 2026) · Financing closed · 2026-09-15 · recorded 2026-10-05

Cipher Digital's Barber Lake site near Colorado City (ERCOT). Fluidstack for Anthropic: 168 MW (September 2025) plus 39 MW (November 2025), extended in late September 2026 to 300 MW and 20 years ($9bn contracted). Cipher also signed a 15-year AWS lease on 2025-10-29 for 300 MW to be delivered in 2026 at another site. Phase 1 (168 MW) targeted for 2026-09-30 and phase 2 (39 MW) for 2027-01-31. · source ◐ secondary, confidence medium

Recorded readiness — 2 of 6 applicable milestones have a dated public record

● Land 2025-09○ Permits○ Grid supply· Generation○ Water● Financing 2026-09◐ Construction

Gate to first power — target 2026-09-30 (announced) · path: Grid supply · each step must finish its lead time before the target

1 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-06-28 (15 mo before)13 mo before (n=26)2025-09-01context168 MW lease signed · ◐
Grid supply agreed2025-12-28 (9 mo before)7 mo before (n=11)no public dateno public date · would need to be done by 2025-12-28No date on record
Substation and lines energized2026-07-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2026-07-28No date on record
Building ready for IT2026-09-28 (0 mo before)2 mo after (n=7)2027-03-31 planplan 6 mo past the deadlineData halls delivered to Fluidstack in phases from Q4 2026 through Q1 2027 (slightly later than planned); a second ten-year lease by an AI lab from Q4 2026 · ◐
Full build-out complete (context)2027-09-28 (-12 mo before)—2027-01-31 plancontextPhase 2 delivery target (39 MW) · ◐
Financing closed (context)2025-09-28 (12 mo before)12 mo before (n=2)2026-09-15contextCipher's Barber Lake contracted revenue above $9bn after a second ten-year lease commitment (reported September 2026) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-09-01 Site secured168 MW lease signed · ◐
2025-11-12 Site secured39 MW expansion signed · ◐
2026-09-15 Financing closedCipher's Barber Lake contracted revenue above $9bn after a second ten-year lease commitment (reported September 2026) · ◐
2026-09-25 Site securedFluidstack lease extended to 300 MW and 20 years · ◐
2026-09-30 First powerPhase 1 delivery target (168 MW) · ◐
2026-12-30 plan First powerFirst power (Epoch estimate) · ◐
2027-01-31 plan Full build-out completePhase 2 delivery target (39 MW) · ◐
2027-03-31 plan Building ready for ITData halls delivered to Fluidstack in phases from Q4 2026 through Q1 2027 (slightly later than planned); a second ten-year lease by an AI lab from Q4 2026 · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-09-18—Site grading and civil works begin.
2025-11-29—Foundations of Building 1 are visible.
2026-07-30—Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov
2026-12-30 est.168 MWBuilding 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely). We estimate ~Dec 2026, about 3 months later than the disclosed target, because the si
2027-04-30 est.207 MWBuilding 1 Phase II is operational: 207 MW total critical IT (300 MW gross). Phase II adds 39 MW critical IT (see [Cipher 2025-11-20 PR](https://www.globenewswire.com/news-release/2025/11/20/3191801/0/en/Cipher-Mining-Si

Recorded fact building ready for it has a recorded date later than the rule-based deadline for a 2026-09-30 first power.

Calculated requirement Grid supply agreed must finish by 2025-12-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2027-03-28 (6 mo after the announced target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Cipher signs 168 MW AI hosting deal with Fluidstack, Google backs it (Sep 2025) · Cipher adds 56 MW gross to reach 300 MW at Barber Lake (Nov 2025) · Cipher 8-K exhibit: 207 MW total critical IT load (SEC, Nov 2025) · Anthropic to expand use of Google Cloud TPUs (Oct 2025) · Anthropic $50B US AI infrastructure with Fluidstack (Nov 2025) · DCD: Cipher secures Fluidstack as customer, Google as investor

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id anthropic-barber-lake; include the row and a source link).