CoreWeave Muskogee OK · Muskogee, OK

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerCoreWeave
UsersOpenAI
IT power, end of 202670 MW (est.)
Planned end state153 MW
First power2026-12-31 (est.)
Build-out complete2027-12-31 (est.)
Power pathGrid supply
Binding step Construction (from reporting)
First power vs announced+6 months (announced 2026-06-30)
Full build-out vs announcedNo announced date on record
Utility / power partnersOklahoma Gas & Electric

Latest: Second 82.5 MW building initial delivery (Q4 2027) · Full build-out complete · 2027-12-31 (plan) · recorded 2026-10-04

Core Scientific's Muskogee campus: the leased 70 MW GB300 building was in final testing for Q2 2026 delivery; a second 82.5 MW building is due Q4 2027. Core Scientific is buying Polaris DS (bitcoin miner) with 440 MW of OG&E service, an on-site substation and 40 adjacent acres, to scale the campus toward 1.5 GW gross. · source ● primary, confidence high

Recorded readiness — 2 of 6 applicable milestones have a dated public record

○ Land○ Permits● Grid supply 2024-11· Generation○ Water○ Financing● Construction 2024-11

Gate to first power — target 2026-06-30 (announced) · path: Grid supply · each step must finish its lead time before the target

2 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Grid supply agreed2025-09-28 (9 mo before)7 mo before (n=11)2024-11-15on record in timeOG&E service for the 100 MW site at groundbreaking · ●
Substation and lines energized2026-04-28 (2 mo before)15 mo after (n=1)2026-05-31on record in time70 MW building in final testing and commissioning (Q2 2026) · ●
Construction started (context)2024-06-28 (24 mo before)29 mo before (n=15)2024-11-15contextGround broken (November 2024) · ◐
Building ready for IT2026-06-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2026-06-28No date on record
Full build-out complete (context)2027-06-28 (-12 mo before)—2027-12-31 plancontextSecond 82.5 MW building initial delivery (Q4 2027) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-11-15 Construction startedGround broken (November 2024) · ◐
2024-11-15 Grid supply agreedOG&E service for the 100 MW site at groundbreaking · ●
2026-05-31 Substation and lines energized70 MW building in final testing and commissioning (Q2 2026) · ●
2026-06-30 First power70 MW building delivery (planned Q2 2026) · ◐
2026-08-01 Grid supply agreedPolaris acquisition adds 440 MW OG&E service and an on-site substation · ●
2026-12-31 plan First powerFirst power (Epoch estimate) · ◐
2027-12-31 plan Full build-out completeSecond 82.5 MW building initial delivery (Q4 2027) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-11-18—Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center. Core Scientific [says](https://investors.corescientific.com/news-events/press-releases/detail/99/cor
2026-04-09—Based on satellite imagery, Building 1 looks mostly complete, but the site still appears to be in construction or commissioning. Not much progress has happened in the past 4 months, and a Q2 2026 finish seems unlikely.
2026-06-13—Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard
2026-12-31 est.70 MWEstimating building 1 is operational by the end of the year, judging from the building currently completed, the completed power substation to the southwest. The surrounding yard work/construction will likely still take s
2027-12-31 est.153 MWCore Scientific expects initial delivery of the second, unleased 82.5 MW Muskogee building in Q4 2027. Not signed to have CoreWeave GPUs as of yet, but may change in the future. Source: https://www.sec.gov/Archives/edgar

Recorded fact No public date for building ready for it.

Calculated requirement Building ready for IT must finish by 2026-06-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2026-07-28 (1 mo after the announced target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Core Scientific ground breaking announcement · Port Muskogee ground breaking announcement · Air quality permit application

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id coreweave-muskogee-ok; include the row and a source link).