CoreWeave Ellendale ND · Ellendale, ND

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerCoreWeave
UsersOpenAI
IT power, end of 202688 MW (est.)
Planned end state400 MW
First power2025-10-27
Build-out complete2027-06-01 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedon time (announced 2027-12-31)
Utility / power partnersOtter Tail / Dakota Valley (territory estimate) (verify)

Latest: Full 400 MW (Epoch estimate) · Building ready for IT · 2027-06-01 (plan) · recorded 2026-10-04

Applied Digital Polaris Forge 1, 400 MW critical IT leased to CoreWeave for 15 years. Construction from 2022-09-08. Building 1: first 50 MW ready October 2025, full 100 MW on 2025-11-24. Building 2 phase 1 (75 MW) ready 2026-07-01; 250 MW operational by October 2026. Third 150 MW building slated for 2027. · source ◐ secondary, confidence high

Recorded readiness — 1 of 6 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water○ Financing● Construction 2022-09

Gate to first power — target 2025-10-27 (estimate) · path: Grid supply · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Construction started (context)2023-10-27 (24 mo before)29 mo before (n=15)2022-09-08contextConstruction starts · ◐
Building ready for IT2025-10-27 (0 mo before)2 mo after (n=7)2027-06-01 planplan 19 mo past the deadlineFull 400 MW (Epoch estimate) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2022-09-08 Construction startedConstruction starts · ◐
2025-10-27 First powerFirst 50 MW ready for service · ◐
2025-11-24 First powerBuilding 1 fully energized (100 MW) · ◐
2026-07-01 First powerBuilding 2 phase 1 ready (75 MW) · ◐
2027-06-01 plan Building ready for ITFull 400 MW (Epoch estimate) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2023-10-31—Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave was not leased yet a
2025-05-28—CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) from this date.
2025-08-29—[A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project is now clearly sche
2025-10-2750 MWThe first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-for-service-for-phase
2025-11-2468 MW[This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready for Service, bringi
2026-03-2768 MWAccording to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, though it's very safe
2026-06-3068 MWAccording to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid
2026-12-31 est.88 MWAccording to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the second half of 2026. We
2027-06-01 est.400 MWAccording to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2027. That would brin

Recorded fact building ready for it has a recorded date later than the rule-based deadline for a 2025-10-27 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Applied Digital Announces 250MW AI Data Center Lease With CoreWeave · SEC 8k Filing with Applied Digital · Applied Digital Delivers Second Building at Polaris Forge 1

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id coreweave-ellendale-nd; include the row and a source link).