Google Cedar Rapids · Cedar Rapids, IA

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerGoogle
UsersGoogle DeepMind
IT power, end of 202687 MW (est.)
Planned end state261 MW
First power2026-12-31 (est.)
Build-out complete2027-05-23 (est.)
Power pathGrid supply
Binding step 1 required step without a date
First power vs announcedon time (announced 2026-12-31)
Full build-out vs announcedNo announced date on record
Utility / power partnersAlliant Energy

Latest: First power (Epoch estimate) · First power · 2026-12-31 (plan) · recorded 2026-10-04

Google's Big Cedar campus (about $576m, at least four buildings) next to QTS; the phase under construction is expected to complete in 2026. Served by Alliant Energy, which owns the park; Google also partnered on the Duane Arnold nuclear restart in Iowa. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 5 applicable milestones have a dated public record

● Land 2025-06○ Permits● Grid supply 2025-06· Generation○ Water· Financing● Construction 2025-06

Gate to first power — target 2026-12-31 (announced) · path: Grid supply · each step must finish its lead time before the target

2 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-09-28 (15 mo before)13 mo before (n=26)2025-06-04contextGoogle confirmed at Big Cedar · ●
Grid supply agreed2026-03-28 (9 mo before)7 mo before (n=11)2025-06-04on record in timeAlliant Energy announces the Google project at Big Cedar (utility-owned park with 1 GW) · ●
Substation and lines energized2026-10-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2026-10-28No date on record
Construction started (context)2024-12-28 (24 mo before)29 mo before (n=15)2025-06-01contextExcavation and cranes across the site (summer 2025) · ◐
Building ready for IT2026-12-28 (0 mo before)2 mo after (n=7)2026-12-31 planplan inside the deadlineCurrent phase complete (2026) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-06-01 Construction startedExcavation and cranes across the site (summer 2025) · ◐
2025-06-04 Site securedGoogle confirmed at Big Cedar · ●
2025-06-04 Grid supply agreedAlliant Energy announces the Google project at Big Cedar (utility-owned park with 1 GW) · ●
2026-12-31 plan First powerFirst power (Epoch estimate) · ●
2026-12-31 plan Building ready for ITCurrent phase complete (2026) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-06-14—Land clearing begins.
2025-10-27—Building 1 cooling towers and generators starting to be put in place. There's a foundation for Building 2 and 3.
2025-12-29—About half of Building 1 generators are in place. Building 2 roofing has started - about where Google Omaha Building 3 was on 2025-03-16.
2026-04-16—Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers a
2026-12-31 est.87 MWBuilding 1 is operational. There is still work to be done since April, and Q4 2026 operational estimate was based on visible progress then.
2027-02-22 est.174 MWBuilding 2 is operational. Based on Google Omaha Building 3 taking about 14 months from starting the roof to operation.
2027-05-23 est.261 MWBuilding 3 is operational. Earlier satellite images suggest it was about 3 months behind Building 2.

Recorded fact No public date for substation and lines energized.

Calculated requirement Substation and lines energized must finish by 2026-10-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2026-12-31 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): MISO new load announcements · Permit application

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id google-cedar-rapids; include the row and a source link).