Vantage TX1 · San Antonio, TX

Last change recorded 2026-10-04 · Last checked 2026-10-04

Owner—
Users—
IT power, end of 202632 MW
Planned end state128 MW
First power2026-02-15
Build-out complete2027-08-31 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersCPS Energy

Latest: TX12 estimated operational (Epoch) · Full build-out complete · 2027-08-31 (plan) · recorded 2026-10-04

Vantage San Antonio campus served by CPS Energy (100-250 MW in the interconnection tracker). TX11 (32 MW) was set to go live in early 2026; TX12 (up to 96 MW) is filed. · source ◐ secondary, confidence medium

Recorded readiness — 0 of 6 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water○ Financing○ Construction

Gate to first power — target 2026-02-15 (estimate) · path: Grid supply · each step must finish its lead time before the target

0 of 0 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Full build-out complete (context)2027-02-15 (-12 mo before)—2027-08-31 plancontextTX12 estimated operational (Epoch) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2026-02-15 First powerTX11 first power (Epoch) · ◐
2027-08-31 plan Full build-out completeTX12 estimated operational (Epoch) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2023-12-15—Land clearing begins for both Building 1 & Building 2
2026-02-1532 MWBuilding 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based
2027-08-31 est.128 MWEstimated construction completion date of Building 2. [Construction Project Filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026001234)

Recorded fact The site is energized.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Construction Permitting for TX11 · Construction Permitting for TX12 · Air quality permitting that references TX13

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id vantage-tx1; include the row and a source link).