OpenAI Stargate Lordstown · Warren, OH

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerSoftbank
UsersOpenAI
IT power, end of 20260 MW
Planned end state214 MW
First power2027-03-01 (est.)
Build-out complete2027-03-01 (est.)
Power pathGrid supply
Binding step 1 required step without a date
First power vs announcedannounced 2026-12-31; current estimate not confirmed
Full build-out vs announcedNo announced date on record
Utility / power partnersOhio Edison (FirstEnergy) (verify)

Latest: First power (Epoch estimate) · First power · 2027-03-01 (plan) · recorded 2026-10-04

SoftBank site at the former GM/Foxconn plant in Warren, Ohio, retooled to make AI servers with a data center alongside; grid supply through the plant's existing substation. Imagery from 2026-07-30 shows active construction with roofing mostly in place and no building operational. Epoch projects 214 MW IT in Q1 2027; SoftBank's original target was 2026. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2025-09○ Permits● Grid supply 2025-09· Generation○ Water○ Financing● Construction 2025-10

Gate to first power — target 2026-12-31 (announced) · path: Grid supply · each step must finish its lead time before the target

2 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-09-28 (15 mo before)13 mo before (n=26)2025-09-23contextSite announced; ground broken · ●
Grid supply agreed2026-03-28 (9 mo before)7 mo before (n=11)2025-09-23on record in timeExisting plant substation provides grid supply (no new interconnection reported) · ◐
Substation and lines energized2026-10-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2026-10-28No date on record
Construction started (context)2024-12-28 (24 mo before)29 mo before (n=15)2025-10-01contextSite preparation begins · ◐
Building ready for IT2026-12-28 (0 mo before)2 mo after (n=7)2026-07-30on record in timeRoofing mostly in place, no building operational (imagery) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-09-23 Site securedSite announced; ground broken · ●
2025-09-23 Grid supply agreedExisting plant substation provides grid supply (no new interconnection reported) · ◐
2025-10-01 Construction startedSite preparation begins · ◐
2026-07-30 Building ready for ITRoofing mostly in place, no building operational (imagery) · ◐
2026-09-30 Construction startedData center foundation work expected Q3 2026; Epoch imagery shows cleared land but no large-scale construction · ◐
2027-03-01 plan First powerFirst power (Epoch estimate) · ●

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-10-12—Land clearing begins in the front of the site (the side facing the Ohio Turnpike), clearing away a parking lot and solar array
2026-02-27—Still no visible construction, although construction within preexisting facilities
2026-07-30—Active construction visible on and around the datacenter, with the roofing mostly in place. This is based on satellite imagery. No buildings operational yet.
2027-03-01 est.214 MWProjected operational date. OpenAI [stated](https://openai.com/index/five-new-stargate-sites/) Lordstown and Milam County could scale to 1.5 GW within 18 months of their September 23, 2025 announcement; subtracting Milam

Recorded fact No public date for substation and lines energized.

Calculated requirement Substation and lines energized must finish by 2026-10-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2026-12-31 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): Announcement of 5 new Stargate sites mentioning Lordstown · Water Quality Permitting stating that “manufacturing and assembly” is the main purpose of the construction · Stormwater Permitting

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id openai-stargate-lordstown; include the row and a source link).