Stream Phoenix · Goodyear, AZ

Last change recorded 2026-10-04 · Last checked 2026-10-04

Owner—
Users—
IT power, end of 202664 MW
Planned end state220 MW
First power2026-05-01
Build-out complete2030-01-01 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersArizona Public Service

Latest: Phoenix IV (planned 2029) · Building ready for IT · 2029-12-31 (plan) · recorded 2026-10-04

Stream Data Centers' Goodyear campus: up to 2 million sq ft and 280 MW critical load at full build-out, fed from an on-site 350 MW APS substation. Phoenix IV is planned for 2029. · source ◐ secondary, confidence medium

Recorded readiness — 0 of 6 applicable milestones have a dated public record

○ Land○ Permits○ Grid supply· Generation○ Water○ Financing◐ Construction

Gate to first power — target 2026-05-01 (estimate) · path: Grid supply · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Building ready for IT2026-05-01 (0 mo before)2 mo after (n=7)2029-12-31 planplan 44 mo past the deadlinePhoenix IV (planned 2029) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2026-05-01 First powerFirst power of the tracked expansion (Epoch) · ◐
2029-12-31 plan Building ready for ITPhoenix IV (planned 2029) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2022-10-30—Construction beginning, as can be seen on satellite. Major renovations on western side of the non AI building (PX1), including adding generators and cooling towers.
2026-01-31—Major construction has finished on AI building 1, and AI building 6 has been expedited, as depicted by satellite imagery.
2026-05-0164 MWEstimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.
2030-01-01 est.220 MWAlthough official [promotional sources](https://www.streamdatacenters.com/wp-content/uploads/2026/01/SDC-Goodyear-CaseStudy-251218.pdf) estimate the campus to be fully operational in 10-12 years, it is likely to be finis

Recorded fact building ready for it has a recorded date later than the rule-based deadline for a 2026-05-01 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Official page for the data center. · Official pre-construction planning document.

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id stream-phoenix; include the row and a source link).