Coreweave Helios · Afton (Dickens County), TX

Last change recorded 2026-10-05 · Last checked 2026-10-04

OwnerCoreWeave
UsersOpenAI
IT power, end of 2026132 MW
Planned end state528 MW
First power2026-08-30
Build-out complete2029-01-01 (est.)
Power pathGrid supply
Binding step Grid interconnection (from reporting)
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record

Latest: Galaxy closes a $1.4bn debt facility for the Helios campus · Financing closed · 2025-08-15 · recorded 2026-10-05

Galaxy Digital's Helios campus in Dickens County, leased in full to CoreWeave (about 800 MW gross, 526 MW critical IT across three phases, 15 years). $1.4bn project financing closed August 2025. ERCOT approved 830 MW after a large-load interconnection study in January 2026; a further 2.7 GW is under study. Phase I (133 MW IT) was delivered with rent starting Q2 2026; Phase II (260 MW IT) in development. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2025-08○ Permits● Grid supply 2026-01· Generation○ Water● Financing 2025-08○ Construction

Gate to first power — target 2026-08-30 (estimate) · path: Grid supply · each step must finish its lead time before the target

1 of 1 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-05-28 (15 mo before)13 mo before (n=26)2025-08-15context$1.4bn project financing closed · ◐
Grid supply agreed2025-11-28 (9 mo before)7 mo before (n=11)2026-01-15recorded 2 mo after the deadlineERCOT approves 830 MW large-load interconnection · ◐
Full build-out complete (context)2027-08-28 (-12 mo before)—2029-01-01 plancontextPhase II at full capacity (Epoch estimate) · ◐
Financing closed (context)2025-08-28 (12 mo before)12 mo before (n=2)2025-08-15contextGalaxy closes a $1.4bn debt facility for the Helios campus · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-08-15 Site secured$1.4bn project financing closed · ◐
2025-08-15 Financing closedGalaxy closes a $1.4bn debt facility for the Helios campus · ◐
2026-01-15 Grid supply agreedERCOT approves 830 MW large-load interconnection · ◐
2026-06-30 First powerPhase I (133 MW IT) delivered, rent starts Q2 2026 · ◐
2029-01-01 plan Full build-out completePhase II at full capacity (Epoch estimate) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-05-31—The former [crypto mining](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Commitment-with-CoreWeave-to-Host-Additional-Artificial-Intelligence-and-High-Performance-Computing-Infrastructure-at-Helios-
2025-08-27—Backup generator pads and steel framing for chillers are visible, similar to the [3D renderings](https://www.galaxy.com/data-centers).
2026-04-04—Building 1 appears substantially complete. The main white-roofed data hall is visible with exterior mechanical/electrical equipment rows installed on both sides, and adjacent generator/equipment pads plus laydown yards a
2026-06-17—Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave li
2026-08-30132 MWBuilding 1 operational at full capacity. This is based on "Phase I", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be operat
2028-01-01 est.396 MWBuilding 2 and 3 are operational at full capacity. This corresponds to "Phase II", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx
2029-01-01 est.528 MWBuilding 4 operational at full capacity. This corresponds to "Phase III", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be d

Recorded fact grid supply agreed has a recorded date later than the rule-based deadline for a 2026-08-30 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Galaxy Q3 financial results with power capacity timeline · Permit review with details on backup generators and power capacity · 3D renderings of Helios Building 1 on Galaxy's website, showing generators and chillers · TDLR record with Building 1 construction costs and end date

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id coreweave-helios; include the row and a source link).