Nebius Mantsala · Mäntsälä, Finland

Last change recorded 2026-10-04 · Last checked 2026-10-04

OwnerNebius
UsersMicrosoft
IT power, end of 202675 MW
Planned end state145 MW
First power2024-10-08
Build-out complete2027-12-31 (est.)
Power pathGrid supply
Binding stepNo data yet
First power vs announcedNo announced date on record
Full build-out vs announcedNo announced date on record
Utility / power partnersFingrid; Caruna (territory estimate) (verify)

Latest: Second Mäntsälä site first capacity (planned 2027) · First power · 2027-12-31 (plan) · recorded 2026-10-04

Nebius tripled Mäntsälä from 25 to 75 MW (announced October 2024, completed early 2026). A second Mäntsälä data center of up to 70 MW was announced in August 2026 for 2027; Caverion is building its 70 MW substation (about €15m) for autumn 2027. A separate 310 MW AI factory is planned in Lappeenranta from 2027. · source ◐ secondary, confidence medium

Recorded readiness — 2 of 6 applicable milestones have a dated public record

● Land 2024-10○ Permits◐ Grid supply· Generation○ Water○ Financing● Construction 2026-03

Gate to first power — target 2024-10-08 (estimate) · path: Grid supply · each step must finish its lead time before the target

2 of 2 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2023-07-08 (15 mo before)13 mo before (n=26)2024-10-08contextExpansion to 75 MW announced · ◐
Grid supply agreed2024-01-08 (9 mo before)7 mo before (n=11)2027-10-31 planplan 46 mo past the deadline70 MW substation for the second site (autumn 2027) · ◐
Building ready for IT2024-10-08 (0 mo before)2 mo after (n=7)2026-03-31recorded 18 mo after the deadline75 MW complete (early 2026) · ◐

This site is energized; lights only show how its recorded steps compared with the lead times.

Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2024-10-08 Site securedExpansion to 75 MW announced · ◐
2026-03-31 Building ready for IT75 MW complete (early 2026) · ◐
2026-08-13 Site securedSecond Mäntsälä data center (up to 70 MW from 2027) announced; Caverion €15m substation due autumn 2027; site total 145 MW · ◐
2027-10-31 plan Grid supply agreed70 MW substation for the second site (autumn 2027) · ◐
2027-12-31 plan First powerSecond Mäntsälä site first capacity (planned 2027) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2024-10-0840 MW[Nebius announces expansion of Mantsala campus to 75MW.](https://nebius.com/newsroom/nebius-to-triple-capacity-at-finland-data-center-to-75-mw)
2025-11-1440 MWSatellite imagery suggests that installation of the cooling units is finalizing on the expansion building. Construction equipment remains around the site. We do not believe the building is operational at this point.
2026-03-3175 MW[Nebius announces that the expansion to 75MW is operational at the beginning of 2026.](https://nebius.com/newsroom/nebius-to-construct-310-mw-ai-factory-in-finland)
2026-06-2975 MWAll three buildings in the first phase are operational.
2027-12-31 est.145 MW[According to company estimates, the second expansion of 70MW will be complete by the end of 2027.](https://www.linkedin.com/posts/at-earnings-we-said-nebius-is-expanding-its-share-7493603318020370433-hkGo/?utm_source=sh

Recorded fact grid supply agreed, building ready for it have a recorded date later than the rule-based deadline for a 2024-10-08 first power.

Calculated requirement Energized; watch the build-out timeline for the next buildings.

Sources (Epoch AI selection): Nebius to triple capacity of Mantsala campus to 75 MW · Nebius announcing deployment of first GB300 NVL72 systems in Europe

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id nebius-mantsala; include the row and a source link).