AILoadmapAI gigawatts, campus by campus
← Map · All projects

QTS Cedar Rapids · Fairfax, IA

Last change recorded 2026-10-04 · Last checked 2026-10-04

Owner—
Users—
IT power, end of 2026448 MW (est.)
Planned end state1.1 GW
First power2026-11-15 (est.)
Build-out complete2027-11-15 (est.)
Power pathGrid supply
Binding step 1 required step without a date
First power vs announcedon time (announced 2026-12-31)
Full build-out vs announcedNo announced date on record
Utility / power partnersAlliant Energy

Latest: First phase complete (late 2026, QTS) · Building ready for IT · 2026-12-15 (plan) · recorded 2026-10-04

QTS campus on 612 acres of Alliant Energy's Big Cedar Industrial Center, up to seven buildings and $10bn. Alliant provides 1 GW with 161 kV and 69 kV lines and a proposed 345 kV line. First three buildings topped out on 2025-10-21; QTS said in July 2026 the first phase would complete in late 2026, the second in 2027. · source ◐ secondary, confidence medium

Recorded readiness — 3 of 6 applicable milestones have a dated public record

● Land 2025-02○ Permits● Grid supply 2025-02· Generation○ Water○ Financing● Construction 2025-04

Gate to first power — target 2026-12-31 (announced) · path: Grid supply · each step must finish its lead time before the target

2 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2025-09-28 (15 mo before)13 mo before (n=26)2025-02-13contextCampus confirmed by Cedar Rapids and Alliant Energy · ●
Grid supply agreed2026-03-28 (9 mo before)7 mo before (n=11)2025-02-13on record in timeAlliant Energy commits 1 GW at Big Cedar (161/69 kV lines, 345 kV proposed) · ●
Substation and lines energized2026-10-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2026-10-28No date on record
Construction started (context)2024-12-28 (24 mo before)29 mo before (n=15)2025-04-01contextGround broken on the first building (spring 2025) · ◐
Building ready for IT2026-12-28 (0 mo before)2 mo after (n=7)2026-12-15 planplan inside the deadlineFirst phase complete (late 2026, QTS) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-02-13 Site securedCampus confirmed by Cedar Rapids and Alliant Energy · ●
2025-02-13 Grid supply agreedAlliant Energy commits 1 GW at Big Cedar (161/69 kV lines, 345 kV proposed) · ●
2025-04-01 Construction startedGround broken on the first building (spring 2025) · ◐
2026-11-15 plan First powerFirst power (Epoch estimate) · ●
2026-12-15 plan Building ready for ITFirst phase complete (late 2026, QTS) · ◐

Build-out timeline (Epoch AI; dated status notes with IT power; rows after today are estimates)

2025-01-17—Land clearing begins for Building 1-3.
2025-10-27—Building 1 roof complete, with air-cooled chillers in place. Building 2 and 3 roofs are partly completed. Building 4 and 5 have a foundation.
2026-04-16—Based on satellite imagery, the Buildings 1-3 shells look complete. Buildings 4-6 are far along, with roofs largely in place, while the eastern Building 7 foundation is well underway. No buildings operational yet.
2026-05-07—Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway.
2026-11-15 est.448 MWBuildings 1-3 are operational. Based on the expected completion date reported by [local news](https://corridorbusiness.com/scope-of-qts-data-project-in-cedar-rapids-continuing-to-grow/): “A QTS spokesperson said in July
2027-11-15 est.1.1 GWBuildings 4-7 are operational. Based on the expected completion date reported by [local news](https://corridorbusiness.com/scope-of-qts-data-project-in-cedar-rapids-continuing-to-grow/): “A QTS spokesperson said in July

Recorded fact No public date for substation and lines energized.

Calculated requirement Substation and lines energized must finish by 2026-10-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2026-12-31 (on the target). This is a floor set by the record, not a forecast.

Sources (Epoch AI selection): MISO new load announcements · Article by The Gazette · Article by Corridor Business Journal · Post by GLD Commercial

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row). Data retrieved 2026-10-05. Report a correction to contact@ailoadmap.com (campus id qts-cedar-rapids; include the row and a source link).