Where the AI race meets the power grid.

Tracking AI data-center campuses worldwide — what is online, what is coming, and what stands in the way.

150campuses tracked
20 GWonline today
12 GWunder construction
25 GWcommitted
39 GWproposed

95 GW in total across 28 countries · data as of 2026-11-09 · "online today" counts observed energization only, no estimates · stages follow the evidence on record (Method) · tracked campuses, not the whole market

Colour· size = IT power at the end of the selected year

150 campuses tracked · 22.9 GW of IT power at the end of 2026 · hover for details, click to open. Circles for sites not yet energized are hollow.

Meta ByteDance Google Wonder Valley Amazon Microsoft Oracle / Stargate Scala OpenAI Elea Stock Farm Road (Haenam) Anthropic Syncline Energy Envision IREN xAI Reliance CDC Mistral AI / MGX (Paris) YTL Power Bell QTS (Blackstone) Otherscolour = hyperscaler, or any operator with 1 GW+ planned
Filter by operator (click to toggle, double-click to keep only one)
Observed or announced Estimated (Epoch AI or plan)

The AI Infrastructure Race

Who is bringing AI capacity online, and where the next wave is waiting for power.

Open the full Race →
Capacity online, by region · cumulative IT GW at year end · 2023–2030
0 GW10 GW20 GW30 GW40 GW20232024202520262027202820292030today35.6 GW9.8 GW3.0 GW1.4 GW9.7 GW4.9 GW
United States (n=80) China (n=8) Europe (n=17) Middle East & Gulf (n=4) Rest of Asia (n=26) Other regions (n=15)solid = observed · dashed = Epoch AI estimates and announced plans · each line ends where its announced plans end
Tracked campuses only. Coverage differs by country; China is undercounted.Data 2026-W45 (2026-11-09) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers
Waiting for first power, by power path · planned IT GW · 61 GW across 64 campuses not yet energized · by target first-power year
2025400 MW100% grid
202613 GW68% grid
202713 GW83% grid
202818 GW50% grid
203290 MW100% grid
no date17 GW55% grid
Grid supply Grid + new utility generation Hybrid On-site generation
Tracked campuses only. Coverage differs by country; China is undercounted.Data 2026-W45 (2026-11-09) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers

Epoch AI, 'AI data centers', epoch.ai/data/ai-data-centers (CC BY 4.0); coordinates from GeoNames cities500 (CC BY 4.0) and hand-entered places; overrides in tools/project_overrides.csv with their own sources. Campuses outside the Epoch dataset come from tools/campuses.csv (public reporting, source per row).

Changes since 2026-10-05 · update of 2026-11-09

23 changes since the previous update, 6 material.

CampusWhat changedFromTo
OpenAI Stargate Abilenestatusbuildingoperational
Bridge Data Centres MY06campus—added
Meta Aikenplanned MW69129
Meta Gallatinplanned MW087
Meta Gallatinstatusplannedoperational
YTL Green Data Center Park Kulaiplanned MW6001200

See all changes →

Where power is getting tight

Reported lead time · equipment, new orders, from public filings and reporting
How long the steps took · observed at tracked campuses that reached first power (calculated from the campus records)
Grid supply agreed → first power7 mo beforemedian · n=11
Construction started → first power29 mo beforemedian · n=15

Projects to watch · rule-based: first power due within six months, a required step recorded after its deadline, or an event in the last 30 days at a 1 GW+ campus

CampusCountryOperatorPlannedTarget first powerPower pathRecorded issue or change
OpenAI Stargate New MexicoUnited StatesOracle1.8 GW2026-12-31On-site generationFirst power due 2026-12 · Major equipment on site recorded after rule-based deadline · Retired federal judge James Browning appointed air-permit hearing officer after the previous officer recused · Bloom Energy fuel cell on record
Elea Rio AI CityBrazilElea Data Centers3.2 GW2026-12-31Grid supplyFirst power due 2026-12
Meta HyperionUnited StatesMeta1.6 GW2028-01-01Grid + new utility generationNew generation online recorded after rule-based deadline
Colossus 2United StatesSpaceXAI1.5 GW2025-10-19HybridAgreed order with MDEQ sets removal of all 69 temporary mobile turbines, by July 2027 on the company schedule (reported 2026-08-03)
OpenAI Stargate ShackelfordUnited StatesOracle1.4 GW2026-12-01HybridFirst power due 2026-12
QTS Cedar RapidsUnited StatesMeta1.1 GW2026-12-31Grid supplyFirst power due 2026-12
OpenAI Stargate MilamUnited StatesSoftbank857 MW2026-10-31HybridSB Energy solar on record
Racks Central Johor AI Factory CampusMalaysiaRacks Central510 MW2027-03-31Grid supplyFirst power due 2027-03

Commercial openings · what the public record does not show

Gas turbines

12 relevant campuses not yet energized · 23 GW

No supplier in public records: 11 of 12

View all opportunities → · "no supplier in public records" is a statement about the record, not a sales lead.

Public sourcesPress releases, regulatory filings, permits, court records, utility announcements, Epoch AI's satellite notes, reporting. Every dated fact links to its source.
Source tiers● primary · ◐ secondary · ○ tertiary, with a confidence level on each row. Placeholder dates say so.
Recorded vs calculatedFacts are recorded; deadlines, slip, implied first power and readiness counts are calculated by published rules. Nothing here is a forecast.
Data version2026-W45 · generated 2026-11-09. Method · Data & sources