HV breakers

Reported lead time for new orders, from public filings and reporting. This is the equipment dataset, kept separate from the campus dataset; the campus pages show what tracked campuses actually took.

Reported lead time

29 mo · Tight · trend ▲ longer than the previous observation · ◐ secondary source · data 2025H2

125 weeks — High-voltage circuit breakers (Wood Mackenzie analyst) (Reuters reprint (AJOT))

Confidence: high.

By year (a year shows a value only when it was observed in that year or the one before)

YearMonthsData dateSource
202318 mo2023◐ secondary source
202418 mo2023◐ secondary source
202529 mo2025H2◐ secondary source
202629 mo2025H2◐ secondary source

Observations on record

PeriodMetricValueNoteSource
2023lead time weeks hv breaker77 weeksHigh-voltage circuit breakers (Wood Mackenzie analyst)◐ Reuters reprint (AJOT)
2025H2lead time weeks hv breaker125 weeksHigh-voltage circuit breakers (Wood Mackenzie analyst)◐ Reuters reprint (AJOT)
2026Q2backlog eur bn siemens grid51 EUR_bnSiemens Energy Grid Technologies backlog (segment includes more than breakers/GIS)◐ Siemens Energy earnings coverage
2026Q2orders eur bn siemens grid5.4 EUR_bnSiemens Energy Grid Technologies quarterly orders (+28% YoY)◐ Siemens Energy earnings coverage

Sources

  • ◐ Reuters reprint (AJOT) · secondary, confidence high · latest 2025H2
    lead_time_weeks_hv_breaker 2023; lead_time_weeks_hv_breaker 2025H2
  • ◐ Siemens Energy earnings coverage · secondary, confidence high · latest 2026Q2
    backlog_eur_bn_siemens_grid 2026Q2; orders_eur_bn_siemens_grid 2026Q2