Gensets

Reported lead time for new orders, from public filings and reporting. This is the equipment dataset, kept separate from the campus dataset; the campus pages show what tracked campuses actually took.

Reported lead time

17–24 mo · Manageable · trend n/a · ○ tertiary source · data 2026

72-104 weeks — Diesel generators for data centers (market report; methodology unknown) (EnkiAI)

Confidence: low. Based on secondary reporting.

By year (a year shows a value only when it was observed in that year or the one before)

YearMonthsData dateSource
202617–24 mo2026○ tertiary source

Observations on record

PeriodMetricValueNoteSource
2026capacity multiple vs 2024 cat recip3 xCaterpillar large recip engine capacity to ~3x 2024 levels (turbines 2.5x)○ TIKR blog
2026lead time weeks72-104 weeksDiesel generators for data centers (market report; methodology unknown)○ EnkiAI
2026-06order book horizon cummins2028 yearDiesel recip engine order book extends to 2028; 2029 to open soon◐ Quartr summary (Cummins at Wells Fargo conf)
2026-06capacity expansion gw cummins20 GWPlanned capacity addition; USD 450M; mostly in existing plants◐ Quartr summary (Cummins at Wells Fargo conf)
2026-06price usd m per gw600 USD_million/GWReciprocating engine pricing (Cummins management)◐ Quartr summary (Cummins at Wells Fargo conf)

Sources

  • ◐ Quartr summary (Cummins at Wells Fargo conf) · secondary, confidence medium · latest 2026-06
    order_book_horizon_cummins 2026-06; capacity_expansion_gw_cummins 2026-06; price_usd_m_per_gw 2026-06
  • ○ TIKR blog · tertiary, confidence medium · latest 2026
    capacity_multiple_vs_2024_cat_recip 2026
  • ○ EnkiAI · tertiary, confidence low · latest 2026
    lead_time_weeks 2026

Source tiers: ● primary (filings, operator documents) · ◐ secondary (reporting that quotes a primary party) · ○ tertiary (aggregators, market reports of unknown method).