Gas turbines

Reported lead time for new orders, from public filings and reporting. This is the equipment dataset, kept separate from the campus dataset; the campus pages show what tracked campuses actually took.

Reported lead time

70 mo · Severe · trend ▲ longer than the previous observation · ● primary source · data 2026Q2

116 GW waiting (GE Vernova combined; guides >=125 GW by YE2026) ÷ 20 GW/yr (GE Vernova annualized output target reached in Q3 2026)

Confidence: high.

By year (a year shows a value only when it was observed in that year or the one before)

YearMonthsData dateSource
202670 mo2026Q2● primary source

How the number is made — orders waiting ÷ yearly output

GE Vernova2026 Q12026 Q2
Firm equipment backlog44 GW53 GW
Slot reservations56 GW63 GW
Backlog + reservations100 GW116 GW
Shipped in the quarter—3 GW
Annual output—20 GW/yr reached Q3 2026 · 24 (2028) · 30 (2030, announced)

The line grew by 16 GW in one quarter while 3 GW shipped. At 20 GW a year the 116 GW waiting takes about 5.8 years to clear, the ~70 months shown. Management guides to at least 125 GW by the end of 2026 (GE Vernova 8-K, primary). This is an upper estimate of "if I order today, when do I get it", because it assumes every waiting order is ahead of yours.

Makers

MakerBacklogCapacityExpansionSource
GE Vernova53 GW firm + 63 GW reserved (2026 Q2)20 GW/yr (2026 Q3)24 GW/yr 2028; 30 GW/yr 2030 announced, not committed● 8-K
Siemens Energy69 GW firm (Apr–Jun 2026); 15 GW ordered, 6 GW shipped in the quarter; book-to-bill 2.6535 large units/yr; 80 medium units/yr+15 large units planned 2027◐ earnings coverage; ● release
Mitsubishi PowerNot captured yet; the supply total is incomplete without it.—

Siemens units are not converted to GW here: the average output per unit is an assumption that has not been sourced yet.

Sources

  • ● GE Vernova 8-K · primary, confidence high · latest 2030
    backlog_gw_gev_firm 2026Q2; reservation_gw_gev 2026Q2; backlog_plus_reservation_gw_gev 2026Q1; backlog_plus_reservation_gw_gev 2026Q2; shipped_gw_gev 2026Q2; production_capacity_gw_gev 2026Q3; production_capacity_gw_gev 2028; production_capacity_gw_gev 2030
  • ○ Arkolith (citing CompressorTech2) · tertiary, confidence medium · latest 2026Q2
    sold_out_horizon_gev 2026Q2
  • ◐ Utility Dive via Energy News Beat · secondary, confidence high · latest 2026Q2
    backlog_gw_siemens_firm 2026Q2; orders_gw_siemens 2026Q2; shipped_gw_siemens 2026Q2; production_capacity_units_siemens_large 2026
  • ◐ Siemens Energy earnings coverage · secondary, confidence high · latest FY2026
    production_capacity_units_siemens_medium FY2026
  • ● Siemens Energy earnings release · primary, confidence high · latest 2026Q2
    book_to_bill_siemens_gas_services 2026Q2

Source tiers: ● primary (filings, operator documents) · ◐ secondary (reporting that quotes a primary party) · ○ tertiary (aggregators, market reports of unknown method).