Waiting for first power, US vs rest of world
56 GW of planned AI data-center capacity is waiting for first power; 22% of it is in the United States. By target year.
2025400 MWUS 0%
202613 GWUS 49%
20279.5 GWUS 25%
202817 GWUS 15%
no date17 GWUS 6%
United States Rest of world"no date" = announced without a date
Tracked campuses only. Coverage differs by country.Data 2026-W41 (2026-10-05) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers