Waiting for first power, by power path
56 GW across 61 AI data-center campuses is waiting for first power; 62% plans plain grid supply, the rest needs new or on-site generation or has no public power path.
2025400 MW100% grid
202613 GW69% grid
20279.5 GW78% grid
202817 GW53% grid
no date17 GW55% grid
Grid supply Grid + new utility generation Hybrid On-site generation
Tracked campuses only. Coverage differs by country.Data 2026-W41 (2026-10-05) · AI Loadmap · ailoadmap.com · CC BY 4.0 · Epoch AI "AI data centers" CC BY 4.0 for the campuses it covers
More charts: Capacity online, by region · Capacity online, by operator · Waiting for first power, US vs rest of world · Planned IT power, by operator · Planned IT power, by country