SK-AWS Ulsan AI Data Center · Ulsan (Mipo), South Korea

Last change recorded — · Last checked 2026-10-05

Owner—
UsersAmazon, SK Group
IT power, end of 20260 MW
Planned end state1.0 GW
First power2027-11-30 (est.)
Build-out complete2029-02-28 (est.)
Power pathGrid supply
Binding step 3 required steps without a date
First power vs announcedon time (announced 2027-11-30)
Full build-out vs announcedNo announced date on record
Utility / power partnersSK Gas (LNG CHP)

SK Group and AWS campus in the Mipo National Industrial Complex (about 7 trn won): 41 MW by November 2027, 103 MW by February 2029, sized for 60,000 GPUs; SK's chairman said in September 2026 the expansion plan is nearing 900 MW. Sited next to SK Gas's LNG combined heat and power plant. Groundbreaking 2025-08-29; operation from the second half of 2027. · source ◐ secondary, confidence high

Recorded readiness — 2 of 6 applicable milestones have a dated public record

● Land 2025-06○ Permits○ Grid supply· Generation○ Water○ Financing● Construction 2025-08

Gate to first power — target 2027-11-30 (announced) · path: Grid supply · each step must finish its lead time before the target

0 of 3 required steps have a public date. Red = recorded date past the rule-based deadline · grey "no public date" = required step without a record · green = on record in time · context steps never colour.

StepMust finish byOthers did itKnown dateStatusBasis
Site secured (context)2026-08-28 (15 mo before)13 mo before (n=26)2025-06-16contextCampus announced (reported) · ◐
Grid supply agreed2027-02-28 (9 mo before)7 mo before (n=11)no public dateno public date · would need to be done by 2027-02-28No date on record
Substation and lines energized2027-09-28 (2 mo before)15 mo after (n=1)no public dateno public date · would need to be done by 2027-09-28No date on record
Construction started (context)2025-11-28 (24 mo before)29 mo before (n=15)2025-08-29contextConstruction start (reported) · ◐
Building ready for IT2027-11-28 (0 mo before)2 mo after (n=7)no public dateno public date · would need to be done by 2027-11-28No date on record
Full build-out complete (context)2028-11-28 (-12 mo before)—2029-02-28 plancontextFull build-out (announced plan) · ◐
Lead-time assumptions
  • Site secured 15 months before first power — Land under control and campus announced. Rarely binding; shown for context.
  • Permits in hand 0 months before first power — Final air and siting permits. Operators often energize on standard or temporary authorisations and receive the major permit later; flagged only when the permit lands more than 6 months after first power or is missing for an on-site plant.
  • Grid supply agreed 9 months before first power — Interconnection or large-load agreement approved. Observed median 7 months before first power; the physical works (substation, lines) run in parallel with construction.
  • Substation and lines energized 2 months before first power — Utility delivery point live; final tests before the load is taken.
  • New generation online 1 months before first power — Utility plant or on-site plant generating; needed just before energization when the grid cannot carry the load alone.
  • Major equipment on site 6 months before first power — Turbines, transformers, switchgear delivered; installation and commissioning take the remaining months.
  • Construction started 24 months before first power — Groundbreaking of the building that gives first power. Observed 4-26 months for recent AI campuses; Meta's redesigned campuses took 35-58.
  • Building ready for IT 0 months before first power — First building ready for IT. 'Complete' or 'opened' is usually reported after first power; flagged only beyond 3 months.
  • Full build-out complete -12 months before first power — All announced buildings operational. Comes after first power by design; context only.
  • Water supply secured 12 months before first power — Water rights, municipal agreement or desalination contract in hand. Context only; one of the feasibility items.
  • Financing closed 12 months before first power — Project financing, anchor lease or committed capital announced. Context only; not applicable when the owner is a hyperscaler building on its balance sheet.

Dated steps (from the sources; later dates are plans)

2025-06-16 Site securedCampus announced (reported) · ◐
2025-08-29 Construction startedConstruction start (reported) · ◐
2027-11-30 plan First powerFirst phase online (announced plan) · ◐
2029-02-28 plan Full build-out completeFull build-out (announced plan) · ◐

Build-out timeline (announced phases from public reporting; rows after today are plans)

2027-11-30 est.41 MWFirst phase online (announced plan)
2029-02-28 est.1.0 GWFull build-out (announced plan)

Recorded fact No public date for grid supply agreed, substation and lines energized, building ready for it.

Calculated requirement Grid supply agreed must finish by 2027-02-28; no public date is on record for it. Under the current rule set the recorded dates plus their lead times give a first power no earlier than 2027-11-30 (on the target). This is a floor set by the record, not a forecast.